22 Pa. Code § 349.12 - Public hearings on school projects, district
(a)
Adoption of costs. The
board of directors shall adopt a maximum project cost and a maximum building
construction cost prior to the scheduling of a hearing:
(b)
Notice. Notice of the
hearing shall be published at least 20 days in advance of the hearing in
accordance with section 106 of the Public School Code of 1949 (24 P. S. §
1-106). The notice shall include:
(1) The date, the time, and location of the
hearing;
(2) The type of facility
to be constructed;
(3) The maximum
project cost;
(4) The maximum
building construction cost;
(5) The
availability of a description of the project;
(6) The manner by which a resident may gain
agenda time or submit written testimony, or both; and
(7) such other information as is deemed
necessary by the board.
(c)
Nature The board hearing
shall be in the nature of a legislative hearing to receive public comment and
shall not be considered an adjudication within the meaning of the Local Agency
Law (53 P.S. §§
11301-11311).
(d)
New hearing. If, as a
result of the hearing, the board decides to modify the size or design of a
project, a new hearing shall not be required unless the changes are based on a
different use for the project, for example, elementary to middle school.
Nothing in this section shall prevent the board from holding additional
hearings if it so desires.
(e)
Second hearing. If, in accordance with the mandates of
sections 701.1, 731, 733, and 735 of the
Public School Code of 1949 (24 P. S. §§
7-701.1,
7-731,
7-733 and
7-735), a second public
hearing is required because the building construction cost upon receipt of bids
exceeds by 8.0% or more the estimated costs first submitted to the Department,
that hearing shall be properly published in accordance with section 106 of the
Public School Code of 1949 (24 P. S. §
1-106). Nothing in this subsection shall be
construed as preventing the board from advertising such hearing prior to
receipt of bids and convening a hearing regardless of the status of the project
building construction cost based upon bids.