Utah Admin. Code R313-25-31.5 - Calculation of Closure Costs
(1) In
order to demonstrate the adequacy of closure, stabilization, post-closure, and
institutional control funding in compliance with Section
19-3-104
and Subsection
R313-25-31(1)(b),
the applicant or licensee shall establish the level of costs that an
independent contractor would incur by reliance on one of two methods, as
follows:
(a) using the current edition of RS
Means Facility Construction Cost Data; or
(b) using a competitive site-specific
estimate.
(2) Any
proposed competitive site-specific estimate submitted pursuant to Subsection
R313-25-31(14)(b)(i)
shall:
(a) be certified by a professional
engineer or geologist licensed in Utah; and
(b) include sufficient detail so that the
Director can determine that the cost estimate would be sufficient to provide
for closure, post closure costs, and institutional control costs in compliance
with Chapter 19-3 and Section
R313-25-31.
(3) In the intervening four years
following Director approval of a competitive site-specific estimate, a proposed
cost estimate that accounts for current site conditions or changes to site
conditions under Subsection
R313-25-31(14)(b)(ii)
shall be submitted by using either:
(a) the
current edition of RS Means Facility Construction Cost Data; or
(b) the cost estimating rationale developed
in the approved competitive site-specific estimate.