25 Pa. Code § 94.22 - Projected overload
If the annual report shows or if the Department determines that the sewerage facilities or any portion thereof will, within the next 5 years, become hydraulically or organically overloaded, the permittee of the sewerage facilities shall comply with the following:
(1) Submit a report or CAP to the regional
office, with the annual report or within 90 days of notification of the
Department's determination, setting forth steps to be taken by the permittee to
prevent the sewerage facilities from becoming hydraulically or organically
overloaded. If the steps to be taken include planning, design, financing,
construction and operation of sewerage facilities, the facilities shall be
consistent with an official plan approved under the Pennsylvania Sewage
Facilities Act (35 P. S. §§
750.1-750.20) and the regulations
thereunder in Chapter 71 (relating to administration of the sewage facilities
planning program) and consistent with the requirements of the Department and
the Federal government regarding areawide planning and sewerage
facilities.
(2) Limit new
connections to and extensions of the sewerage facilities based upon remaining
available capacity under a plan submitted in accordance with this
section.
Notes
The provisions of this § 94.22 issued under section 9 of the Pennsylvania Sewage Facilities Act (35 P. S. § 750.9).
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.