16 Tex. Admin. Code § 74.111 - Plan Review - New Equipment
(a) A contractor
must submit for review an application and plans for the installation of new
equipment.
(b) To apply for a plan
review for the installation of new equipment, a contractor must:
(1) submit a completed application on a
department-approved form;
(2) pay
the fee required by §74.80; and
(3) submit layout drawings as specified in
the ASME Code A17.1 adopted in §74.100 for the specific type of equipment
to be installed. These layout drawings shall also include:
(A) the rated speed of the equipment in feet
per minute;
(B) the rated capacity
of the equipment in pounds;
(C) the
total travel of the equipment in feet and inches;
(D) elevation drawings of the hoistway,
runway or wellway; and
(E) plan
drawings indicating the arrangement of the equipment in a machine room, machine
space, control room or control space.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.