16 Tex. Admin. Code § 25.128 - Interconnection Meters and Circuit Breakers
(a) Each electric utility purchasing electric
energy shall ensure that all instruments and meters are maintained as may be
necessary to obtain full information as to purchases, unless this information
is metered and furnished by the electric utility supplying the
energy.
(b) Record of automatic
circuit breaker operations. Each electric utility shall keep monthly records of
the number and cause, if known, of the operations of every automatic circuit
breaker in service on its transmission and distribution systems.