52 Pa. Code § 56.372 - Dispute procedures
A notice of dispute, including termination disputes, must proceed, according to this section:
(1)
Attempted resolution.
If, at any time prior to the actual termination of service, a customer advises
the public utility that the customer disputes any matter covered by this
chapter, including, but not limited to, credit determinations, deposit
requirements, the accuracy of public utility metering or billing or the proper
party to be charged, the public utility shall attempt to resolve the dispute in
accordance with §
56.381 (relating to general
rule).
(2)
Termination
stayed. Except as otherwise provided in this chapter, when a
termination dispute or complaint has been properly filed in accordance with
this subchapter, termination shall be prohibited until resolution of the
dispute or complaint. However, the disputing party shall pay undisputed
portions of the bill.
Notes
The provisions of this § 56.372 amended under the Public Utility Code, 66 Pa.C.S. § § 501, 1301, 1401-1419, 1501 and 1509.
This section cited in 52 Pa. Code § 56.266 (relating to transfer of accounts).
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.