25 Pa. Code § 85.25 - Variances granted by the Department
(a) During the period between EQB designation
of a bluff recession hazard area and the approval of the Department of a bluff
setback ordinance and regulations of a municipality, the Department may grant
variances to the bluff setback requirements for all construction in a
designated bluff recession hazard area. A property owner shall file an
application with the Department for a variance to allow construction on his
property.
(b) When the Department
receives the completed application for a variance, it will review the
application based on the criteria for a variance under §
85.37(4)
(relating to contents of ordinance and regulations submitted by municipality)
within 45 days, and send a certified letter to the applicant approving or
disapproving the variance. A copy of this letter will be sent to the
municipality for its permanent record. If the Department does not take action
regarding the application within 45 days of receipt of this application, the
application will be deemed approved.