Utah Admin. Code R315-265-1082 - Air Emission Standards for Tanks, Surface Impoundments, and Containers - Schedule for Implementation of Air Emission Standards
(a) Owners or operators of facilities
existing on December 6, 1996 and subject to Sections
R315-265-170
through
R315-265-178,
Sections
R315-265-190
through
R315-265-202,
and Sections
R315-265-220
through
R315-265-231
shall meet the following requirements:
(1)
Install and begin operation of all control equipment or waste management units
required to comply with Sections R315-265-1080 through R315-265-1090 and
complete modifications of production or treatment processes to satisfy
exemption criteria in accordance with Subsection R315-265-1083(c) by December
6, 1996, except as provided for in Subsection R315-265-1082(a)(2).
(2) If control equipment or waste management
units required to comply with Sections R315-265-1080 through R315-265-1090
cannot be installed and if operation or modifications of production or
treatment processes to satisfy exemption criteria in accordance with Subsection
R315-265-1083(c) cannot be completed by December 6, 1996, the owner or operator
shall:
(i) Install and begin operation of the
control equipment and waste management units, and complete modifications of
production or treatment processes as soon as possible but no later than
December 8, 1997.
(ii) Prepare an
implementation schedule that includes the following information: specific
calendar dates for award of contracts or issuance of purchase orders for
control equipment, waste management units, and production or treatment process
modifications; initiation of on-site installation of control equipment or waste
management units, and modifications of production or treatment processes;
completion of control equipment or waste management unit installation, and
production or treatment process modifications; and performance of testing to
demonstrate that the installed equipment or waste management units, and
modified production or treatment processes meet the applicable standards of
Sections R315-265-1080 through R315-265-1090.
(iii) For facilities subject to the
recordkeeping requirements of Section
R315-265-73,
the owner or operator shall enter the implementation schedule specified in
Subsection R315-265-1082(a)(2)(ii) in the operating record no later than
December 6, 1996.
(iv) For
facilities not subject to Section
R315-265-73,
the owner or operator shall enter the implementation schedule specified in
Subsection R315-265-1082(a)(2)(ii) in a permanent, readily available file
located at the facility no later than December 6, 1996.
(b) Owners or operators of
facilities and units in existence on the effective date of a statutory, EPA, or
Utah regulatory amendment that renders the facility subject to Sections
R315-265-170
through
R315-265-178,
Sections
R315-265-190
through
R315-265-202,
or Sections
R315-265-220
through
R315-265-231
shall meet the following requirements:
(1)
Install and begin operation of control equipment or waste management units
required to comply with Sections R315-265-1080 through R315-265-1090, and
complete modifications of production or treatment processes to satisfy
exemption criteria of Subsection R315-265-1083(c) by the effective date of the
amendment, except as provided for in Subsection R315-265-1082(b)(2).
(2) If control equipment or waste management
units required to comply with Sections R315-265-1080 through R315-265-1090
cannot be installed and begin operation, or if modifications of production or
treatment processes to satisfy exemption criteria of Subsection
R315-265-1083(c) cannot be completed by the effective date of the amendment,
the owner or operator shall:
(i) Install and
begin operation of the control equipment or waste management unit, and complete
modification of production or treatment processes as soon as possible but no
later than 30 months after the effective date of the amendment.
(ii) For facilities subject to the
recordkeeping requirements of Section
R315-265-73,
enter and maintain the implementation schedule specified in Subsection
R315-265-1082(a)(2)(ii) in the operating record no later than the effective
date of the amendment, or
(iii) For
facilities not subject to Section
R315-265-73,
the owner or operator shall enter and maintain the implementation schedule
specified in Subsection R315-265-1082(a)(2)(ii) in a permanent, readily
available file located at the facility site no later than the effective date of
the amendment.
(c) Owners and operators of facilities and
units that become newly subject to the requirements of Sections R315-265-1080
through R315-265-1090 after December 8, 1997 due to an action other than those
described in Subsection R315-265-1082(b) shall comply with all applicable
requirements immediately, for example, shall have control devices installed and
operating on the date the facility or unit becomes subject to Sections
R315-265-1080 through R315-265-1090; the 30-month implementation schedule does
not apply.
(d) The Director may
elect to extend the implementation date for control equipment at a facility , on
a case by case basis, to a date later than December 8, 1997, if special
circumstances that are beyond the facility owner's or operator's control delay
installation or operation of control equipment, and the owner or operator has
made all reasonable and prudent attempts to comply with the requirements of
Sections R315-265-1080 through R315-265-1090.