Utah Admin. Code R649-3-21 - Well Completion and Filing of Well Logs
1. For the purposes of this rule only, a well
shall be determined to be completed when the well has been adequately worked to
be capable of producing oil or gas or when well testing as required by the
division is concluded.
2. Within 30
days after the completion of any well drilled or redrilled for the production
of oil or gas, Form 8, Well Completion or Recompletion Report and Log, shall be
filed with the division, together with a copy of the electric and radioactivity
logs, if run.
3. In addition, one
copy of any drillstem test reports, formation water analyses, porosity,
permeability or fluid saturation determinations, core analyses and lithologic
logs or sample descriptions if compiled, shall be filed with the
division.
4. As prescribed under
Subsection R649-2-12, Test and Surveys, the
directional, deviation or measurement-while-drilling (MWD) survey for a
horizontal well shall be filed within 30 days of being run. Such directional,
deviation or MWD survey specifically related to well location or well bore path
shall not be held confidential. Other MWD survey data that presents well log,
or other geological, geophysical, or engineering information may be held
confidential as provided in Subsection
R649-2-11, Confidentiality of
Well Log Information.