16 Tex. Admin. Code § 25.195 - Terms and Conditions for Transmission Service
(a) Applicability.
This section applies to the provision of transmission service in the Electric
Reliability Council of Texas (ERCOT) region by transmission service providers
(TSPs) to transmission service customers. This section also applies to
ERCOT.
(b) Definitions. The
following terms have the following meanings unless context indicates otherwise.
(1) Transmission-level generator--a
transmission service customer that is an electric generating facility under
§
25.5 of this title (relating to
Definitions), is interconnected to a TSP's system at or above 60 kilovolts
(kV), and is located behind one or more unique points of
interconnection.
(2) Transmission
system upgrade--any additional transmission facilities or modifications beyond
what is required to interconnect a transmission-level generator to the
transmission system. The construction of a new substation or modifications to
an existing substation is not a transmission-system upgrade if necessary to
interconnect a transmission-level generator.
(c) Interconnection agreement. As a condition
of obtaining transmission service, a transmission service customer that owns
electrical facilities in the ERCOT region must execute an interconnection
agreement with the TSP to which it is physically interconnected. The
commission-approved standard generation interconnection agreement (SGIA) must
be used for the interconnection of a new transmission service customer that is
a transmission-level generator. The SGIA may be modified by mutual agreement of
the parties to address specific facts presented by a particular interconnection
request provided that the modifications do not frustrate the goal of
expeditious, nondiscriminatory interconnection and are not otherwise
inconsistent with the principles underlying the commission-approved SGIA. The
SGIA must not be modified to relieve a transmission-level generator's
responsibility for all costs of installing interconnection facilities that are
incurred by the TSP that exceed the allowance under subsection (f) of this
section.
(d) Transmission service
provider responsibilities. The TSP must plan, construct, operate, and maintain
its transmission system in accordance with good utility practice to provide
transmission service customers with transmission service over its transmission
system in accordance with Division 1 of this subchapter (relating to
Open-Access Comparable Transmission Service for Electric Utilities in the
Electric Reliability Council of Texas). The TSP must, consistent with good
utility practice, endeavor to construct and place into service sufficient
transmission capacity to ensure adequacy and reliability of the network to
deliver power to transmission service customer loads. The TSP must plan,
construct, operate, and maintain facilities that are needed to relieve
transmission constraints, as recommended by ERCOT and approved by the
commission, in accordance with Division 1 of this subchapter. The construction
of facilities requiring commission issuance of a certificate of convenience and
necessity is subject to such commission approval.
(e) Construction of new facilities. If new
transmission facilities or interconnections between TSPs are needed to provide
transmission service in response to a request for such service, the TSPs must
construct or acquire transmission facilities necessary to provide the
transmission service in accordance with good utility practice, unless ERCOT
identifies an alternative means of providing the transmission service that is
less costly, is operationally sound, and is as effective as the new
transmission facilities would be at providing the requested transmission
service.
(1) An affected TSP may require the
transmission service customer to pay a reasonable deposit or provide another
means of security, to cover the costs of planning, licensing, and constructing
any new transmission facilities that will be required in order to provide the
requested service. Any repayment of a cash deposit under subparagraph (A) or
(B) of this paragraph must include interest at a commercially reasonable rate
based on that portion of the deposit being returned.
(A) If the new transmission service
customer's interconnection is completed and the transmission service customer
begins to take the requested transmission service, the TSP must return the
deposit or security to the transmission service customer.
(B) If the new transmission service
customer's interconnection is not completed and the new transmission facilities
are not required, the TSP may retain as much of the deposit or security as is
required to cover the costs the TSP incurred in planning, licensing, and
construction activities related to the planned new transmission
facilities.
(2) If the
TSP's acquisition or construction of the new transmission facilities would
impair the tax-exempt status of obligations issued by the TSP then the TSP may
require a contribution in aid of construction (CIAC) from the transmission
service customer to cover all or part of the cost of acquiring and constructing
the new transmission facilities.
(3) For a transmission service customer that
is not a transmission-level generator, the TSP is responsible for the cost of
installing any new transmission facilities, other than those provided for in
paragraph (2) of this subsection, in a contractual agreement between the TSP
and the customer, or in a commission-approved transmission service
tariff.
(4) For a
transmission-level generator, the costs of installing new transmission
facilities must be borne in accordance with subsection (f) of this
section.
(f) Cost
responsibilities to interconnect transmission-level generators at transmission
voltage.
(1) A new transmission-level
generator seeking interconnection to a TSP's transmission network is
responsible for the cost of installing step-up transformers and protective
devices at the point of interconnection capable of electrically isolating the
transmission-level generator.
(2)
If the SGIA between the transmission-level generator and the TSP is executed on
or before December 31, 2025, then the TSP is responsible for the cost of
installing any new transmission facilities.
(3) If the SGIA between a transmission-level
generator and TSP is executed after December 31, 2025, then the interconnecting
transmission-level generator is responsible for all costs of installing
interconnection facilities that are incurred by the TSP that exceed the
allowance established in accordance with this paragraph. The TSP is responsible
for the costs of installing any transmission system upgrades deemed necessary
by the TSP.
