Tenn. Comp. R. & Regs. 1220-04-07-.02 - GENERAL PROVISIONS
(1) These Purchased
Gas Adjustment (PGA) Rules are intended to permit the company to recover, in
timely fashion, the total cost of gas purchased for delivery to its customers
and to assure that the Company does not over-collect or under-collect Gas Costs
from its customers.
(2) These Rules
are intended to apply to all Gas Costs incurred in connection with the
purchase, transportation and/or storage of gas purchased for general system
supply, including, but not limited to, natural gas purchased from interstate
pipeline transmission companies, producers, brokers, marketers, associations,
intrastate pipeline transmission companies, joint ventures, providers of
liquefied natural gas (LNG), liquefied petroleum gas (LPG), substitute,
supplemental or synthetic natural gas (SNG), and other hydrocarbons used as
feed-stock, other distribution companies and end-users, whether or not the Gas
Costs are regulated by the Federal Energy Regulatory Commission and whether or
not the provider of the gas, transportation or storage is affiliated with the
Company.
(3) To the extent,
practicable, any revision in the PGA shall be filed with the Authority no less
than thirty (30) days in advance of the proposed effective date and shall be
accompanied by the computations and information required by these Rules. It is
recognized, however, that in many instances the Company receives less than
thirty (30) days notice from its suppliers and that other conditions may exist
which prevent the Company from providing thirty (30) days advance notice.
Therefore, should circumstances occur where information necessary for the
determination of an adjustment under these Rules is not available to the
Company so that the thirty (30) days requirement can be met, the Authority may
permit the Company to place rates into effect with shorter advance notice, upon
good cause shown.
(4) The rates for
gas service set forth in all of the Rate Schedules of the Company shall be
adjusted pursuant to the terms of the PGA, or any specified portion of the PGA
as determined by individual Rate Schedule(s).
(5) No provisions of these rules shall
supersede any provision of a special contract approved by the
Authority.