Utah Admin. Code R33-111-301 - Performance Bonds for Construction Contracts
A performance bond is required for construction contracts exceeding $50,000, in the amount of 100% of the contract price. The performance bond shall be delivered by the contractor to the procurement unit within 14 days of the contractor receiving notice of the award of the construction contract. If a contractor fails to deliver the required performance bond, the contractor's bid or offer shall be rejected, its bid security may be enforced, and award of the contract may be made to the responsible bidder or offeror with the next lowest responsive bid or highest ranked offer.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.