(A) The allowance will be
calculated by the commission as follows:
(i)
For a transmission-level generator interconnecting at a transmission voltage of
138 kV or less, the allowance beginning on January 1, 2026, is based on the
2024 amount of $14,000,000 adjusted for subsequent years consistent with clause
(ii) of this subparagraph. For a transmission-level generator interconnecting
at a transmission voltage higher than 138kV, the allowance beginning on January
1, 2026, is based on the 2024 amount of $20,000,000 adjusted for subsequent
years consistent with clause (ii) of this subparagraph.
(ii) The commission will increase or decrease
the allowance on or before January 1 of each calendar year in accordance with
this clause. The commission will publish the new values of the allowance to be
used in the subsequent calendar year on or around November 1 of each calendar
year.
(I) The annual adjustment will be
proportional to the third quarter to third quarter percentage change in the
national Consumer Price Index (CPI) published by the United States Department
of Labor, Bureau of Labor Statistics.
(II) The executive director must designate a
substitute index to be used as a reference for adjustments under this clause if
the index referenced by subclause (I) of this clause becomes
unavailable.
(B) A transmission-level generator that seeks
to interconnect an energy storage resource is only eligible to receive the
allowance described under this subsection and not additional allowances
provided to interconnect load, such as may be provided under a
tariff.
(C) The amount of the
allowance that a transmission-level generator is provided to complete the
interconnection is the amount that was in effect on the date the notice to
proceed with the interconnection was issued by the transmission-level generator
to the TSP in accordance with the executed SGIA. A TSP's costs to procure,
design, and construct or upgrade interconnection facilities that exceed the
allowance must be directly billed to and collected from the transmission-level
generator that caused the costs to be incurred by the TSP. The TSP may collect
such costs as a contribution in aid to construction prior to procuring,
designing, and constructing or upgrading the interconnection
facilities.
(D) Notwithstanding any
payments made by a transmission-level generator under this section, an
interconnecting TSP retains ownership and control of its transmission
facilities.
(E) After the
completion and energization of the initial interconnection, the responsibility
for costs incurred by a TSP for new or upgraded interconnection facilities due
to modifications or expansions made by the interconnected transmission-level
generator will be borne in accordance with this subparagraph.
(i) For the ten calendar years following the
date of energization for the initial interconnection of the transmission-level
generator, and to the extent that the costs of the new or upgraded
interconnection facilities needed due to modifications made by the
transmission-level generator exceed the remainder of the allowance calculated
under paragraph (3) of this subsection, the current owner of the
transmission-level generator that is listed in the new or amended SGIA is
responsible for the interconnection costs incurred by the TSP, where:
(I) the allowance is the amount that was in
effect on the date the notice to proceed with the initial interconnection was
issued in accordance with paragraph (3) of this subsection and the executed
SGIA; and
(II) the remainder is the
difference between the allowance described under subclause (I) of this clause
and the actual costs that a TSP incurred to construct, design, and upgrade
interconnection facilities to initially interconnect the transmission-level
generator. The remainder will be adjusted by the TSP in accordance with the
methodology in subparagraph (A)(ii) of this paragraph.
(ii) After ten calendar years from the date
of energization for the initial interconnection, the transmission-level
generator is eligible for a new allowance determined in accordance with
paragraph (3)(A) of this subsection for the costs of new or upgraded
interconnection facilities necessary to accommodate modifications made by the
transmission-level generator at the same point of interconnection.
(F) Beginning on or around May 1,
2029, and at least every five calendar years thereafter, the commission will
open a project and request comments on whether the allowance or annual
allowance adjustment methodology described in paragraph (3)(A) of this
subsection should be modified. If the commission determines the allowance or
the annual allowance adjustment methodology should be adjusted, the commission
will initiate a rulemaking proceeding.
(g) Curtailment of service. In an emergency
situation, as determined by ERCOT and at its direction, a TSP may interrupt
transmission service on a non-discriminatory basis, if necessary, to preserve
the stability of the transmission network and service to customers. Such
curtailments must be carried out in accordance with §
25.200 of this title (relating to
Load Shedding, Curtailments, and Redispatch) and in accordance with ERCOT
protocols.
(h) Filing of contracts.
An electric utility must file with the commission each new, and all amendments
to, interconnection agreements within 30 days of execution, including a cover
letter explaining any deviations from the commission-approved SGIA. An
interconnection agreement is subject to commission review and approval upon
request by any party to the agreement. Appropriate portions of the filings may
be filed confidentially and be subject to provisions of confidentiality to
protect competitively sensitive commercial or financial information.
(i) Transmission-level generator
interconnection costs report. ERCOT must, in consultation with commission
staff, include as part of the ERCOT Generation Interconnection Status report or
any successor report the generation interconnection costs for each new
transmission-level generator interconnected in each calendar month based on
date of energization, including the total cost of the interconnection, any CIAC
paid by the transmission-level generator, and any above-allowance costs
incurred by the transmission-level generator.
(1) Beginning in January 2026, within 90
calendar days from the end of each calendar month the TSP must provide to ERCOT
the information described in this subsection for each new transmission-level
generator interconnection to the TSP's system in that calendar month.
(2) Beginning in April 2027 and every
calendar year thereafter, ERCOT will publish the information described in this
subsection in a separate report for each new transmission-level generator
interconnection to the ERCOT transmission system in the prior calendar year.
ERCOT will, at a minimum, provide the information described in this subsection
and total amounts for the prior calendar year.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.