Utah Admin. Code R315-265-1085 - Air Emission Standards for Tanks, Surface Impoundments, and Containers - Standards: Tanks
(a) The provisions
of Section R315-265-1085 apply to the control of air pollutant emissions from
tanks for which Subsection R315-265-1083(b) references the use of Section
R315-265-1085 for such air emission control.
(b) The owner or operator shall control air
pollutant emissions from each tank subject to Section R315-265-1085 in
accordance with the following requirements, as applicable:
(1) For a tank that manages hazardous waste
that meets all of the conditions specified in Subsections
R315-265-1085(b)(1)(i) through R315-265-1085(b)(1)(iii), the owner or operator
shall control air pollutant emissions from the tank in accordance with the Tank
Level 1 controls specified in Subsection R315-265-1085(c) or the Tank Level 2
controls specified in Subsection R315-265-1085(d).
(i) The hazardous waste in the tank has a
maximum organic vapor pressure which is less than the maximum organic vapor
pressure limit for the tank's design capacity category as follows:
(A) For a tank design capacity equal to or
greater than 151 m3, the maximum organic vapor pressure limit for the tank is
5.2 kPa.
(B) For a tank design
capacity equal to or greater than 75 m3 but less than 151 m3, the maximum
organic vapor pressure limit for the tank is 27.6 kPa.
(C) For a tank design capacity less than 75
m3, the maximum organic vapor pressure limit for the tank is 76.6
kPa.
(ii) The hazardous
waste in the tank is not heated by the owner or operator to a temperature that
is greater than the temperature at which the maximum organic vapor pressure of
the hazardous waste is determined for the purpose of complying with Subsection
R315-265-1085(b)(1)(i).
(iii) The
hazardous waste in the tank is not treated by the owner or operator using a
waste stabilization process, as defined in Section R315-265-1081.
(2) For a tank that manages
hazardous waste that does not meet all of the conditions specified in
Subsections R315-265-1085(b)(1)(i) through R315-265-1085(b)(1)(iii), the owner
or operator shall control air pollutant emissions from the tank by using Tank
Level 2 controls in accordance with the requirements of Subsection
R315-265-1085(d). Examples of tanks required to use Tank Level 2 controls
include: A tank used for a waste stabilization process; and a tank for which
the hazardous waste in the tank has a maximum organic vapor pressure that is
equal to or greater than the maximum organic vapor pressure limit for the
tank's design capacity category as specified in Subsection
R315-265-1085(b)(1)(i).
(c) Owners and operators controlling air
pollutant emissions from a tank using Tank Level 1 controls shall meet the
requirements specified in Subsections R315-265-1085(c)(1) through
R315-265-1085(c)(4):
(1) The owner or
operator shall determine the maximum organic vapor pressure for a hazardous
waste to be managed in the tank using Tank Level 1 controls before the first
time the hazardous waste is placed in the tank. The maximum organic vapor
pressure shall be determined using the procedures specified in Subsection
R315-265-1084(c). Thereafter, the owner or operator shall perform a new
determination if changes to the hazardous waste managed in the tank could
potentially cause the maximum organic vapor pressure to increase to a level
that is equal to or greater than the maximum organic vapor pressure limit for
the tank design capacity category specified in Subsection
R315-265-1085(b)(1)(i), as applicable to the tank.
(2) The tank shall be equipped with a fixed
roof designed to meet the following specifications:
(i) The fixed roof and its closure devices
shall be designed to form a continuous barrier over the entire surface area of
the hazardous waste in the tank. The fixed roof may be a separate cover
installed on the tank, for example, a removable cover mounted on an open-top
tank, or may be an integral part of the tank structural design, for example, a
horizontal cylindrical tank equipped with a hatch.
(ii) The fixed roof shall be installed in a
manner such that there are no visible cracks, holes, gaps, or other open spaces
between roof section joints or between the interface of the roof edge and the
tank wall.
