16 Tex. Admin. Code § 25.56 - Temporary Emergency Electric Energy Facilities (TEEEF)
(a) Applicability. This section establishes
the requirements for a transmission and distribution utility (TDU) to lease,
operate, and recover costs associated with a temporary emergency electric
energy facility (TEEEF). This section applies to a TDU that operates facilities
in the Electric Reliability Council of Texas (ERCOT) region to serve
distribution customers.
(b)
Definitions. The following terms, when used in this section, have the following
meanings unless the context indicates otherwise.
(1) Affected generator or load resource--a
generator or load resource that:
(A) is
registered with ERCOT for purposes of settlement; and
(B) is located within the portion of the grid
that is isolated from the bulk power system and where a TEEEF is energized to
restore power.
(2)
Significant power outage--an event that:
(A)
causes ERCOT to order a TDU to shed load;
(B) the Texas Division of Emergency
Management, ERCOT, or the executive director of the commission determines is a
significant power outage; or
(C)
results in a loss of electric power that:
(i)
affects a significant number of a TDU's distribution customers, and has lasted,
or is expected to last, for at least six hours;
(ii) affects distribution customers of a TDU
in an area for which the governor has issued a disaster or emergency
declaration;
(iii) affects
distribution customers served by a radial transmission or distribution
facility, creates a risk to public health or safety, and has lasted, or is
expected to last for, at least 12 hours; or
(iv) creates a risk to public health or
safety because it affects a critical infrastructure facility that serves the
public such as a hospital, health care facility, law enforcement facility, fire
station, or water or wastewater facility.
(3) Temporary Emergency Electric Energy
Facility (TEEEF)--a facility that provides electric energy to distribution
customers on a temporary basis.
(c) Authorization to lease TEEEF. Except as
authorized under subsection (d) of this section, a TDU must not enter into,
renew, or extend any lease involving a TEEEF without receiving prior commission
authorization. Authorization under this subsection applies to a TDU's TEEEF
fleet. A TDU may enter into one or more leases for TEEEF, simultaneously or
consecutively, provided that the capacity and characteristics of its leased
TEEEF fleet complies with the authorization provided under this subsection at
all times.
(1) Contents of application. An
application under this subsection must include the following:
(A) The TDU's history with TEEEF, including:
(i) Whether the TDU is currently or has
previously been authorized by the commission to lease TEEEF, the details of
existing or prior authorizations, and each docket number in which the
authorization was granted;
(ii) A
description of all TEEEF the TDU has under lease at the time of the
application, including the total capacity the TDU has under lease, the length
of the lease or leases, a description of the capacity, intended functions, and
relevant characteristics of each leased unit, and whether each leased unit has
been energized to aid in restoring power during a significant power
outage;
(iii) A description of any
previous emergency leases of TEEEF or prior use of another TDU's TEEEF under a
mutual assistance agreement or program. A TDU must include an explanation for
the necessity of each use of TEEEF under an emergency lease or mutual
assistance agreement or program;
(iv) A copy of every after-action report
submitted by the TDU to the commission under this section during the five years
prior to the date on which the application was filed, including a cover page
with summary statistics on significant power outages and TEEEF energizations in
the TDU's service territory; and
(v) The interchange item number of the TDU's
most recently filed emergency operations plan filed in project no.
53385.
