Tenn. Comp. R. & Regs. 0400-52-08-.04 - HORIZONTAL DRILLING
(1) Wells drilled
by horizontal methods shall comply with the following spacing requirements:
(a) For all oil wells, and for gas wells
drilled to the top of the Conasauga Group, the surface trace of that portion of
the well bore or any portion of the horizontal drainhole that penetrates the
producing formation, including the horizontal drainhole end point, shall not be
located closer than 330 feet from any property or unit line.
(b) For gas wells drilled below the top of
the Conasauga Group, the surface trace of that portion of the well bore or any
portion of the horizontal drainhole that penetrates the producing formation,
including the horizontal drainhole end point, shall not be located closer than
660 feet from any property or unit line.
(c) Any number of producing formations may be
penetrated by lateral drainholes from a single vertical well bore.
(d) All of the producing portion of the well
shall be in compliance with the spacing requirements of this paragraph. The
horizontal portion of the well is the formation of record for
production.
(2) For all
horizontal wells, the operator shall at a minimum cement the production casing
from the first packer up to 100 feet inside the intermediate casing.
Alternatively, the operator may utilize an appropriate packer at the bottom of
the intermediate casing instead of cement. Casing shall have an external
collapse pressure rating to handle cement design from termination point to
surface. If cement is used, the operator shall use cement with 500 psi
compressive strength and have a minimum 8 hour wait, or until cement has
adequately set. The operator shall present all cement and casing designs on a
specifications sheet with Permit Application for approval. A copy of cement
tickets shall be kept on location to be viewed by the inspector until the drill
rig is removed. When unknown or over pressured conditions are encountered a
5000 psi rating on casing shall apply. The operator shall attach a copy of all
cement tickets to the well history tickets and shall include all volumes and
pressures of job from start to finish.
Notes
Authority: T.C.A ยงยง 60-1-201 et seq., and 4-5-201 et seq.