Utah Admin. Code R930-8-6 - Relocation
The basic concept when relocating utility facilities is to functionally restore the Utility's operation facilities that existed before the department constructing a department project.
(1) The department incorporates by reference
23 CFR Section 645, subpart A (12/03/2021), for utility facility relocations
required by department projects. For deviations in determining whether the
Utility's real property
needed for the department project should be handled as a utility relocation or right-of-way acquisition, Subsection R930-7-13(5) shall apply.
(2) If the
Utility's regulatory and construction requirements can be met, the department
may require utility companies to jointly occupy trenches for a department
project. To the extent Utilities have valid agreements concerning the joint use
of above -ground facilities, the utility companies shall cooperate with each
other for the relocated joint use.
(3) If a Utility determines the existing
utility facilities do not need to be replaced or are not needed to maintain its
operational facilities, payment for the real property, which is needed to
accommodate the construction of the department project where the utility
facilities are located, shall be handled as a right-of-way
acquisition.