(iii) Each opening in
the fixed roof, and any manifold system associated with the fixed roof, shall
be either:
(A) Equipped with a closure device
designed to operate such that if the closure device is secured in the closed
position there are no visible cracks, holes, gaps, or other open spaces in the
closure device or between the perimeter of the opening and the closure device;
or
(B) Connected by a closed-vent
system that is vented to a control device. The control device shall remove or
destroy organics in the vent stream, and shall be operating if hazardous waste
is managed in the tank, except as provided for in Subsections
R315-265-1085(c)(2)(iii)(B)(1) and (2).
(1)
During periods it is necessary to provide access to the tank for performing the
activities of Subsection R315-265-1085(c)(2)(iii)(B)(2), venting of the vapor
headspace underneath the fixed roof to the control device is not required,
opening of closure devices is allowed, and removal of the fixed roof is
allowed. Following completion of the activity , the owner or operator shall
promptly secure the closure device in the closed position or reinstall the
cover, as applicable, and resume operation of the control device.
(2) During periods of routine inspection ,
maintenance, or other activities needed for normal operations, and for the
removal of accumulated sludge or other residues from the bottom of the
tank.
(iv)
The fixed roof and its closure devices shall be made of suitable materials that
will minimize exposure of the hazardous waste to the atmosphere, to the extent
practical, and will maintain the integrity of the fixed roof and closure
devices throughout their intended service life. Factors to be considered when
selecting the materials for and designing the fixed roof and closure devices
shall include: Organic vapor permeability, the effects of any contact with the
hazardous waste or its vapors managed in the tank; the effects of outdoor
exposure to wind, moisture, and sunlight; and the operating practices used for
the tank on which the fixed roof is installed.
(3) If a hazardous waste is in the tank, the
fixed roof shall be installed with each closure device secured in the closed
position except as follows:
(i) Opening of
closure devices or removal of the fixed roof is allowed at the following times:
(A) To provide access to the tank for
performing routine inspection , maintenance, or other activities needed for
normal operations. Examples of such activities include those times when a
worker needs to open a port to sample the liquid in the tank, or when a worker
needs to open a hatch to maintain or repair equipment. Following completion of
the activity , the owner or operator shall promptly secure the closure device in
the closed position or reinstall the cover, as applicable, to the
tank.
(B) To remove accumulated
sludge or other residues from the bottom of tank.
(ii) Opening of a spring-loaded
pressure-vacuum relief valve, conservation vent, or similar type of pressure
relief device which vents to the atmosphere is allowed during normal operations
for the purpose of maintaining the tank internal pressure in accordance with
the tank design specifications. The device shall be designed to operate with no
detectable organic emissions if the device is secured in the closed position.
The settings at which the device opens shall be established such that the
device remains in the closed position whenever the tank internal pressure is
within the internal pressure operating range determined by the owner or
operator based on the tank manufacturer recommendations, applicable
regulations, fire protection and prevention codes, standard engineering codes
and practices, or other requirements for the safe handling of flammable,
ignitable, explosive, reactive, or hazardous materials. Examples of normal
operating conditions that may require these devices to open are during those
times when the tank internal pressure exceeds the internal pressure operating
range for the tank as a result of loading operations or diurnal ambient
temperature fluctuations.
(iii)
Opening of a safety device, as defined in Section R315-265-1081, is allowed at
any time conditions require doing so to avoid an unsafe condition.
(4) The owner or operator shall
inspect the air emission control equipment in accordance with the following
requirements.
(i) The fixed roof and its
closure devices shall be visually inspected by the owner or operator to check
for defects that could result in air pollutant emissions. Defects include, but
are not limited to, visible cracks, holes, or gaps in the roof sections or
between the roof and the tank wall; broken, cracked, or otherwise damaged seals
or gaskets on closure devices; and broken or missing hatches, access covers,
caps, or other closure devices.
(ii) The owner or operator shall perform an
initial inspection of the fixed roof and its closure devices on or before the
date that the tank becomes subject to this section. Thereafter, the owner or
operator shall perform the inspections at least once every year except under
the special conditions provided for in Subsection R315-265-1085(l).
(iii) In the event that a defect is detected,
the owner or operator shall repair the defect in accordance with the
requirements of Subsection R315-265-1085(k).
