Wash. Admin. Code § 480-106-080 - Interconnection costs
(1) Any costs of
interconnection are the responsibility of the owner or operator of the
qualifying facility entering into a power contract under this chapter. The
utility must assess all reasonable interconnection and necessary system or
network upgrade costs the utility incurs against a qualifying facility on a
non-discriminatory basis.
(2) The
owner or operator of the qualifying facility must reimburse the utility for any
reasonable interconnection costs the utility may incur. Such reimbursement may
be made, at the utility's election:
(a) At
the time the utility invoices the owner or operator of the qualifying facility
for interconnection costs incurred by the utility; or
(b) Over an agreed period not greater than
the length of any contract between the utility and the qualifying
facility.