25 Pa. Code § 76.61 - Construction progress reports
(a)
Written construction progress reports shall be submitted to the Department
quarterly for development and demonstration projects by the development agency,
in consultation with the designer of the plans and specifications and the
construction contractor. A more frequent progress report may be required for
some projects, if set forth in the agreement.
(b) Progress reports shall fully describe in
chart or narrative format the progress achieved in relation to the approved
schedule and project milestones. Special delays or problems shall be fully
explained. Progress reports shall be attested to by the project
engineer.