(iv) The owner or operator shall maintain a
record of the inspection in accordance with the requirements specified in
Subsection R315-265-1090(b).
(d) Owners and operators controlling air
pollutant emissions from a tank using Tank Level 2 controls shall use one of
the following tanks:
(1) A fixed-roof tank
equipped with an internal floating roof in accordance with the requirements
specified in Subsection R315-265-1085(e);
(2) A tank equipped with an external floating
roof in accordance with the requirements specified in Subsection
R315-265-1085(f);
(3) A tank vented
through a closed-vent system to a control device in accordance with the
requirements specified in Subsection R315-265-1085(g);
(4) A pressure tank designed and operated in
accordance with the requirements specified in Subsection R315-265-1085(h);
or
(5) A tank located inside an
enclosure that is vented through a closed-vent system to an enclosed combustion
control device in accordance with the requirements specified in Subsection
R315-265-1085(i).
(e)
The owner or operator who controls air pollutant emissions from a tank using a
fixed-roof with an internal floating roof shall meet the requirements specified
in Subsections R315-265-1085(e)(1) through R315-265-1085(e)(3).
(1) The tank shall be equipped with a fixed
roof and an internal floating roof in accordance with the following
requirements:
(i) The internal floating roof
shall be designed to float on the liquid surface except when the floating roof
must be supported by the leg supports.
(ii) The internal floating roof shall be
equipped with a continuous seal between the wall of the tank and the floating
roof edge that meets either of the following requirements:
(A) A single continuous seal that is either a
liquid-mounted seal or a metallic shoe seal, as defined in Section
R315-265-1081; or
(B) Two
continuous seals mounted one above the other. The lower seal may be a
vapor-mounted seal.
(iii) The internal floating roof shall meet
the following specifications:
(A) Each
opening in a noncontact internal floating roof except for automatic bleeder
vents, vacuum breaker vents, and the rim space vents is to provide a projection
below the liquid surface.
(B) Each
opening in the internal floating roof shall be equipped with a gasketed cover
or a gasketed lid except for leg sleeves, automatic bleeder vents, rim space
vents, column wells, ladder wells, sample wells, and stub drains.
(C) Each penetration of the internal floating
roof for the purpose of sampling shall have a slit fabric cover that covers at
least 90 percent of the opening.
(D) Each automatic bleeder vent and rim space
vent shall be gasketed.
(E) Each
penetration of the internal floating roof that allows for passage of a ladder
shall have a gasketed sliding cover.
(F) Each penetration of the internal floating
roof that allows for passage of a column supporting the fixed roof shall have a
flexible fabric sleeve seal or a gasketed sliding cover.
(2) The owner or operator shall
operate the tank in accordance with the following requirements:
(i) If the floating roof is resting on the
leg supports, the process of filling, emptying, or refilling shall be
continuous and shall be completed as soon as practical.
(ii) Automatic bleeder vents are to be set
closed at all times when the roof is floating, except when the roof is being
floated off or is being landed on the leg supports.
(iii) Prior to filling the tank, each cover,
access hatch, gauge float well or lid on any opening in the internal floating
roof shall be bolted or fastened closed, for example, no visible gaps. Rim
space vents are to be set to open only if the internal floating roof is not
floating or if the pressure beneath the rim exceeds the manufacturer's
recommended setting.
(3)
The owner or operator shall inspect the internal floating roof in accordance
with the procedures specified as follows:
(i)
The floating roof and its closure devices shall be visually inspected by the
owner or operator to check for defects that could result in air pollutant
emissions. Defects include, but are not limited to: The internal floating roof
is not floating on the surface of the liquid inside the tank; liquid has
accumulated on top of the internal floating roof; any portion of the roof seals
have detached from the roof rim; holes, tears, or other openings are visible in
the seal fabric; the gaskets no longer close off the hazardous waste surface
from the atmosphere; or the slotted membrane has more than 10 percent open
area.
