25 Pa. Code § 111.14 - Phase I-scope of study
(a) A scope of
study shall include, but not be limited to, the following:
(1) A description of tasks required under
section 5 of the act (32 P. S. §
680.5), consistent with the Stormwater
Management Guidelines.
(2) A
schedule for completion of the tasks in the preparation of the detailed
watershed stormwater plan or revision.
(3) A description of the level of effort,
including personnel requirements, required to complete the tasks within each
time period.
(4) A cost estimate
for each task.
(5) A narrative of
services to be provided by consultants, if any, and a justification for the use
of consulting services, including the names of the individuals within the
consulting firm providing the services and their qualifications.
(6) A listing of outside funding sources and
the amounts of the funds.
(b) The scope of study shall also:
(1) Establish plan products that will meet
the objectives of the act.
(2)
Provide consistency in planning efforts between counties.
(3) Eliminate duplication of effort in
utilizing outside consulting services.