Utah Admin. Code R655-11-5C - Method of Analysis
A. Procedures are
available for selecting design earthquakes and associated site-specific motions
and for assessing the resistance of dams to these earthquake motions.
Procedures and techniques for evaluating the effects on dams from estimated
earthquake ground motions range from simplified concepts to comprehensive
dynamic analyses. When the degree of sophistication of analytical procedures is
far advanced, however, uncertainty is produced in the results by imperfect
knowledge of input parameters obtained through field exploration and laboratory
testing programs.
B. The extent or
scope of studies, investigations, tests and analyses which may be required to
adequately determine the seismic safety of a dam will vary from site to site.
In general, the following physical factors will indicate a high priority and a
greater degree of investigations and analysis:
1. Proximity to known active
faults.
2. Indications of
low-density materials in the dam or foundation.
3. Zones of high pore pressures or potential
liquefaction.
4. Indications of
marginal static stability.
5. Lack
of adequate construction records for existing dams.
C. Regardless of these factors, however, one
of the major considerations will be the "consequences of a failure". High and
moderate hazard structures with permanent pools which could result in loss of
life or extensive property damage from a failure will, in general, require a
greater scope of investigation and analyses.
D. Following are the general analysis
requirements, unless otherwise stipulated by the State Engineer, for MCE design
earthquakes:
1. Embankments, foundations, and
abutments not subject to liquefaction or significant strength loss:
a. For a maximum acceleration of 0.2g or
less, or a maximum acceleration of .35g or less if the embankment consists of
clay on a clay or bedrock foundation, a pseudo-static coefficient which is at
least 50 percent of the maximum peak bedrock acceleration at the site should be
used in the stability analysis. The minimum factor of safety in an analysis
should be 1.0.
b. For a maximum
peak acceleration greater than indicated above, a deformation and settlement
analysis should be performed to estimate anticipated total crest movement. The
evaluation should consider the potential for excess pore pressure generation
and be performed for both the upstream and downstream slopes of the dam. Total
crest movement should consider settlement and potential accumulation of
movement from both sides. The minimum factor of safety against overtopping
should be 2.0.
2.
Embankment, foundation, or abutment soils subject to liquefaction or
significant strength loss:
a. A
liquefaction/strength loss analysis should be completed with enough detail to
establish the boundaries of the liquefiable/strength loss soils and the
physical characteristics of the soil during and immediately following the
design earthquake.
b. A post
earthquake stability analysis should be performed to show that the embankment
is stable after liquefaction/strength loss occurs with a minimum factor of
safety of 1.2. The potential for excess pore pressure generation will be
considered.
c. Calculated
deformation and settlement of the embankment total crest movement should result
in a minimum factor of safety, against overtopping, of 3.0. Analyses will
consider liquefaction/strength loss and the potential for excess pore pressure
generation.
3. Other
more sophisticated analytical procedures may be required at the discretion of
the State Engineer, where conditions warrant greater detailed
studies.
E. In addition
to analysis of deformation and liquefaction, it will be necessary to assess the
potential for internal erosion and cracking. Judgment must be used to decide
whether or not erosion would tend to be self- healing as a result of
filtering.
F. Construction of dams
on active faults will not be allowed unless evidence is presented to, and
approved by, the State Engineer that the dam can safely withstand the
anticipated offset.
G. Evaluation
of a dam under OBE conditions should be completed by similar methods to those
described for the MCE. Under the OBE loading conditions the dam should
experience no significant damage.