(ii) The owner or operator
shall inspect the internal floating roof components as follows except as
provided in Subsection R315-265-1085(e)(3)(iii):
(A) Visually inspect the internal floating
roof components through openings on the fixed-roof, for example, manholes and
roof hatches, at least once every 12 months after initial fill, and
(B) Visually inspect the internal floating
roof, primary seal, secondary seal, if one is in service, gaskets, slotted
membranes, and sleeve seals, if any, each time the tank is emptied and degassed
and at least every 10 years.
(iii) As an alternative to performing the
inspections specified in Subsection R315-265-1085(e)(3)(ii) for an internal
floating roof equipped with two continuous seals mounted one above the other,
the owner or operator may visually inspect the internal floating roof, primary
and secondary seals, gaskets, slotted membranes, and sleeve seals, if any, each
time the tank is emptied and degassed and at least every 5 years.
(iv) Prior to each inspection required by
Subsections R315-265-1085(e)(3)(ii) or R315-265-1085(e)(3)(iii), the owner or
operator shall notify the Director in advance of each inspection to provide the
Director with the opportunity to have an observer present during the
inspection . The owner or operator shall notify the Director of the date and
location of the inspection as follows:
(A)
Prior to each visual inspection of an internal floating roof in a tank that has
been emptied and degassed, written notification shall be prepared and sent by
the owner or operator so that it is received by the Director at least 30
calendar days before refilling the tank except when an inspection is not
planned as provided for in Subsection R315-265-1085(e)(3)(iv)(B).
(B) If a visual inspection is not planned and
the owner or operator could not have known about the inspection 30 calendar
days before refilling the tank, the owner or operator shall notify the Director
as soon as possible, but no later than 7 calendar days before refilling of the
tank. This notification may be made by telephone and immediately followed by a
written explanation for why the inspection is unplanned. Alternatively, written
notification, including the explanation for the unplanned inspection , may be
sent so that it is received by the Director at least 7 calendar days before
refilling the tank.
(v)
In the event that a defect is detected, the owner or operator shall repair the
defect in accordance with the requirements of Subsection
R315-265-1085(k).
(vi) The owner or
operator shall maintain a record of the inspection in accordance with the
requirements specified in Subsection R315-265-1090(b).
(4) Safety devices, as defined in Section
R315-265-1081, may be installed and operated as necessary on any tank complying
with the requirements of Subsection R315-265-1085(e).
(f) The owner or operator who controls air
pollutant emissions from a tank using an external floating roof shall meet the
requirements specified in Subsections R315-265-1085(f)(1) through
R315-265-1085(f)(3).
(1) The owner or
operator shall design the external floating roof in accordance with the
following requirements:
(i) The external
floating roof shall be designed to float on the liquid surface except if the
floating roof must be supported by the leg supports.
(ii) The floating roof shall be equipped with
two continuous seals, one above the other, between the wall of the tank and the
roof edge. The lower seal is referred to as the primary seal, and the upper
seal is referred to as the secondary seal.
(A) The primary seal shall be a
liquid-mounted seal or a metallic shoe seal, as defined in Section
R315-265-1081. The total area of the gaps between the tank wall and the primary
seal shall not exceed 212 square centimeters (cm2) per meter of tank diameter,
and the width of any portion of these gaps shall not exceed 3.8 centimeters
(cm). If a metallic shoe seal is used for the primary seal, the metallic shoe
seal shall be designed so that one end extends into the liquid in the tank and
the other end extends a vertical distance of at least 61 centimeters above the
liquid surface.
(B) The secondary
seal shall be mounted above the primary seal and cover the annular space
between the floating roof and the wall of the tank. The total area of the gaps
between the tank wall and the secondary seal shall not exceed 21.2 square
centimeters (cm2) per meter of tank diameter, and the width of any portion of
these gaps shall not exceed 1.3 centimeters (cm).
(iii) The external floating roof shall meet
the following specifications:
(A) Except for
automatic bleeder vents, vacuum breaker vents, and rim space vents, each
opening in a noncontact external floating roof shall provide a projection below
the liquid surface.
(B) Except for
automatic bleeder vents, rim space vents, roof drains, and leg sleeves, each
opening in the roof shall be equipped with a gasketed cover, seal, or
lid.
