(1)
Selection
and installation criteria.
(a)
Original crane/derrick wire rope and replacement wire rope must be selected and
installed in accordance with the requirements of this section. Selection of
replacement wire rope must be in accordance with the recommendations of the
wire rope manufacturer, the crane/derrick manufacturer, or a qualified
person.
(b) Wire rope design
criteria: Wire rope (other than rotation resistant rope) must comply with
either Option (1) or Option (2) of this section, as follows:
(i)
Option (1). Wire rope must
comply with Section 5-1.7.1 of ASME B30.5-2007 except that section's paragraph
(c) must not apply.
(ii)
Option (2). Wire rope must be designed to have, in relation to the
crane's/derrick's rated capacity, a sufficient minimum breaking force and
design factor so that compliance with the applicable inspection provisions in
this section will be an effective means of preventing sudden rope
failure.
(c) Wire rope
must be compatible with the safe functioning of the crane/derrick.
(d)
Boom hoist reeving.
(i) Fiber core ropes must not be used for
boom hoist or luffing attachment reeving, except for derricks.
(ii) Rotation resistant ropes must be used
for boom hoist reeving only where the requirements of (e) of this subsection
are met.
(e)
Rotation resistant ropes.
(i)
Definitions.
Type I rotation resistant wire rope (Type I).
Type I rotation resistant rope is stranded rope constructed to have little or
no tendency to rotate or, if guided, transmits little or no torque. It has at
least 15 outer strands and comprises an assembly of at least 3 layers of
strands laid helically over a center in two operations. The direction of lay of
the outer strands is opposite to that of the underlying layer.
Type II rotation resistant wire rope (Type II).
Type II rotation resistant rope is stranded rope constructed to have resistance
to rotation. It has at least 10 outer strands and comprises an assembly of two
or more layers of strands laid helically over a center in two or 3 operations.
The direction of lay of the outer strands is opposite to that of the underlying
layer.
Type III rotation resistant wire rope (Type
III). Type III rotation resistant rope is stranded rope constructed to
have limited resistance to rotation. It has no more than 9 outer strands, and
comprises an assembly of two layers of strands laid helically over a center in
two operations. The direction of lay of the outer strands is opposite to that
of the underlying layer.
(ii)
Requirements.
(A) Types II and III with an operation design
factor of less than 5 must not be used for duty cycle or repetitive
lifts.
(B) Rotation resistant ropes
(including Types I, II and III) must have an operating design factor of no less
than 3.5.
(C) Type I must have an
operating design factor of no less than 5, except where the wire rope
manufacturer and the crane/derrick manufacturer approves the design factor, in
writing.
(D) Types II and III must
have an operating design factor of no less than 5, except where the
requirements of (e)(iii) of this subsection are met.
(iii) When Types II and III with an operation
design factor of less than 5 are used (for nonduty cycle, nonrepetitive lifts),
the following requirements must be met for each lifting operation:
(A) A qualified person must inspect the rope
in accordance with subsection (2)(a) of this section. The rope must be used
only if the qualified person determines that there are no deficiencies
constituting a hazard. In making this determination, more than one broken wire
in any one rope lay must be considered a hazard.
(B) Operations must be conducted in such a
manner and at such speeds as to minimize dynamic effects.
(C) Each lift made under these provisions
must be recorded in the monthly and annual inspection documents. Such prior
uses must be considered by the qualified person in determining whether to use
the rope again.
(iv)
Additional requirements for rotation resistant ropes for boom hoist reeving.
(A) Rotation resistant ropes must not be used
for boom hoist reeving, except where the requirements of (e)(iv)(B) of this
subsection are met.
(B) Rotation
resistant ropes may be used as boom hoist reeving when load hoists are used as
boom hoists for attachments such as luffing attachments or boom and mast
attachment systems. Under these conditions, all of the following requirements
must be met:
(I) The drum must provide a
first layer rope pitch diameter of not less than 18 times the nominal diameter
of the rope used.
(II) The
requirements in WAC
296-155-53400(44)
(irrespective of the date of manufacture of the crane/derrick), and WAC
296-155-53400(45).
(III) The requirements of ANSI/ASME
B30.5-2007, Section 5-1.3.2(a), (a)(2) through (a)(4), (b) and (d), except that
the minimum pitch diameter for sheaves used in multiple rope reeving is 18
times the nominal diameter of the rope used instead of the value of 16
specified in Section 5-1.3.2(d).
