25 Pa. Code § 78a.82 - Use of conductor pipe
If the operator installs conductor pipe in the well, the following provisions apply:
(1) The
operator may not remove the pipe.
(2) Conductor pipe shall be installed in a
manner that prevents the subsurface infiltration of surface water or fluids by
either driving the pipe into place or cementing the pipe from the seat to the
surface.
(3) Conductor pipe must be
made of steel unless a different material is approved for use by the
Department.