52 Pa. Code § 69.3101 - Scope
(a) The Commission
adopts this section and §
§
69.3102-69.3107 regarding the additional
information that should be provided with a transmission siting application by
an electric utility under §
§
57.71-57.76 (relating to Commission
review of siting and construction of electric transmission lines). The
Commission encourages future applicants to file applications that comply with
the existing regulations as supplemented by this section and §
§
69.3102-69.3107 to ensure that adequate
additional information is provided and to ensure the efficient and expeditious
processing of transmission siting applications. In the event an applicant
determines there to be a conflict between the information requested in this
section and §
§
69.3102-69.3107 and the existing
regulations, the applicant should follow the requirements in §
§
57.71-57.76.