(a) The Department will first provide for the
reclamation of bond forfeiture sites where permits were issued under the
Federally-approved coal surface mining regulatory program which took effect
July 31, 1982, and where bonds under the permits were subsequently forfeited by
the Department. After the Department provides for reclamation of these sites,
the Department will provide for the reclamation of other bond forfeiture
sites.
(b) The Department will
provide for reclamation of bond forfeiture sites through one of the following:
(1) The Department may provide for
reclamation to be conducted under the public bidding and contracting
requirements of the Commonwealth under the site evaluation procedure in §
86.188 (relating to evaluation of
bond forfeiture sites). Under this approach, the Department will advertise for
bids for reclamation of the bond forfeiture site in a newspaper of general
circulation in the locality in which the work is to take place. The
advertisement will appear once a week for a minimum of 2-consecutive weeks. In
advertising for bids, the Department may consider various construction methods
for bidding, including the rental of equipment with equipment operators to be
supervised by the Department during completion of the reclamation
plan.
(2) Based on an engineering
cost estimate for completing the approved reclamation plan of the licensed mine
operator whose bonds were forfeited for the reclamation site, the Department
may negotiate and enter into a contract with the landowner of a bond forfeiture
site or another licensed mine operator to complete the reclamation of a bond
forfeiture site advertised for bids under paragraph (1). The Department will
give public notice of the intent to reclaim sites selected by the Department to
be advertised for public bids under paragraph (1) in a newspaper of general
circulation in the locality in which the work is to take place. The public
notice will appear once a week for a minimum of 2 consecutive weeks and may be
combined with the notice in paragraph (1). Payments to a person to whom the
Department has granted a contract under this paragraph will be made to the
extent of the appropriate compensation provisions according to a payment
schedule to be established by the Department. The final payment will be made
when the Department is satisfied that the person has completed reclamation of
the site in accordance with the approved reclamation plan and as specified in
the contract.
(i) The Department will
compensate landowners of bond forfeiture sites at a rate equal to the lesser of
one of the following:
(A) The Department's
engineering cost estimate for the site.
(B) The prevailing bond
rate.
(ii) The Department
will compensate licensed mine operators at a rate equal to the lesser of one of
the following:
(A) The Department's
engineering cost estimate for the site.
(B) The prevailing bond
rate.
(3) When
a licensed mine operator is granted a permit or has filed a permit application
on property contiguous to a property on which the Department has forfeited
bonds for failure to complete the reclamation plan, the permittee shall be
provided the opportunity to make a proposal to complete the reclamation plan of
the bond forfeiture site developed under §
86.187 (relating to use of money).
(i) The proposal shall contain estimated
costs and the necessary information upon which the Department can determine the
cost effectiveness of the proposal. Upon receipt of the proposal, the
Department may negotiate and enter into a contract with the permittee to
complete the reclamation plan. A determination whether to negotiate will be
made by the Department within 30 days of receipt of a complete proposal.
Contract negotiations will begin within 30 days of the determination to
negotiate.
(ii) Payments to a
person with whom the Department has entered into a contract under this
paragraph will be made to the extent of the appropriate compensation provisions
according to a payment schedule to be established by the Department, and the
final payment will be made when the Department is satisfied that the person has
completed reclamation of the site in accordance with the approved reclamation
plan and as specified in the contract. The Department will compensate licensed
mine operators at a rate equal to the lesser of one of the following:
(A) The Department's engineering cost
estimate for the site.
(B) The
prevailing bond rate.
(4) Under cooperative agreements among the
Department, the State Conservation Commission and the County Conservation
District in which the bond forfeiture site is located, the District may enter
into a contract with the landowner of the bond forfeiture site to reclaim the
site.
(i) The landowners of bond forfeiture
sites will be compensated at a rate equal to the lesser of one of the
following:
(A) The Department's engineering
cost estimate for the site.
