Utah Admin. Code R650-302-7 - Reporting and Reimbursement Cooperation Requirements
(1) An infrastructure grant recipient shall:
(a) cooperate with the division's reasonable
requests for site visits during and after the completion of the
project;
(b) provide any financial
records related to the project upon the division's request;
(c) provide the division with a progress
report twice yearly until the project's completion;
(d) provide economic development information
and supporting documentation of economic development goals achieved on an
annual basis or upon the division's request;
(e) provide economic development information
for up to 10 years following completion of the project; and
(f) provide the division with a description
and an itemized report detailing infrastructure grant expenditures or the
intended cost of any unspent awarded funds.
(2) An infrastructure grant recipient shall
provide the division with a final written itemized report after the project's
completion.
(3)
(a) An applicant shall provide the reports
referenced in Subsections (1) and (2) at least annually and no later than 60
days after the infrastructure grant agreement has expired; and
(b) Each report shall include assurances that
all monies awarded to the infrastructure grant recipient were spent on
planning, construction, or improvements in accordance with the recipient's
infrastructure grant application and the infrastructure grant
agreement.
(4) The
division, upon receipt of a reimbursement request, shall require recipients to
submit the following documentation:
(a) a
reimbursement request on a form provided by the division;
(b) copies of all invoices and evidence of
payment as well as records of volunteer labor or other in-kind donations for
work completed on the project;
(c)
several photos that show the recipient completed the project in accordance with
the recipient's application and the infrastructure grant agreement;
(d) a final report with a detailed
description of the project and any other information requested by the division;
and
(e) any other documentation the
division deems necessary to ensure compliance with the infrastructure grant
agreement.
(5) The
division may make partial advance reimbursement payments pursuant to the terms
of the grant agreement.
(6) Partial
advance reimbursement payments may not exceed 75% of expenses incurred during
the development of the project.
(7)
(a) The division shall in the program guide
provide a reference to which an applicant may refer to make a request and be
granted advance funding up to 75% of the award.
(b) The applicant shall state within the
application that they intend to request advance funding so that the advisory
committee may consider the advance funding request.
(c) The division may advance no more than 75%
of the infrastructure grant award to the recipient before the project is
completed.
(d) The recipient shall
make a written request to the division, outlining the need and use for advance
funds needed for project costs over the subsequent six-month period.
(e) The infrastructure grant recipient shall
provide the division with an itemized report detailing the expenditure of the
advance funds or the intended expenditure of the advanced
funds.
(8) All project
spending shall occur during the contract period.
(a) The division shall not reimburse the
recipient for costs incurred before or after the contract period.
(b) The infrastructure grant recipient shall
submit reimbursement documentation within 60 days following the contract
expiration.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.