Utah Admin. Code R649-9-13 - Closure and Post Closure of E and P Recycling Facilities
(1) A plan for
final closure of an E and P recycling facility shall be submitted to the
division, for approval upon cessation of operations. The closure plan shall
include the following:
(a) Provisions for
removal of all equipment, buildings, fences and roads at the site;
(b) A plan to restore the impacted surface
area to a safe and stable condition or to the condition that existed before the
construction of the E and P recycling facility;
(c) Removal of solid and hazardous waste to
an appropriate nonhazardous solid waste facility or a hazardous waste disposal
facility as applicable, in accordance with the requirements of Title 19,
Chapter 6, Solid and Hazardous Waste Act and the associated rules;
(d) Removal of berms and disposal method for
liners;
(e) Plans and procedures
for sampling and testing soils and ground water at the site. The operator shall
notify the division at least 48 hours in advance to witness soil sampling;
(i) Soils shall meet division cleanup
standards or background levels whichever is less stringent;
(f) A post closure monitoring plan
if required by the division; and
(g) Proof of a signed post closure plan
agreement with the current landowner.
(2) During closure operations, the operator
shall maintain the E and P recycling facility to protect freshwater, public
health, safety and the environment.
(3) The bond for the E and P recycling
facility will be released when the division approved closure plan requirements
have been met, as determined by the division.