(IV) All sheaves used in the boom hoist
reeving system must have a rope pitch diameter of not less than 18 times the
nominal diameter of the rope used.
(V) The operating design factor for the boom
hoist reeving system must be not less than 5.
(VI) The operating design factor for these
ropes must be the total minimum breaking force of all parts of rope in the
system divided by the load imposed on the rope system when supporting the
static weights of the structure and the load within the crane's/derrick's rated
capacity.
(VII) When provided, a
power-controlled lowering system must be capable of handling rated capacities
and speeds as specified by the manufacturer.
(f) Wire rope clips used in
conjunction with wedge sockets must be attached to the unloaded dead end of the
rope only, except that the use of devices specifically designed for dead-ending
rope in a wedge socket is permitted.
(g) Socketing must be done in the manner
specified by the manufacturer of the wire rope or fitting.
(h) Prior to cutting a wire rope, seizings
must be placed on each side of the point to be cut. The length and number of
seizings must be in accordance with the wire rope manufacturer's instructions.
(2)
Inspection of
wire ropes.
(a)
Shift
inspection.
(i) A competent person
must begin a visual inspection prior to each shift the crane/derrick is used,
which must be completed before or during that shift. The inspection must
consist of observation of accessible wire ropes (running and standing) that are
likely to be in use during the shift for apparent deficiencies, including those
listed in (a)(ii) of this subsection. Untwisting (opening) of wire rope or
booming down is not required as part of this inspection.
(A) Category I. Apparent deficiencies in this
category include the following:
(I)
Distortion of the wire rope structure such as kinking, crushing, unstranding,
birdcaging, signs of core failure or steel core protrusion between the outer
strands.
(II) Corrosion.
(III) Electric arc damage (from a source
other than power lines) or heat damage.
(IV) Improperly applied end
connections.
(V) Corroded, cracked,
bent, or worn end connections (such as from severe service).
(B) Category II. Apparent
deficiencies in this category are:
(I)
Visibly broken wires in running wire ropes: 6 randomly distributed broken wires
in one rope lay or 3 broken wires in one strand in one rope lay, where a rope
lay is the length along the rope in which one strand makes a complete
revolution around the rope;
(II)
Visibly broken wires in rotation resistant ropes: Two randomly distributed
broken wires in 6 rope diameters or 4 randomly distributed broken wires in 30
rope diameters;
(III) Visibly
broken wires in pendants or standing wire ropes: More than two broken wires in
one rope lay located in rope beyond end connections and/or more than one broken
wire at an end connection; and
(IV)
A diameter reduction of more than 5% from nominal diameter.
(C) Category III. Apparent
deficiencies in this category include the following:
(I) In rotation resistant wire rope, core
protrusion or other distortion indicating core failure.
(II) Prior electrical contact with a power
line.
(III) A broken
strand.
(ii)
Critical review items. The competent person must give particular
attention to all of the following:
(A)
Rotation resistant wire rope in use.
(B) Wire rope being used for boom hoists and
luffing hoists, particularly at reverse bends.
(C) Wire rope at flange points, crossover
points and repetitive pickup points on drums.
(D) Wire rope at or near terminal
ends.
(E) Wire rope in contact with
saddles, equalizer sheaves or other sheaves where rope travel is
limited.
(iii)
Removal from service.
(A) If a
deficiency in Category I is identified, an immediate determination must be made
by the competent person as to whether the deficiency constitutes a safety
hazard. If the deficiency is determined to constitute a safety hazard,
operations involving use of the wire rope in question must be prohibited until:
(I) The wire rope is replaced; or
(II) If the deficiency is localized, the
problem is corrected by removing the damaged section of the wire rope; the
undamaged portion may continue to be used. Joining lengths of wire rope by
splicing is prohibited. If a rope is shortened under this subsection, you must
ensure that the drum will still have two wraps of wire when the load and/or
boom is in its lowest position.
(B) If a deficiency in Category II is
identified, operations involving use of the wire rope in question must be
prohibited until:
(I) You comply with the wire
rope manufacturer's established criterion for removal from service or a
different criterion that the wire rope manufacturer has approved in writing for
that specific wire rope;
(II) The
wire rope is replaced.