(C) Each access hatch and each
gauge float well shall be equipped with a cover designed to be bolted or
fastened if the cover is secured in the closed position.
(D) Each automatic bleeder vent and each rim
space vent shall be equipped with a gasket.
(E) Each roof drain that empties into the
liquid managed in the tank shall be equipped with a slotted membrane fabric
cover that covers at least 90 percent of the area of the opening.
(F) Each unslotted and slotted guide pole
well shall be equipped with a gasketed sliding cover or a flexible fabric
sleeve seal.
(G) Each unslotted
guide pole shall be equipped with a gasketed cap on the end of the
pole.
(H) Each slotted guide pole
shall be equipped with a gasketed float or other device which closes off the
liquid surface from the atmosphere.
(I) Each gauge hatch and each sample well
shall be equipped with a gasketed cover.
(2) The owner or operator shall operate the
tank in accordance with the following requirements:
(i) If the floating roof is resting on the
leg supports, the process of filling, emptying, or refilling shall be
continuous and shall be completed as soon as practical.
(ii) Except for automatic bleeder vents, rim
space vents, roof drains, and leg sleeves, each opening in the roof shall be
secured and maintained in a closed position at all times except when the
closure device must be open for access.
(iii) Covers on each access hatch and each
gauge float well shall be bolted or fastened when secured in the closed
position.
(iv) Automatic bleeder
vents shall be set closed at all times if the roof is floating, except if the
roof is being floated off or is being landed on the leg supports.
(v) Rim space vents shall be set to open only
at those times that the roof is being floated off the roof leg supports or if
the pressure beneath the rim seal exceeds the manufacturer's recommended
setting.
(vi) The cap on the end of
each unslotted guide pole shall be secured in the closed position at all times
except if measuring the level or collecting samples of the liquid in the
tank.
(vii) The cover on each gauge
hatch or sample well shall be secured in the closed position at all times
except if the hatch or well must be opened for access.
(viii) Both the primary seal and the
secondary seal shall completely cover the annular space between the external
floating roof and the wall of the tank in a continuous fashion except during
inspections.
(3) The
owner or operator shall inspect the external floating roof in accordance with
the procedures specified as follows:
(i) The
owner or operator shall measure the external floating roof seal gaps in
accordance with the following requirements:
(A) The owner or operator shall perform
measurements of gaps between the tank wall and the primary seal within 60
calendar days after initial operation of the tank following installation of the
floating roof and, thereafter, at least once every five years.
(B) The owner or operator shall perform
measurements of gaps between the tank wall and the secondary seal within 60
calendar days after initial operation of the tank following installation of the
floating roof and, thereafter, at least once every year .
(C) If a tank ceases to hold hazardous waste
for a period of one year or more, subsequent introduction of hazardous waste
into the tank shall be considered an initial operation for the purposes of
Subsections R315-265-1085(f)(3)(i)(A) and R315-265-1085(f)(3)(i)(B).
(D) The owner or operator shall determine the
total surface area of gaps in the primary seal and in the secondary seal
individually using the following procedure:
(1) The seal gap measurements shall be
performed at one or more floating roof levels if the roof is floating off the
roof supports.
(2) Seal gaps, if
any, shall be measured around the entire perimeter of the floating roof in each
place where a 0.32-centimeter (cm) diameter uniform probe passes freely,
without forcing or binding against the seal, between the seal and the wall of
the tank and measure the circumferential distance of each such
location.
(3) For a seal gap
measured under Subsection R315-265-1085(f)(3), the gap surface area shall be
determined by using probes of various widths to measure accurately the actual
distance from the tank wall to the seal and multiplying each such width by its
respective circumferential distance.
(4) The total gap area shall be calculated by
adding the gap surface areas determined for each identified gap location for
the primary seal and the secondary seal individually, and then dividing the sum
for each seal type by the nominal diameter of the tank. These total gap areas
for the primary seal and secondary seal are then compared to the respective
standards for the seal type as specified in Subsection
R315-265-1085(f)(1)(ii).
(E) In the event that the seal gap
measurements do not conform to the specifications in Subsection
R315-265-1085(f)(1)(ii), the owner or operator shall repair the defect in
accordance with the requirements of Subsection R315-265-1085(k).
