Wash. Admin. Code § 480-54-030 - Duty to provide access; make-ready work; timelines
(1) An owner shall provide requesters with
nondiscriminatory access for attachments to or in any facility the owner owns
or controls, except that if the owner is an electrical company as defined in
RCW 80.04.-010, the owner is not obligated to provide access for attachment to
its facilities by another electrical company. An owner may deny such access to
specific facilities on a nondiscriminatory basis where there is insufficient
capacity or for reasons of safety, reliability, and generally applicable
engineering principles; provided that the owner may not deny access to a pole
based on insufficient capacity if the requester is willing to compensate the
owner for the costs to replace the existing pole with a taller pole and
otherwise undertake make-ready work to increase the capacity of the pole to
accommodate an additional attachment including, but not limited to, using
space- and cost-saving attachment techniques, such as boxing (installation of
attachments on both sides of the pole at approximately the same height) or
bracketing (installation of extension arms), to the extent that the owner uses,
or allows occupants to use, such attachment techniques in the communications
space of the owner's poles.
(2) All
rates, terms, and conditions made, demanded, or received by any owner for any
attachment by a licensee or by a utility must be fair, just, reasonable, and
sufficient and must be included in an attachment agreement with the licensee or
utility. Parties may mutually agree on terms for attachment to or in facilities
that differ from those in this chapter. In the event of disputes submitted for
commission resolution, any party advocating rates, terms, or conditions that
vary from the rules in this chapter bears the burden to prove those rates,
terms, or conditions are fair, just, reasonable, and sufficient.
(3) Except for overlashing requests described
in subsection (11) of this section, a requester must submit a written
application to an owner to request access to its facilities. The owner may
recover from the requester the reasonable costs the owner actually and
reasonably incurs to process the application, including the costs of inspecting
the facilities identified in the application and preparing a preliminary
estimate for any necessary make-ready work, to the extent these costs are not,
and would not ordinarily be, included in the accounts used to calculate the
attachment rates in WAC 480-54-060. The owner may survey the facilities
identified in the application and may recover from the requester the costs the
owner actually and reasonably incurs to conduct that survey. The owner must
provide the requester with an estimate of those costs prior to conducting a
survey. The owner must complete any such survey and respond in writing to
requests for access to the facilities identified in the application within
forty-five days from the date the owner receives a complete application, except
as otherwise provided in this section. A complete application is an application
that provides the information necessary to enable the owner to identify and
evaluate the facilities to or in which the requester seeks to attach.
(4) If the owner denies the request in an
application for access, in whole or in part, the owner's written response to
the application must include an explanation of the reasons for the denial for
each facility to which the owner is denying access. Such a response must
include all relevant information supporting the denial.
(5) To the extent that it grants the access
requested in an application, the owner's written response must inform the
requester of the results of the review of the application. Within fourteen days
of providing its written response, the owner must provide an estimate of
charges to perform all necessary make-ready work, including the costs of
completing the estimate. Make-ready work costs are nonrecurring costs that are
not included in carrying charges and must be costs that the owner actually and
reasonably incurs to provide the requester with access to the facility.
(a) The requester must accept or reject an
estimate of charges to perform make-ready work within thirty days of receipt of
the estimate. The owner may require the requester to pay all estimated charges
to perform make-ready work as part of acceptance of the estimate or before the
owner undertakes the make-ready work subject to true-up to the reasonable costs
the owner actually incurs to undertake the work.
(b) An owner may withdraw an outstanding
estimate of charges to perform make-ready work any time after thirty days from
the date the owner provides the estimate to the requester if the requester has
not accepted or rejected that estimate. An owner also may establish a date no
earlier than thirty days from the date the owner provides the estimate to the
requester after which the estimate expires without further action by the
owner.
(6) For requests
to attach to poles, the owner must determine the time period for completing the
make-ready work and provide that information in a written notice to the
requester and all known occupants with existing attachments on the poles that
may be affected by the make-ready work. The owner and the requester must
coordinate the make-ready work with any such occupants, as necessary.
(a) For attachments in the communications
space, the notice shall:
(i) Specify where
and what make-ready work will be performed.
(ii) Set a date for completion of make-ready
work that is no later than sixty days after the notice is sent. For good cause
shown, the owner may extend completion of the make-ready work by an additional
fifteen days.
(iii) State that any
occupant with an existing attachment may modify that attachment consistent with
the specified make-ready work before the date set for completion of that work.
Any occupant with an existing attachment that does not comply with applicable
safety requirements must modify that attachment to bring it into compliance
before the date set for completion of the make-ready work. The occupant shall
be responsible for all costs incurred to bring its attachment into
compliance.
(iv) State that the
owner may assert its right to fifteen additional days to complete the
make-ready work.
(v) State that if
make-ready work is not completed by the completion date set by the owner (or
fifteen days later if the owner has asserted its right to fifteen additional
days), the owner and the requester may negotiate an extension of the completion
date or the requester, after giving reasonable notice to the owner, may hire a
contractor from the list of contractors the owner has authorized to work on its
poles to complete the specified make-ready work within the communications
space. If the owner does not maintain a list of authorized contractors, the
requester may choose a contractor without the owner's authorization.
(vi) State the name, telephone number, and
e-mail address of a person to contact for more information about the make-ready
work.