(B) The total
capacity of TEEEF the TDU is requesting authorization to lease, each function
the requested TEEEF will serve (e.g. to restore power to individual facilities,
to restore power to feeders to assist in load rotation, etc.) and how much of
the requested capacity is requested for each function, and the length of time
for which the TDU is requesting authorization. In support of its request, the
TDU must include the following:
(i) A
description of any necessary characteristics a TEEEF unit must have to perform
each of the functions for which authorization is requested. These
characteristics should be identified with enough specificity to allow the
commission to evaluate, in a subsequent proceeding, whether the TDU's leased
TEEEF fleet complies with the commission's authorization. These characteristics
should include, as applicable, the capacity or range of capacities of
individual units, the mobility of individual units, the types of connections
the units must be compatible with, such as mid-span or point-of-use, fuel type,
and whether the units can fulfill the function individually or with multiple
units working in tandem;
(ii) An
explanation with any necessary supporting documentation that the functions the
TEEEF is being requested to perform are reasonable and necessary to aid in the
restoration of power under this section. This supporting documentation must
include, at minimum, historical data on significant power outages that occurred
in the TDU's service territory and would have qualified for TEEEF deployment
for the five-year period preceding the date of the application, including:
(I) the start and end date of the outage and
information on how long customers were affected by the outage;
(II) a description of the events that caused
the outage;
(III) the number of
affected distribution customers and amount of load, in megawatts, that were
affected by the outage; and
(IV)
the number and type of critical load, critical care customers, or other
critical infrastructure facilities as defined in §
25.497 of this title (relating to
Critical Load Industrial Customers, Critical Load Public Safety Customers,
Critical Care Residential Customers, and Chronic Condition Residential
Customers) affected by the outage.
(iii) A description of any additional
measures being implemented or scheduled for implementation that may mitigate
the need for TEEEF, such as the TDU's implementation of a resiliency plan
measure under §
25.62 of this chapter, relating to
Transmission and Distribution System Resiliency Plans.
(C) As appropriate, data provided under this
section must be filed in a format native to Microsoft Excel and must permit
basic data manipulation functions, such as copying and pasting of
data.
(2) The application
will be processed in a contested case proceeding as follows.
(A) Sufficiency. An application is sufficient
if it includes the information required by paragraph (1) of this subsection and
the TDU has filed proof that notice has been provided in accordance with this
subsection.
(i) Within 30 calendar days of
the TDU filing its application, commission staff must file a recommendation on
sufficiency of the application. If commission staff recommends the application
be found deficient, commission staff must identify the deficiencies in its
recommendation. The TDU will have five working days to file a response, which
may include an amendment to the application to attempt to cure the
deficiency.
(ii) If the presiding
officer determines the application is deficient, the presiding officer will
file a notice of deficiency and cite the particular requirements with which the
application does not comply. The presiding officer must provide the TDU an
opportunity to amend its application. Commission staff must file a
recommendation on sufficiency within 10 working days after the filing of an
amended application, when the amendment is filed in response to a notice of
deficiency.
(iii) If the presiding
officer has not filed a written order concluding that the application is
deficient within 10 working days after a deadline for a recommendation on
sufficiency, the application is deemed sufficient.
(B) Notice and intervention. Within one
working day after the TDU files its application, the TDU must provide notice of
its filed application, including the docket number assigned to the application
and the deadline for intervention in accordance with this paragraph. The
intervention deadline is 30 days from the date service of notice is complete.
The notice must be provided using a reasonable method of notice to:
(i) all municipalities in the TDU's service
area that have retained original jurisdiction;
(ii) all parties in the TDU's last base-rate
proceeding;
(iii) each retail
electric provider that provides service in the TDU's service area;
and
(iv) the Office of Public
Utility Counsel.
(3) Commission evaluation and final
determination. The commission will authorize a TDU to lease TEEEF under this
subsection if it determines that leasing the requested TEEEF is reasonable and
necessary to aid in restoring power to the TDU's distribution customers during
a significant power outage that qualifies for TEEEF energization. The
commission's final order will include the total TEEEF capacity the TDU is
authorized to lease, the capacity of TEEEF the TDU is authorized to lease for
each function the TEEEF fleet will perform, and the date or dates the
authorization expires (i.e., TEEEF leases must not extend past this date). The
commission may include additional requirements related to the characteristics
the TEEEF the TDU is authorized to lease.
(d) Emergency TEEEF lease.
