Utah Admin. Code R653-10-3 - Grants for Secondary Water Meters
(1)
(a) The
board may issue a grant to an applicant to fund a project for the purchase and
installation of meters on an existing secondary water system that provides
secondary water service that is not metered.
(b) The board may not issue a grant under
this section to fund:
(i) metering of
secondary water for service that begins on or after the effective date of this
rule; or
(ii) the replacement or
repair of an existing secondary water meter.
(2)
(a) A
secondary water supplier with 7,000 secondary water connections or fewer may
receive no more than $5,000,000 in grant funds.
(b) A secondary water supplier with more than
7,000 secondary water connections may receive no more than $10,000,000 in grant
funds.
(c)
(i) Subject to the other provisions of this
rule, a grant may not exceed the following amounts for the costs associated
with a project, including installation or purchase of meters:
(A) for contracts completed with the board
calendar year 2022, 70% of the costs of a project;
(B) for contracts completed with the board
calendar year 2023, 70% of the costs of a project; and
(C) for contracts completed with the board
calendar year 2024, 65% of the costs of a project.
(d) A secondary water supplier may
pay up to 85% of its share of project costs under Subsection (c) through a 1%
interest loan from the board.
(3) Projects receiving project grant funds
under this rule must:
(a) commit all grant
funds through contract no later than December 31, 2024; and
(b) spend all grant funds and complete
construction of the project no later than December 31, 2026.