31 Tex. Admin. Code § 51.208 - Timetable
(a) Following receipt of a contractor's
notice of claim, the executive director of the department or other
representative designated in the contract shall review the contractor's
claim(s) and the department's counterclaim(s), if any, and initiate
negotiations with the contractor to attempt to resolve the claim(s) and
counterclaim(s).
(b) Subject to
subsection (c) of this section, the parties shall begin negotiations within a
reasonable period of time, not to exceed 60 days following the later of:
(1) the date of termination of the
contract;
(2) the completion date,
or substantial completion date in the case of construction projects, in the
original contract; or
(3) the date
the department receives the contractor's notice of claim.
(c) The department may delay negotiations
until after the 180th day after the date of the event giving rise to the claim
of breach of contract by:
(1) delivering
written notice to the contractor that the commencement of negotiations will be
delayed; and
(2) delivering written
notice to the contractor when the department is ready to begin
negotiations.
(d) The
parties may conduct negotiations according to an agreed schedule as long as
they begin negotiations no later than the deadlines set forth in subsections
(b) or (c) of this section, whichever is applicable.
(e) Subject to subsection (f) of this
section, the parties shall complete the negotiations that are required by this
chapter as a prerequisite to a contractor's request for contested case hearing
no later than 270 days after the department receives the contractor's notice of
claim.
(f) The parties may agree in
writing to extend the time for negotiations on or before the 270th day after
the department receives the contractor's notice of claim. The agreement shall
be signed by representatives of the parties with authority to bind each
respective party and shall provide for the extension of the statutory
negotiation period until a date certain. The parties may enter into a series of
written extension agreements that comply with the requirements of this
section.
(g) The contractor may
request a contested case hearing before the State Office of Administrative
Hearings ("SOAH") pursuant to §
51.213 of this title (relating to
Request for Contested Case Hearing) after the 270th day after the department
receives the contractor's notice of claim, or the expiration of any extension
agreed to under subsection (f) of this section.
(h) The parties may agree to mediate the
dispute at any time before the 270th day after the department receives the
contractor's notice of claim or before the expiration of any extension agreed
to by the parties pursuant to subsection (f) of this section. The mediation
shall be governed by the provisions of this subchapter.
(i) Nothing in this section is intended to
prevent the parties from agreeing to commence negotiations earlier than the
deadlines established in subsections (b) and (c) of this section, or from
continuing or resuming negotiations after the contractor requests a contested
case hearing before SOAH.