(1) A TDU may enter into a lease for TEEEF
without prior commission approval if the TDU lacks the leased TEEEF generating
capacity necessary to aid in restoring power, consistent with subsection (f) of
this section.
(2) The amount of
TEEEF generating capacity leased by a TDU under this subsection must not exceed
the amount of megawatts or length of time necessary to restore electric service
to the TDU's distribution customers by more than a reasonable amount.
(3) The TDU must provide sufficient
documentation to support the reasonableness, necessity, and prudence of any
generating capacity and costs of TEEEF leased by a TDU under this subsection
during the TDU's next base-rate proceeding.
(e) Competitive bidding process. Except for
an emergency lease under subsection (d) of this section, a TDU must use a
competitive bidding process to lease TEEEF under this section.
(1) In any proceeding in which the commission
is reviewing the reasonableness, necessity, or prudence of the costs associated
with leasing a TEEEF under this section, the commission may also consider
whether the contracts the TDU entered into to lease TEEEF were reasonable
relative to other bids that were available to the TDU, if any.
(2) In any proceeding in which a TDU is
requesting recovery of costs associated with TEEEF that was not leased using a
competitive bidding process, the TDU must demonstrate that the TEEEF was leased
under an emergency lease consistent with subsection (d)..
(3) A TDU may not enter into a lease for
TEEEF with a competitive affiliate of the TDU unless that lease was subject to
a competitive bidding process.
(4)
If requested by a commissioner or commission staff, a TDU must allow for the
inspection of any lease entered into under this section. If the commissioner or
commission staff retains a copy of the lease, the lease will be treated as a
confidential document if so requested by the TDU.
(f) Energization of TEEEF.
(1) A TDU may energize TEEEF to aid in
restoring power to its distribution customers during an event that a TDU
reasonably determines is a significant power outage in which:
(A) ERCOT has ordered the TDU to shed load;
or
(B) the TDU's distribution
facilities are not being fully served by the bulk power system under normal
operations.
(2) A TDU may
loan its leased TEEEF to other TDUs or otherwise utilize its leased TEEEF in
another TDU's service territory under a mutual assistance agreement or program,
provided that all costs and reimbursements associated with such a loan or
utilization are properly accounted for and reconciled.
(3) A TDU that leases a TEEEF must not sell
energy or ancillary services from the facility.
(4) A TEEEF must:
(A) be operated in isolation from the bulk
power system; and
(B) not be
included in locational marginal price calculations, pricing, or reliability
models developed by ERCOT.
(5) Notice. A TDU must issue notices under
subparagraphs (A), (B), (C), and (D) of this paragraph to ERCOT and all
operators of affected generators or load resources. Notice under this paragraph
is not required if the area isolated from the bulk power system does not
contain any affected generators or load resources.
(A) Prior to isolation. For an isolation from
the bulk power system due to circumstances within a TDU's control in which
TEEEF will be energized, a TDU must issue notice at least 10 minutes prior to
isolation of an affected area from the bulk power system. For an isolation from
the bulk power system due to circumstances beyond a TDU's control in which
TEEEF will be energized, a TDU must issue notice as soon as is reasonably
practicable. Notices prior to isolation of an affected area from the bulk power
system must include:
(i) identification of
each substation and modeled load associated with customer load that will be
served by TEEEF;
(ii) the total
amount of load expected to be served by TEEEF;
(iii) the time the affected area is
anticipated to be isolated from the bulk power system;
(iv) the time the affected area is
anticipated to be reconnected to the bulk power system;
(v) identification of each generator or load
resource that will be an affected generator or load resource following the
energization of TEEEF; and
(vi) a
statement that any energy produced by an affected generator during the time it
is isolated from the bulk power system will not be settled through
ERCOT.
(B) Upon
isolation. For an isolation from the bulk power grid due to circumstances
within a TDU's control in which TEEEF will be energized, a TDU must issue
notice immediately upon isolation of an affected area from the bulk power
system. For an isolation from the bulk power system due to circumstances beyond
a TDU's control in which TEEEF will be energized, a TDU must issue notice as
soon as is reasonably practicable. A notice issued under this subparagraph must
state the time an affected area's isolation from the bulk power system was
completed.
