Tenn. Comp. R. & Regs. 1220-04-06-.04 - DEPLOYMENT SCHEDULES
(1) In order to
develop rational deployment strategies for each of the service capabilities,
counties are classified according to their demographic characteristics as
urban, suburban or small urban, and rural. Under the Plan, the various service
capabilities are to be deployed as follows:
(a) Full deployment of intelligent network
capability (CCS#7) in the five urban counties in 1991, and in the rest of the
State by 1993.
(b) Deployment of
ISDN in 1991 in the urban areas, moving to full deployment by 1998. In the
suburban counties, deployment will start in 1993 with rapid initial buildup and
full deployment by the year 2000. Similarly, deployment will start in rural
counties in 1994 with a rapid initial buildup, leading to full deployment in
the year 2000.
(c) Offer broadband
capability in the urban counties starting in 1995, in suburban counties
starting in 1997, and in rural counties starting in 1999. In all cases,
broadband is planned to grow slowly at first, reaching 10 percent penetration
in the urban areas, 5 percent in the suburbs and 2 percent in the rural areas
by the year 2000.
(2)
These deployment schedules are designed to require additional expenditures by
the telephone companies that do not fluctuate too much from year to year. The
total additional cost over the ten- (10) year period is just under $400
million, with the highest cost, close to $100 million, incurred in 1991.
Translating these into estimates of revenue requirements, the increase fostered
by the Master Plan is an average of about $50 million per year, ranging from
$27 million in 1992 to $67 million in 1999. These cost increases represent an
approximate eleven and one half percent (11.5%) increase in capital expenses
and a four and three quarter percent (4.75%) increase in revenue requirements
over the life of the Plan. These estimates do not reflect any of the
operational savings or new service revenues which will flow from accelerated
deployment.
(3) Not included in the
costs is a plan to deploy fiber interoffice trunks to all wire centers serving
more than 1,000 access lines by 1993, and to all wire centers by 1995. Although
not needed for the service capabilities defined above, this deployment will
allow provision of broadband private line services to every county in the State
by 1993 and to every wire center by 1995. It is expected that the additional
costs of this deployment will be small since a great deal of added fiber trunk
capacity is already included in current plans.
Notes
Authority: T.C.A. ยงยง 65-2-102 and 65-4-104.
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.