(b) For wireless
antennas or other attachments on poles in the space above the communications
space, the notice shall:
(i) Specify where and
what make-ready work will be performed.
(ii) Set a date for completion of make-ready
work that is no later than ninety days after notice is sent. For good cause
shown, the owner may extend completion of the make-ready work by an additional
fifteen days.
(iii) State that any
occupant with an existing attachment may modify the attachment consistent with
the specified make-ready work before the date set for completion of that work.
Any occupant with an existing attachment that does not comply with applicable
safety requirements must modify that attachment to bring it into compliance
before the date set for completion of the make-ready work. The occupant shall
be responsible for all costs incurred to bring its attachment into
compliance.
(iv) State that the
owner may assert its right to fifteen additional days to complete the
make-ready work.
(v) State the
name, telephone number, and e-mail address of a person to contact for more
information about the make-ready work.
(7) For the purpose of compliance with the
time periods in this section:
(a) The time
periods apply to all requests for access to up to three hundred poles or 0.5
percent of the owner's poles in Washington, whichever is less.
(b) An owner shall negotiate in good faith
the time periods for all requests for access to more than three hundred poles
or 0.5 percent of the owner's poles in Washington, whichever is less.
(c) An owner may treat multiple requests from
a single requester as one request when the requests are filed within the same
thirty-day period. The applicable time period for completing the optional
survey or required make-ready work begins on the date of the last request the
owner receives from the requester within the thirty-day period.
(8) An owner may extend the time
periods specified in this section under the following circumstances:
(a) For replacing existing poles to the
extent that circumstances beyond the owner's control including, but not
necessarily limited to, local government permitting, landowner approval, or
adverse weather conditions, require additional time to complete the work;
or
(b) During performance of
make-ready work if the owner discovers unanticipated circumstances that
reasonably require additional time to complete the work. Upon discovery of the
circumstances in (a) or (b) of this subsection, the owner must promptly notify,
in writing, the requester and other affected occupants with existing
attachments. The notice must include the reason for the extension and date by
which the owner will complete the work. The owner may not extend completion of
make-ready work for a period any longer than reasonably necessary and shall
undertake such work on a nondiscriminatory basis with the other work the owner
undertakes on its facilities.
(9) If the owner determines that a survey is
necessary for responding to a request for attachment to poles and fails to
complete a survey of the facilities specified in the application within the
time periods established in this section, a requester seeking attachment in the
communications space may negotiate an extension of the completion date with the
owner or may hire a contractor from the list of contractors the owner has
authorized to work on its poles to complete the survey. If the owner does not
maintain a list of authorized contractors, the requester may choose a
contractor without the owner's authorization.
(10) If the owner does not complete any
required make-ready work within the time periods established in this section, a
requester seeking attachment in the communications space may negotiate an
extension of the completion date with the owner or may hire a contractor from
the list of contractors the owner has authorized to work on its poles to
complete the make-ready work within the communications space:
(a) Immediately, if the owner declines to
exercise its right to perform any necessary make-ready work by notifying the
requester that the owner will not undertake that work; or
(b) After the end of the applicable time
period authorized in this section if the owner has asserted its right to
perform make-ready work and has failed to timely complete that work.
If the owner does not maintain a list of authorized contractors, the requester may choose a contractor without the owner's authorization.
(11) An occupant need not submit an
application to the owner if the occupant intends only to overlash additional
communications wires or cables onto communications wires or cables it
previously attached to poles with the owner's consent under the following
circumstances:
(a) The occupant must provide
the owner with written notice fifteen business days prior to undertaking the
overlashing. The notice must identify no more than one hundred affected poles
and describe the additional communications wires or cables to be overlashed so
that the owner can determine any impact of the overlashing on the poles or
other occupants' attachments. The notice period does not begin until the owner
receives a complete written notice that includes the following information:
(i) The size, weight per foot, and number of
wires or cables to be overlashed; and
(ii) Maps of the proposed overlash route,
including pole numbers if available.
(b) A single occupant may not submit more
than five notices or identify more than a total of one hundred poles for
overlashing in any ten business day period. The applicable time period for
responding to multiple notices begins on the date of the last notice the owner
receives from the occupant within the ten business day period.
(c) The occupant may proceed with the
overlashing described in the notice unless the owner provides a written
response, within ten business days of receiving the occupant's notice,
prohibiting the overlashing as proposed. The owner may recover from the
requester the costs the owner actually and reasonably incurs to inspect the
facilities identified in the notice and to prepare any written response. The
occupant must correct any safety violations caused by its existing attachments
before overlashing additional wires or cables on those attachments.
(d) The owner may refuse to permit the
overlashing described in the notice only if, in the owner's reasonable
judgment, the overlashing would have a significant adverse impact on the poles
or other occupants' attachments. The refusal must describe the nature and
extent of that impact, include all relevant information supporting the owner's
determination, and identify the make-ready work that the owner has determined
would be required prior to allowing the proposed overlashing. The parties must
negotiate in good faith to resolve the issues raised in the owner's
refusal.
(e) A utility's or
licensee's wires or cables may not be overlashed on another occupant's
attachments without the owner's consent and unless the utility or licensee has
an attachment agreement with the owner that includes rates, terms, and
conditions for overlashing on the attachments of other occupants.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.