(F) The owner or operator shall maintain a
record of the inspection in accordance with the requirements specified in
Subsection R315-265-1090(b).
(ii) The owner or operator shall visually
inspect the external floating roof in accordance with the following
requirements:
(A) The floating roof and its
closure devices shall be visually inspected by the owner or operator to check
for defects that could result in air pollutant emissions. Defects include, but
are not limited to: Holes, tears, or other openings in the rim seal or seal
fabric of the floating roof; a rim seal detached from the floating roof; all or
a portion of the floating roof deck being submerged below the surface of the
liquid in the tank; broken, cracked, or otherwise damaged seals or gaskets on
closure devices; and broken or missing hatches, access covers, caps, or other
closure devices.
(B) The owner or
operator shall perform an initial inspection of the external floating roof and
its closure devices on or before the date that the tank becomes subject to
Section R315-265-1085. Thereafter, the owner or operator shall perform the
inspections at least once every year except for the special conditions provided
for in Subsection R315-265-1085(l).
(C) In the event that a defect is detected,
the owner or operator shall repair the defect in accordance with the
requirements of Subsection R315-265-1085(k).
(D) The owner or operator shall maintain a
record of the inspection in accordance with the requirements specified in
Subsection R315-265-1090(b).
(iii) Prior to each inspection required by
Subsections R315-265-1085(f)(3)(i) or R315-265-1085(f)(3)(ii), the owner or
operator shall notify the Director in advance of each inspection to provide the
Director with the opportunity to have an observer present during the
inspection . The owner or operator shall notify the Director of the date and
location of the inspection as follows:
(A)
Prior to each inspection to measure external floating roof seal gaps as
required under Subsection R315-265-1085(f)(3)(i), written notification shall be
prepared and sent by the owner or operator so that it is received by the
Director at least 30 calendar days before the date the measurements are
scheduled to be performed.
(B)
Prior to each visual inspection of an external floating roof in a tank that has
been emptied and degassed, written notification shall be prepared and sent by
the owner or operator so that it is received by the Director at least 30
calendar days before refilling the tank except when an inspection is not
planned as provided for in Subsection R315-265-1085(f)(3)(iii)(C).
(C) If a visual inspection is not planned and
the owner or operator could not have known about the inspection 30 calendar
days before refilling the tank, the owner or operator shall notify the Director
as soon as possible, but no later than 7 calendar days before refilling of the
tank. This notification may be made by telephone and immediately followed by a
written explanation for why the inspection is unplanned. Alternatively, written
notification, including the explanation for the unplanned inspection , may be
sent so that it is received by the Director at least 7 calendar days before
refilling the tank.
(4) Safety devices, as defined in Section
R315-265-1081, may be installed and operated as necessary on any tank complying
with the requirements of Subsection R315-265-1085(f).
(g) The owner or operator who controls air
pollutant emissions from a tank by venting the tank to a control device shall
meet the requirements specified in Subsections R315-265-1085(g)(1) through
R315-265-1085(g)(3).
(1) The tank shall be
covered by a fixed roof and vented directly through a closed-vent system to a
control device in accordance with the following requirements:
(i) The fixed roof and its closure devices
shall be designed to form a continuous barrier over the entire surface area of
the liquid in the tank.
(ii) Each
opening in the fixed roof not vented to the control device shall be equipped
with a closure device. If the pressure in the vapor headspace underneath the
fixed roof is less than atmospheric pressure when the control device is
operating, the closure devices shall be designed to operate such that when the
closure device is secured in the closed position there are no visible cracks,
holes, gaps, or other open spaces in the closure device or between the
perimeter of the cover opening and the closure device. If the pressure in the
vapor headspace underneath the fixed roof is equal to or greater than
atmospheric pressure when the control device is operating, the closure device
shall be designed to operate with no detectable organic emissions.
