16 Tex. Admin. Code § 74.80 - Fees
(a) Inspector Registration Fees.
(1) Original application--$50
(2) Renewal application--$50
(3) Revised/Duplicate registration
card--$25
(b)
Certificate of Compliance Filing Fees.
(1)
Filing fees submitted within 30 days of the equipment inspection date: $20 per
unit of equipment, along with a copy of the inspection report.
(2) Late filing fees: $10 per unit of
equipment for 30 day period if the inspection report, filing fees, and
verification about correcting deficiencies in the inspection report are filed
after the 60th day from the equipment inspection date.
(3) Revised/Duplicate Certificate Fee--$25
per certificate.
(c)
Waiver or Delay Application Fees.
(1) $50 for
each violation of the ASME Safety Codes or ASCE Standards as adopted in §
74.100 per unit of equipment requested to be waived or delayed.
(2) Fees shall be charged and collected by
the department for a waiver or delay application for an institution of higher
education.
(d)
Contractor Registration Fees.
(1) Original
application--$115
(2) Renewal
application--$115
(3)
Revised/Duplicate registration card--$25
(e) Late renewal fees for Inspector and
Contractor registrations issued under this chapter are provided under §
60.83 of this title (relating to
Late Renewal Fees).
(f) New
Technology Variance Fees.
(1) Application
fee--$2,500
(2) Fee to file an
appeal of a denial of an application--$200
(g) Fees for Plan Reviews.
(1) The plan review fee for the installation
or alteration of equipment included in a contract shall be calculated as
follows:
(A) $200 for each unit of equipment
for which a decal is required; and
(B) the maximum fee shall not exceed
$5,000.
(2) The fee to
review plans on an expedited basis is $1,000 per unit of equipment included in
a contract for which a decal is required. There is no maximum fee or cap for
expedited reviews.
(h)
Fees for Amendments to Previously Approved Plan Reviews.
(1) The plan review fee for amendments to
previously approved plan reviews where the installation or alteration of
equipment included in a contract has not been completed shall be as follows:
(A) $100 per unit of equipment for which a
decal is required; and
(B) the
maximum fee shall not exceed $2,500.
(2) The fee to review amendments to
previously approved plan reviews on an expedited basis is $1,000 per unit of
equipment included in a contract for which a decal is required. There is no
maximum fee or cap for expedited reviews.
(i) The fee for "Installation Removed from
Service" is $20 per unit of equipment.
Notes