31 Tex. Admin. Code § 375.82 - Contract Documents: Review and Approval
(a) Contract documents include the documents
that form the construction contracts and the documents that form the contracts
for alternative methods of project delivery, which may include the construction
phase or other phases of the project.
(b) Unless otherwise specified by the
executive administrator, an Applicant must submit at least one electronic copy
of proposed contract documents, including the engineering plans and
specifications, which must be as detailed as would be required for submission
to contractors bidding on the work. The Applicant must provide the executive
administrator with all contract documents proposed for bid advertising. The
executive administrator will review contract documents:
(1) to ensure consistency with the approved
engineering feasibility report and with approved environmental planning
documents;
(2) to ensure the
proposed construction drawings and specifications provide adequate information
so that a contractor can bid and construct the project without additional
details or directions;
(3) to
ensure compliance with Commission rules at 30 TAC Chapter 217 (relating to
Design Criteria for Domestic Wastewater Systems) and other applicable state and
federal laws and rules;
(4) to
ensure the contract documents notify the contractor about the Board's authority
to audit project files and inspect during construction; and
(5) to ensure compliance with other
requirements as provided in guidance forms and documents, including any
additional documentation required by EPA for equivalency projects.
(c) An applicant with a commitment
of financial assistance from the Board may qualify for a risk-based review
pursuant to Texas Water Code, §
17.276.
(1) The EA may perform a risk-based review
when:
(A) the applicant's internal risk score
rating is 2B or higher; and
(B) the
design scope is limited to in-situ replacement or rehabilitation of existing
facilities, or new gravity sewer lines and manholes, and project work is not
located within the Edwards Aquifer recharge zone; or the applicant has approval
authority granted by TCEQ for collection systems pursuant to 30 TAC §
217.8.
(2) Designs qualifying for a risk-based
review require the following:
(A) contract
documents submitted for review and approval in accordance with this section;
and
(B) certification from the
applicant's design engineer verifying the plans and specifications comply with
30 TAC Chapter 217 requirements and include no variances, or the entity has
approval authority granted by the TCEQ for collection systems.
(3) The EA may outline additional
criteria in TWDB's guidance documents.
(d) Other approvals. The Applicant shall
obtain the approval of the plans and specifications from any other local,
state, and federal agencies having jurisdiction over the project. The executive
administrator's approval is not an assumption of the Applicants' liability or
responsibility to conform to all requirements of applicable laws relating to
design, construction, operation, or performance of the project.