Or. Admin. Code § 952-001-0040 - Pre-Marking Required by the Excavator; Exemption

(1) Except as provided in paragraph (2) of this rule, prior to notifying the Oregon Utility Notification Center, an excavator shall pre-mark with the color white the immediate area of the proposed excavation within both the public rights-of-way and underground easements.
(2) An excavator need not pre-mark as required in paragraph (1) of this rule if:
(a) The operator can determine precisely the direction, length and location of the proposed excavation by referring to a locate ticket; or
(b) The excavator and operator have had a meeting prior to the beginning of the proposed project, at the construction site for the exchange of information required under paragraph (1) of this rule.

Notes

Or. Admin. Code § 952-001-0040
OUNC 1-1997, f. & cert. ef. 4-17-97

Stat. Auth.: Sec. 1 - 5 & 7, Ch. 691, OL 1995

Stats. Implemented:

State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.


No prior version found.