(iii) The fixed roof and its closure devices
shall be made of suitable materials that will minimize exposure of the
hazardous waste to the atmosphere, to the extent practical, and will maintain
the integrity of the fixed roof and closure devices throughout their intended
service life. Factors to be considered when selecting the materials for and
designing the fixed roof and closure devices shall include: Organic vapor
permeability, the effects of any contact with the liquid and its vapor managed
in the tank; the effects of outdoor exposure to wind, moisture, and sunlight;
and the operating practices used for the tank on which the fixed roof is
installed.
(iv) The closed-vent
system and control device shall be designed and operated in accordance with the
requirements of Section R315-265-1088.
(2) If a hazardous waste is in the tank, the
fixed roof shall be installed with each closure device secured in the closed
position and the vapor headspace underneath the fixed roof vented to the
control device except as follows:
(i) Venting
to the control device is not required, and opening of closure devices or
removal of the fixed roof is allowed at the following times:
(A) To provide access to the tank for
performing routine inspection , maintenance, or other activities needed for
normal operations. Examples of such activities include those times when a
worker needs to open a port to sample liquid in the tank, or when a worker
needs to open a hatch to maintain or repair equipment. Following completion of
the activity , the owner or operator shall promptly secure the closure device in
the closed position or reinstall the cover, as applicable, to the
tank.
(B) To remove accumulated
sludge or other residues from the bottom of a tank.
(ii) Opening of a safety device, as defined
in Section R315-265-1081, is allowed at any time conditions require doing so to
avoid an unsafe condition.
(3) The owner or operator shall inspect and
monitor the air emission control equipment in accordance with the following
procedures:
(i) The fixed roof and its
closure devices shall be visually inspected by the owner or operator to check
for defects that could result in air pollutant emissions. Defects include, but
are not limited to, visible cracks, holes, or gaps in the roof sections or
between the roof and the tank wall; broken, cracked, or otherwise damaged seals
or gaskets on closure devices; and broken or missing hatches, access covers,
caps, or other closure devices.
(ii) The closed-vent system and control
device shall be inspected and monitored by the owner or operator in accordance
with the procedures specified in Section R315-265-1088.
(iii) The owner or operator shall perform an
initial inspection of the air emission control equipment on or before the date
that the tank becomes subject to Section R315-265-1085. Thereafter, the owner
or operator shall perform the inspections at least once every year except for
the special conditions provided for in Subsection R315-265-1085(l).
(iv) In the event that a defect is detected,
the owner or operator shall repair the defect in accordance with the
requirements of Subsection R315-265-1085(k).
(v) The owner or operator shall maintain a
record of the inspection in accordance with the requirements specified in
Subsection R315-265-1090(b).
(h) The owner or operator who controls air
pollutant emissions by using a pressure tank shall meet the following
requirements.
(1) The tank shall be designed
not to vent to the atmosphere as a result of compression of the vapor headspace
in the tank during filling of the tank to its design capacity.
(2) All tank openings shall be equipped with
closure devices designed to operate with no detectable organic emissions as
determined using the procedure specified in Subsection
R315-265-1084(d).
(3) If a
hazardous waste is in the tank, the tank shall be operated as a closed system
that does not vent to the atmosphere except under either of the following
conditions as specified in Subsections R315-265-1085(h)(3)(i) or
R315-265-1085(h)(3)(ii).
(i) At those times
when opening of a safety device, as defined in Section R315-265-1081, is
required to avoid an unsafe condition.
(ii) At those times when purging of inerts
from the tank is required and the purge stream is routed to a closed-vent
system and control device designed and operated in accordance with the
requirements of Section R315-265-1088.
(i) The owner or operator who controls air
pollutant emissions by using an enclosure vented through a closed-vent system
to an enclosed combustion control device shall meet the requirements specified
in Subsections R315-265-1085(i)(1) through R315-265-1085(i)(4).
(1) The tank shall be located inside an
enclosure. The enclosure shall be designed and operated in accordance with the
criteria for a permanent total enclosure as specified in "Procedure T--Criteria
for and Verification of a Permanent or Temporary Total Enclosure" under
40
CFR 52.741, appendix B. The enclosure may
have permanent or temporary openings to allow worker access; passage of
material into or out of the enclosure by conveyor, vehicles, or other
mechanical means; entry of permanent mechanical or electrical equipment; or
direct airflow into the enclosure. The owner or operator shall perform the
verification procedure for the enclosure as specified in Section 5.0 to
"Procedure T--Criteria for and Verification of a Permanent or Temporary Total
Enclosure" initially when the enclosure is first installed and, thereafter,
annually.
