25 Pa. Code § 103.43 - Information required
The following information shall be submitted in triplicate with all requests for reimbursement:
(1) A breakdown of the material and labor
which the constructing company used, if applicable.
(2) Copies of bills from the constructing
company to the local sponsor.
(3)
Copies of cancelled checks from the sponsor to the constructing
company.
(4) An invoice from the
sponsor to the Department.
(5) A
sketch showing original and relocated facilities.
Notes
This section cited in 25 Pa. Code § 103.42 (relating to reimbursement to local agency).
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.