16 Tex. Admin. Code § 12.31 - Stockpiling of Minerals
(a) Coal. Coal
extracted and stockpiled may be excluded from the calculation of cumulative
production until the time of its sale, transfer to a related entity or use:
(1) up to an amount equaling a 12-month
supply of the coal required for future sale, transfer or use as calculated
based upon the average annual sales, transfer and use from the mining area over
the two preceding years; or
(2) for
a mining area where coal has been extracted for a period of less than two
years, up to an amount that would represent a 12-month supply of the coal
required for future sales, transfer or use as calculated based on the average
amount of coal sold, transferred, or used each month.
(b) Other minerals.
(1) The Commission shall disallow all or part
of an operator's tonnages of stockpiled other minerals for purposes of meeting
the requirements of §§12.25-12.30, this section, and §
12.32 and §
12.33 of this title (relating to
Exemption for Coal Extraction Incidental to the Extraction of Other Minerals)
if the operator fails to maintain adequate and verifiable records of the mining
area of origin, the disposition of stockpiles or if the disposition of the
stockpiles indicates the lack of commercial use or market for the
minerals.
(2) The Commission may
only allow an operator to utilize tonnages of stockpiled other minerals for
purposes of meeting the requirements of §§12.25-12.30, this section,
and §12.32 and §12.33 if:
(A) the
stockpiling is necessary to meet market conditions or is consistent with
generally accepted industry practices; and
(B) except as provided in paragraph (3) of
this subsection, the stockpiled other minerals do not exceed a 12-month supply
of the mineral required for future sales as approved by the Commission on the
basis of the exemption application.
(3) The Commission may allow an operator to
utilize tonnages of stockpiled other minerals beyond the 12-month limit
established in paragraph (2) of this subsection if the operator can demonstrate
to the Commission's satisfaction that the additional tonnage is required to
meet future business obligations of the operator, such as may be demonstrated
by a legally binding agreement for future delivery of the minerals.
(4) The Commission may periodically revise
the other mineral stockpile tonnage limits in accordance with the criteria
established in paragraphs (2) and (3) of this subsection based on additional
information available to the Commission.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.