25 Pa. Code § 78.401 - Storage well construction
(a) In
addition to the casing and cementing requirements of Subchapter D (relating to
well drilling, operation and plugging), when constructing new gas storage wells
the operator shall:
(1) Cement the surface and
intermediate casings with sufficient cement to circulate cement to the surface
or to equal at least 120% of the calculated volume to fill the annular space on
the outside of the casing.
(2)
Cement the production casing with sufficient cement to fill the calculated
annular space with cement to a point at least 500 feet above the casing shoe
and at least 200 feet above the upper most perforations.
(b) Gas storage wells being reconditioned
shall meet the requirements of this section unless an alternate method of
casing and cementing has been approved by the Department under §
78.75 (relating to alternative
methods).
(c) The storage operator
shall give the Department notice at least 15 days prior to reconditioning or
altering a gas storage well and describe the procedure that the operator will
use to recondition or alter the gas storage well. If no objections are raised
by the Department within 10 days, the operator may proceed to recondition or
alter the well as proposed. The operator shall submit an updated well record
within 30 days of completing a reconditioning or
alteration.
Notes
This section cited in 25 Pa. Code § 78.405 (relating to emergency repairs).