Utah Admin. Code R307-415-7a - Permit Issuance: Action on Application
(1) A permit, permit modification, or renewal
may be issued only if all of the following conditions have been met:
(a) The director has received a complete
application for a permit, permit modification, or permit renewal, except that a
complete application need not be received before issuance of a general
permit;
(b) Except for
modifications qualifying for minor permit modification procedures under
R307-415-7f(1)and
(2), the director has complied with the
requirements for public participation under R307-415-7 i;
(c) The director has complied with the
requirements for notifying and responding to affected States under
R307-415-8(2);
(d) The conditions of the permit provide for
compliance with all applicable requirements and the requirements of
R307-415;
(e) EPA has received a
copy of the proposed permit and any notices required under
R307-415-8(1)
and (2), and has not objected to issuance of
the permit under
R307-415-8(3)
within the time period specified therein.
(2) Except as provided under the initial
transition plan provided for under R307-415-5 a(3) or under regulations
promulgated under Title IV of the Act for the permitting of Title IV affected
sources under the Acid Rain Program, the director shall take final action on
each permit application, including a request for permit modification or
renewal, within 18 months after receiving a complete application.
(3) The director shall promptly provide
notice to the applicant of whether the application is complete. Unless the
director requests additional information or otherwise notifies the applicant of
incompleteness within 60 days of receipt of an application, the application
shall be deemed complete. A completeness determination shall not be required
for minor permit modifications.
(4)
The director shall provide a statement that sets forth the legal and factual
basis for the draft permit conditions, including references to the applicable
statutory or regulatory provisions. The director shall send this statement to
EPA and to any other person who requests it.
(5) The submittal of a complete application
shall not affect the requirement that any source have an approval order under
R307-401.