Utah Admin. Code R647-2-114 - Revised Notice
1. Minor additions
or changes in the location of exploration operations do not require the
submittal of a revised notice of intention. A new or revised Notice of
Intention to Conduct Exploration (FORM MR-EXP) letter must be submitted when:
1.1. The proposed additions or changes will
occur outside the originally designated legal subdivision; or
1.2. For exploration operations under 5 acres
the proposed additions will cause the total unreclaimed surface disturbance to
increase by more than 1 acre or exceed 5 acres; or
1.3. For exploration operations over 5 acres,
the proposed additions or changes will cause an increase in the area of
disturbance previously approved.
2. In the event the Division or the operator
determine at the time a revision is submitted that the amount of the current
surety does not accurately reflect the potential cost to complete reclamation
at any particular point in time during the revised exploration operations, the
Division may undertake a recalculation of the surety amount as provided in
R647-2-111.3. If the recalculated amount is greater than the amount of the
existing surety, the revised operations may not be implemented until a revised
surety is filed with the Division.