(B) The
amount of the forfeited and collected bond.
(ii) The District may also compensate
landowners for the reasonable cost of insurance required for landowner
reclamation and the design and engineering costs incurred by the landowner in
the incidental modification of the reclamation plan, subject to approval by the
Department.
(c)
The Department will not enter into a reclamation contract under this section
with a person unless the person demonstrates the following to the satisfaction
of the Department:
(1) Neither the person nor
a related party has been convicted of a misdemeanor within the last 3 years for
violating The Clean Streams Law (35 P. S. §§
691.1-691.1001), the Coal Refuse
Disposal Control Act (52 P. S. §§
30.51-30.66), the Bituminous Mine
Subsidence and Land Conservation Act (52 P. S. §§
1406.1-1406.21), the Air Pollution
Control Act (35 P. S. §§
4001-4015), the Solid Waste
Management Act (35 P. S. §§
6018.101-6018.1003) or the Dam Safety
and Encroachments Act (32 P. S. §§
693.1-693.27).
(2) For bond forfeiture sites for which
permits were issued under the Federally-approved surface coal mining regulatory
program which took effect July 31, 1982, the proposed reclamation plan will
result in reclamation of the site in a manner consistent with The Clean Streams
Law and the regulations promulgated thereunder for active surface coal mining
operations, as specified in the contract, and the Surface Mining Conservation
and Reclamation Act and the regulations promulgated thereunder for active
surface coal mining operations.
(3)
For bond forfeiture sites for which the bonds were declared forfeit on or after
May 3, 1978, and for which permits were not issued under the Federally-approved
surface coal mining regulatory program which took effect July 31, 1982, the
proposed reclamation plan will result in reclamation of the site in a manner
that is consistent with the interim Federal program regulations first published
at 42 FR
62639 (December 13, 1977), as well as The Clean Streams Law and the
regulations promulgated thereunder in effect at the time the bonds were
declared forfeit, as specified in the contract, and the Surface Mining
Conservation and Reclamation Act and the regulations promulgated thereunder in
effect at the time the bonds were declared forfeit. If the Department's permit
files for the site clearly show that surface mining activities on the site
occurred before August 3, 1977, the proposed reclamation plan may be consistent
with paragraph (4).
(4) For bond
forfeiture sites for which the bonds were declared forfeit before May 3, 1978,
the proposed reclamation plan will result in reclamation of the site in a
manner that is consistent with The Clean Streams Law and the regulations
promulgated thereunder that were applicable to active surface coal mining
operations at the time the bonds were declared forfeit, as specified in the
contract, and the Surface Mining Conservation and Reclamation Act and the
regulations that were promulgated thereunder at the time the bonds were
declared forfeit.
(5) Except in the
case of a landowner of a bond forfeiture site under subsection (b)(2) and (4),
the person shall demonstrate the following:
(6) Except in the case of a landowner of a
bond forfeiture site under subsection (b)(2) and (4) the person shall
demonstrate the following:
(i) Neither the
person nor a related party has a legal obligation to correct the present
conditions at the site.
(ii) The
person meets the requirements of §
86.37(a)(8)-(11)
(relating to criteria for permit approval or
denial).
(d)
Prior to advertising a project for bids under subsection (b)(1) or to entering
into negotiations with the landowner or licensed mine operator under subsection
(b)(2), or upon receipt of an unsolicited proposed contract from a licensed
mine operator under subsection (b)(3), the Department will publish notice in
the Pennsylvania Bulletin, and notify the landowners of the
bond forfeiture site proposed for reclamation, of the location of the project
and a brief summary of work to be done.
(e) Upon awarding a reclamation contract
under this section, the Department will notify the landowners of the bond
forfeiture site proposed for reclamation of the name of the contract recipient,
the location of the project, a summary of work to be done and the cost of the
work and will publish a notice in the Pennsylvania Bulletin
annually of reclamation contracts awarded under this
section.