43 Tex. Admin. Code § 21.158 - Permit Application Review
(a) The department will consider permit applications in the order of the receipt of completed applications.
(b) If an application is rejected because it is not complete, lacks documentation, or has incorrect information, the application loses its priority position. The department will notify the applicant of the reasons the application was rejected.
(c) The department will hold an application for a site that is the same as or conflicts with the site of an application that the department previously received until the department makes a final decision on the previously received application. The department will notify the applicant that the applicant's application is being held because an application for the same or a conflicting site was previously received. For the purposes of this subsection, the date of a final decision on an application is:
(1) the date the application is approved; or
(2) if the application is denied:
(A) the date of the final decision on an appeal under §
21.167 of this subchapter (relating to Appeal Process for Application Denials); or
(d) The department will review the permit application for completeness, correctness, and compliance with all requirements of this subchapter. Measurements will be taken at the site to determine if the sign placement meets the spacing and location requirements.