43 Tex. Admin. Code § 21.57 - Temporary Saltwater Pipeline
(a) A temporary saltwater pipeline may be installed on highway right of way pursuant to a lease from the department. Before a temporary saltwater pipeline may be installed, the installation must be approved by the department.
(b) The outer diameter of a pipe used for a temporary saltwater pipeline may not to exceed 12 inches.
(c) A temporary saltwater pipeline may not operate at a pressure of over 60 pounds per inch.
(d) A temporary saltwater pipeline may not be in place on highway right of way for a period that exceeds 180 days.