Tenn. Comp. R. & Regs. 1680-07-01-.02 - APPLICATION PROCESS FOR SPECIAL PERMITS
(1) Applications
for special permits may be made in person, or by letter, email, or telephone,
to the Tennessee Department of Transportation, Overweight and Overdimensional
Permit Office (hereinafter "TDOT Permit Office"), Suite 800, James K. Polk
State Office Building, 505 Deaderick Street, Nashville, TN 37243; email
address: tdot.permitoffice@tn.gov; telephone number: (615) 741-3821; or,
subject to the terms and conditions of a contract between TDOT and the
applicant or an authorized vendor, through TDOT's online
overweight/overdimensional permitting system.
(2) The applicant must provide the following
information:
(a) Name of applicant;
(b) Address of applicant;
(c) Description of article and/or commodity
to be moved;
(d) Method of moving
(truck and trailer, towing by truck, under own power, etc.);
(e) Motor vehicle registration number of
vehicle to be permitted;
(f)
Overall dimensions and/or gross weight of load;
(g) Number and spacing of axles, including
steering (if overweight);
(h)
Address of the place of origin and/or place of destination of movement within
Tennessee;
(i) Proposed highway
routes over which movement will be made;
(j) Proposed effective date of permit;
and
(k) Address to which permit is
to be transmitted and method of transmittal.
(3) The application for a special permit
shall be submitted in advance of the requested starting date of the permit in
accordance with the following schedule:
(a)
Applications for overdimensional permits shall be submitted at least three (3)
business days before the starting date of the permit; provided, however, that
applications for loads defined as extra-overdimensional under Rule
1680-07-01-.12
shall be submitted at least ten (10) business days before the starting date of
the permit.
(b) Applications for
overweight permits shall be submitted at least the following minimum number of
days before the starting date of the permit:
1. For gross vehicle weights of less than
165,000 pounds, at least three (3) business days;
2. For gross vehicle weights equal to or
greater than 165,000 pounds but less than 250,000 pounds, at least five (5)
business days;
3. For gross vehicle
weights equal to or greater than 250,000 pounds but less than 500,000 pounds,
at least fifteen (15) business days; and
4. For gross vehicle weights equal to or
greater than 500,000 pounds, at least thirty (30) business days.
(c) The TDOT Permits Office may
waive these application deadlines for good cause; and provided further, the
TDOT Permits Office reserves the right, upon giving notice to the applicant, to
take additional time as needed to review an application for a special
permit.
(4) Failure to
provide the required information may result in denial of the special permit
request or a delay in issuance of the special permit.
Notes
Authority: T.C.A. ยง 55-7-205.
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.