(C) Prior to
reconnection. A TDU must issue notice at least 10 minutes prior to the
reconnection of an affected area to the bulk power system. A notice issued
under this subparagraph must state the anticipated time that an affected area
will be reconnected to the bulk power system.
(D) Upon reconnection. A TDU must issue
notice immediately after the reconnection of an affected area to the bulk power
system has been completed. A notice issued under this subparagraph must state
the time the reconnection of an affected area to the bulk power system was
completed.
(E) If a TDU has issued
notice under subparagraphs (A) or (C) of this paragraph, and coordination with
ERCOT under paragraph (6) of this subsection results in a delay in the
anticipated time of isolation or reconnection, the TDU must notify operators of
affected generators and load resources of such delay.
(6) Coordination with ERCOT.
(A) TDUs. The requirements of this
subparagraph apply only to energizations of TEEEF that occur outside of an
energy emergency declared by ERCOT. A TDU's isolation or reconnection of load
associated with an energization of TEEEF must be coordinated with ERCOT
according to the following timeframes if the total amount of load at any single
substation that would be isolated or reconnected exceeds 20 megawatts.
(i) For isolations of load from the bulk
power system due to circumstances within a TDU's control, a TDU should
coordinate with ERCOT within a period of 10 minutes.
(ii) For isolations of load from the bulk
power system due to circumstances beyond a TDU's control, a TDU should
coordinate with ERCOT as soon as is reasonably practicable.
(B) Affected generators and load resources.
(i) Upon receiving notice from a TDU that an
affected area will be isolated from the bulk power system, an operator of an
affected generator or load resource that is required by ERCOT protocols to
provide status telemetry to ERCOT must, at the expected time of isolation as
indicated in the TDU's notice, update its real-time status telemetry and
current operating plan information to reflect that the affected generator or
load resource is disconnected from the ERCOT system, is unavailable for
dispatch by ERCOT, and will be unavailable for dispatch by ERCOT for the time
period specified by the TDU in its notice.
(ii) Upon receiving notice from a TDU that an
affected area has been reconnected to the bulk power system, the operator of
any affected generator or load resource must update its real-time status
telemetry and current operating plan information to reflect the appropriate
status of the affected generator or load
resource.
(7) A
TDU's liability related to the provision of service using a TEEEF is governed
by §
25.214 of this title (relating to
Terms and Conditions of Retail Delivery Service Provided by Investor-Owned
Transmission and Distribution Utilities).
(8) A TDU will ensure, to the extent
reasonably practicable, that:
(A) A retail
distribution customer's usage during the TDU's operation of a TEEEF is excluded
or removed from the electric usage reported to ERCOT for final settlement and
to retail electric providers (REPs) for customer billing; and
(B) Energy generated in an area isolated from
the bulk power system in accordance with this section, including any energy
generated by an affected generator, is excluded or removed from the generation
reported to ERCOT for final settlement purposes.
(9) During an energy emergency declared by
ERCOT, the amount of any load shed by a TDU for the area operated in isolation
from the bulk power system during TEEEF energization must be accounted for net
of any generation in the affected area that was online and producing before the
area was isolated from the bulk power system.
(10) After-action report. After each
significant power outage in a TDU's service territory that meets the criteria
for TEEEF energization under paragraph (1) of this subsection, a TDU that has
leased TEEEF must file an after-action report with the commission. The report
must be filed within 30 days from the last day of the significant power outage.
