25 Pa. Code § 127.13 - Extensions
(a) Approval
granted by the Department will be valid for a limited time, as specified by the
Department in the approval. Except as provided in §§
127.11a and
127.215 (relating to reactivation
of sources; and reactivation), at the end of the time, if the construction,
modification, reactivation or installation has not been completed, a new plan
approval application or an extension of the previous approval will be
required.
(b) If the construction,
modification or installation is not commenced within 18 months of the issuance
of the plan approval or if there is more than an 18-month lapse in
construction, modification, or installation, a new plan approval application
that meets the requirements of this subchapter and Subchapters D and E
(relating to prevention of significant deterioration of air quality; and new
source review) shall be submitted. The Department may extend the 18-month
period upon a satisfactory showing that an extension is
justified.