(C) If the deficiency is localized, the
problem is corrected by severing the wire rope in two; the undamaged portion
may continue to be used. Joining lengths of wire rope by splicing is
prohibited. If a rope is shortened under this subsection, you must ensure that
the drum will still have two wraps of wire when the load and/or boom is in its
lowest position. If a deficiency in category III is identified, operations
involving use of the wire rope in question must be prohibited until:
(I) The wire rope is replaced; or
(II) If the deficiency (other than power line
contact) is localized, the problem is corrected by severing the wire rope in
two; the undamaged portion may continue to be used. Joining lengths of wire
rope by splicing is prohibited. Repair of wire rope that contacted an energized
power line is also prohibited. If a rope is shortened under this subsection,
you must ensure that the drum will still have two wraps of wire when the load
and/or boom is in its lowest position.
(D) Where a wire rope is required to be
removed from service under this section, either the crane/derrick (as a whole)
or the hoist with that wire rope must be tagged-out, in accordance with WAC
296-155-53400(67),
until the wire rope is repaired or replaced.
(b) Monthly inspection.
(i) Each month an inspection must be
conducted in accordance with (a) of this subsection (shift
inspection).
(ii) The inspection
must include any deficiencies that the qualified person who conducts the annual
inspection determines under (c)(iii) of this subsection must be
monitored.
(iii) Wire ropes on a
crane/derrick must not be used until an inspection under this subsection
demonstrates that no corrective action under (a)(iii) of this subsection is
required.
(iv) This inspection must
be documented and be kept and made available upon request. Electronic records
are acceptable.
(c)
Annual/comprehensive, for cranes and derricks not covered by WAC
296-155-531 through
296-155-53214.
(i) At least every 12 months, wire ropes in
use on the crane/derrick must be inspected by a qualified person in accordance
with (a) of this subsection (shift inspection).
(ii) In addition, at least every 12 months,
the wire ropes in use on the crane/derrick must be inspected by a qualified
person, as follows:
(A) The inspection must
be for deficiencies of the types listed in (a)(i)(B) of this
subsection.
(B) The inspection must
be complete and thorough, covering the surface of the entire length of the wire
ropes, with particular attention given to all of the following:
(I) Critical review items listed in (a)(ii)
of this subsection.
(II) Those
sections that are normally hidden during shift and monthly
inspections.
(III) Wire rope in
contact with saddles, equalizer sheaves or other sheaves where rope travel is
limited.
(IV) Wire rope subject to
reverse bends.
(V) Wire rope
passing over sheaves.
(VI) Wire
rope at or near terminal ends.
(C) Exception: In the event an inspection
under (c)(ii) of this subsection is not feasible due to existing set-up and
configuration of the crane/derrick (such as where an assist crane is needed) or
due to site conditions (such as a dense urban setting). The inspection must
consist of observation of the working range plus 3 additional wraps (running
and standing) prior to use.
(iii) If a deficiency is identified, an
immediate determination must be made by the qualified person as to whether the
deficiency constitutes a safety hazard.
(A) If
the deficiency is determined to constitute a safety hazard, operations
involving the use of the wire rope in question is prohibited until:
(I) The wire rope is replaced; or
(II) If the deficiency is localized, the
problem is corrected by severing the wire rope in two; the undamaged portion
may continue to be used. Joining lengths of wire rope by splicing is
prohibited. If a rope is shortened under this subsection, you must ensure that
the drum will still have two wraps of wire when the load and/or boom is in its
lowest position.
(B) If
the qualified person determines that, though not presently a safety hazard, the
deficiency needs to be monitored, you must ensure that the deficiency is
checked in the monthly inspections.
(iv) This inspection must be documented and
be kept and made available upon request. Electronic records are acceptable.
(d) Rope lubricants that
are of the type that hinder inspection must not be used.
(3) All documents produced under this section
must be available, during the applicable document retention period, to all
persons who conduct inspections under this section.
Notes
Wash. Admin.
Code §
296-155-53404
Amended by
WSR
16-09-085, Filed 4/19/2016, effective
5/20/2016
Statutory Authority:
RCW
49.17.010,
49.17.040,
49.17.050,
49.17.060 and chapter 49.17 RCW,
and 29 C.F.R. 1926, Subpart CC. 13-02-068, § 296-155-53404, filed
12/31/12, effective 2/1/13. Statutory Authority:
RCW
49.17.010,
49.17.040,
49.17.050,
49.17.440,
49.17.060, and 29 C.F.R. 1926,
Subpart CC. 12-01-086, § 296-155-53404, filed 12/20/11, effective
2/1/12.