The report must include, as applicable:
(A) A
description of the events that resulted in the significant power outage within
the TDU's service territory, including the dates and times the significant
power outage began and ended;
(B)
The estimated number of affected distribution customers and estimated amount of
load, in megawatts, that were affected by the significant power outage in the
TDU's service territory and the estimated number of which that were served by
TEEEF;
(C) The estimated number and
type of critical load, critical care customers or other critical infrastructure
facilities as defined in §
25.497 of this title, affected by
the significant power outage and the estimated number that were served by
TEEEF. A TDU must also include available details on the duration of service
interruptions for these customers;
(D) The total nameplate generating capacity
in megawatts and the total number of affected generators or load resources that
were isolated from the bulk power system for TEEEF energization.
(E) A description of any TEEEF energizations,
including the capacity, fuel type, connection configuration, and mobile
capability of each TEEEF unit that was energized, the function each TEEEF unit
was performing, the date and time each TEEEF unit was energized, and the
duration that the affected area was isolated from the bulk power
system;
(F) A list of TEEEF that
was not energized, including the capacity, fuel type, connection configuration,
and mobile capability of each TEEEF unit that was not energized and a brief
summary explaining why each TEEEF unit was not energized.
(G) A description of any TEEEF units that
were leased under subsection (d) of this section or utilized under a mutual
assistance agreement or program. A TDU must include an explanation for the
necessity of the emergency lease or utilization of the mutual assistance
agreement or program;
(g) Emergency operations annex. A TDU that
leases TEEEF under this section must include a detailed plan on the use of the
TDU's leased TEEEF in the TDU's emergency operations plan filed with the
commission, as required by §
25.53 of this title (relating to
Electric Service Emergency Operations Plans), that is updated, as necessary, on
an ongoing basis.
(h) Eligible
costs.
(1) Costs to obtain, and operate a
TEEEF. Reasonable and necessary costs of leasing, and operating a TEEEF,
including the present value of future payments required under the lease, are
eligible for recovery under this section. A lease involving a TEEEF must be
treated as a capital lease or finance lease for ratemaking purposes, regardless
of its classification under generally accepted accounting principles or other
accounting frameworks.
(2) Return.
Reasonable and necessary costs under this section include a return on
investment, including the present value of future payments required under the
lease, using the rate of return on investment established in the commission's
final order in a TDU's most recent comprehensive base-rate
proceeding.
(i) Deferred
recovery of certain eligible costs. A TDU may create a regulatory asset to
defer the following for recovery in a future ratemaking proceeding:
(1) The reasonable and necessary incremental
operations and maintenance expenses, not otherwise included in any of the TDU's
rates; and
(2) The return, not
otherwise included in any of the TDU's rates.
(j) Cost recovery. Eligible costs under this
section may be recovered as follows.
(1)
Ratemaking proceedings. A TDU may request recovery of eligible costs, including
any deferred expenses, through a standalone TEEEF rider proceeding, a
proceeding under §
25.243 of this title (relating to
Distribution Cost Recovery Factor (DCRF)), or in another ratemaking proceeding
where it is appropriate to recover distribution invested capital and associated
costs. A river authority may request recovery of eligible costs, including any
deferred expenses, through a ratemaking proceeding where it is appropriate to
recover distribution invested capital and associated costs or through a
standalone TEEEF rider proceeding.
(A) A TDU
must provide notice to REPs of the approved rates not later than the 45th day
prior to the effective date of the approved.
(B) TEEEF costs must not be allocated to, or
collected from, retail transmission service customers or wholesale transmission
service at transmission voltage customers.
(C) Notwithstanding the provisions of §
25.243 of this title, an
allocation of TEEEF costs among distribution-level rate classes, based on
substation-level class non-coincident peak demand, regardless of the time at
which the class demand occurs, from the TDU's current or most recent base-rate
proceeding, is presumed to be reasonable.
(D) TEEEF rates may not be established on a
per-kilowatt-hour basis for any customer class that includes demand
charges.
(E) Upon any amendment to
a lease under this section that would reduce the rate of cost recovery
necessary for a TEEEF, a TDU must submit an application to reflect the reduced
rate of cost recovery necessary, by the earlier of three months from the lease
amendment or the TDU's next DCRF proceeding.