(2) The enclosure shall
be vented through a closed-vent system to an enclosed combustion control device
that is designed and operated in accordance with the standards for either a
vapor incinerator, boiler, or process heater specified in Section
R315-265-1088.
(3) Safety devices,
as defined in Section R315-265-1081, may be installed and operated as necessary
on any enclosure, closed-vent system, or control device used to comply with the
requirements of Subsections R315-265-1085(i)(1) and
R315-265-1085(i)(2).
(4) The owner
or operator shall inspect and monitor the closed-vent system and control device
as specified in Section R315-265-1088.
(j) The owner or operator shall transfer
hazardous waste to a tank subject to Section R315-265-1085 in accordance with
the following requirements:
(1) Transfer of
hazardous waste , except as provided in Subsection R315-265-1085(j)(2), to the
tank from another tank subject to Section R315-265-1085 or from a surface
impoundment subject to Section R315-265-1086 shall be conducted using
continuous hard-piping or another closed system that does not allow exposure of
the hazardous waste to the atmosphere. For the purpose of complying with this
provision, an individual drain system is considered to be a closed system if it
meets the requirements of 40 CFR part 63, subpart RR--National Emission
Standards for Individual Drain Systems.
(2) The requirements of Subsection
R315-265-1085(j)(1) do not apply if transferring a hazardous waste to the tank
under any of the following conditions:
(i)
The hazardous waste meets the average VO concentration conditions specified in
Subsection R315-265-1083(c)(1) at the point of waste origination.
(ii) The hazardous waste has been treated by
an organic destruction or removal process to meet the requirements in
Subsection R315-265-1083(c)(2).
(iii) The hazardous waste meets the
requirements of Subsection R315-265-1083(c)(4).
(k) The owner or operator shall repair each
defect detected during an inspection performed in accordance with the
requirements of Subsections R315-265-1085(c)(4), R315-265-1085(e)(3),
R315-265-1085(f)(3), or R315-265-1085(g)(3) as follows:
(1) The owner or operator shall make first
efforts at repair of the defect no later than 5 calendar days after detection,
and repair shall be completed as soon as possible but no later than 45 calendar
days after detection except as provided in Subsection
R315-265-1085(k)(2).
(2) Repair of
a defect may be delayed beyond 45 calendar days if the owner or operator
determines that repair of the defect requires emptying or temporary removal
from service of the tank and no alternative tank capacity is available at the
site to accept the hazardous waste normally managed in the tank. In this case,
the owner or operator shall repair the defect the next time the process or unit
that is generating the hazardous waste managed in the tank stops operation.
Repair of the defect shall be completed before the process or unit resumes
operation.
(l) Following
the initial inspection and monitoring of the cover as required by the
applicable provisions of Sections R315-265-1080 through R315-265-1090,
subsequent inspection and monitoring may be performed at intervals longer than
one year under the following special conditions:
(1) In the case when inspecting or monitoring
the cover would expose a worker to dangerous, hazardous, or other unsafe
conditions, then the owner or operator may designate a cover as an "unsafe to
inspect and monitor cover" and comply with all of the following requirements:
(i) Prepare a written explanation for the
cover stating the reasons why the cover is unsafe to visually inspect or to
monitor, if required.
(ii) Develop
and implement a written plan and schedule to inspect and monitor the cover,
using the procedures specified in the applicable section of Sections
R315-265-1080 through R315-265-1090, as frequently as practicable during those
times when a worker can safely access the cover.
(2) In the case when a tank is buried
partially or entirely underground, an owner or operator is required to inspect
and monitor, as required by the applicable provisions of Section R315-265-1085,
only those portions of the tank cover and those connections to the tank, for
example, fill ports, access hatches, gauge wells, etc., that are located on or
above the ground surface.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.