(F) TEEEF costs must not be included in base
rates. All TEEEF costs must be recovered through a single rider associated with
TEEEF. A TDU with a previously established TEEEF rider may recover additional
TEEEF costs by updating the existing TEEEF rider.
(G) TEEEF costs will not be reviewed for
reasonableness, necessity, or prudence in a proceeding other than a base-rate
proceeding, unless the presiding officer finds good cause to review them in
another proceeding.
(H) In any
proceeding in which TEEEF costs are reviewed for reasonableness, necessity, or
prudence, the application must include the after-action reports for significant
power outages during the period for which costs are being reviewed. The
application must also include the leases, filed confidentially, for any leased
TEEEF for which costs are being reviewed.
(I) A TDU that, prior to the effective date
of this rule, received commission approval in a contested case proceeding for
an amount of TEEEF generating capacity may request approval of reductions of
that capacity through a subsequent standalone TEEEF rider proceeding made in
accordance with this paragraph.
(2) Notice. The notice for any ratemaking
proceeding in which eligible TEEEF costs are sought must specifically identify
those eligible costs.
(3) Affiliate
contracts. For any contract between a TDU and an affiliate, the TDU bears the
burden of proof to show that the terms to the TDU were reasonable and necessary
and did not exceed the prices charged by the supplying affiliate to its other
affiliates or divisions or to unaffiliated persons within the same market area
or having the same market conditions. In addition, all affiliate payments must
comply with the requirements of PURA §36.058.
(4) Reconciliation. If TEEEF rates include
any eligible costs that have not been reviewed for reasonableness, necessity,
and prudence, any rates to recover any portion of those costs are temporary
rates that must be reconciled in the TDU's next base-rate proceeding, including
to determine whether the costs are reasonable, necessary, and prudent.
(A) In reconciling TEEEF costs, all revenues
received associated with TEEEF programs, including actual rate revenues and
mutual assistance reimbursements, must be applied to offset reasonable,
necessary, and prudent TEEEF costs as these costs and revenues were incurred
and received.
(B) A TDU must
provide comprehensive testimony and workpapers supporting the reconciliation of
all eligible costs and associated rate revenues as part of any base-rate
proceeding application. Any amounts recovered through rates approved under this
subsection that are found to have been unreasonable, unnecessary, or imprudent,
plus the corresponding return, taxes, and carrying costs, must either be
refunded or applied as an offset to any outstanding regulatory asset associated
with eligible costs. In any proceeding in which the commission determines that
a TDU has included in rates any amounts deemed unreasonable, unnecessary, or
imprudent, or that the TDU has otherwise over-recovered costs, the commission
may order a compliance proceeding to determine the amounts and manner of any
necessary refunds to ratepayers or the proper accounting of over-recovered
amounts as an offset to any outstanding regulatory assets associated with
eligible costs. Carrying costs will be determined as follows:
(i) For the time period beginning with the
date on which over-recovery is determined to have begun to the effective date
of the TDU's base rates set in the base-rate proceeding in which the costs are
reconciled, carrying costs will accrue monthly and will be calculated using an
effective monthly interest rate based on the same rate of return that was
applied to the TDU's rate base included in base rates in effect when the
over-recovery began.
(ii) For the
time period beginning with the effective date of the TDU's rates set in the
base-rate proceeding in which the costs are reconciled, carrying costs will
accrue monthly and will be calculated using an effective monthly interest rate
based on the TDU's rate of return authorized in that base-rate
proceeding.
(5)
As part of the reconciliation of TEEEF costs, the commission may consider
whether the leased TEEEF had the characteristics required to perform the
functions authorized by the commission, whether the TEEEF was properly utilized
to restore power during significant power outages, including appropriate
pre-outage preparations such as positioning and securing fuel or the units, or
any other factor relevant to the prudence or reasonableness of the TDU's
procurement or operation of TEEEF.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.