W. Va. Code R. § 38-2-1 - General
1.1. Slope. -- This
rule establishes general and specific rules for permit application requirements
and contents; haulageways or access roads; drainage and sediment control
systems; blasting; premining and postmining land use; fish and wildlife
considerations; revegetation; prime farmlands; insurance and bonding;
replacement, release, and forfeiture of bonds; requirements of a notice of
intent to prospect; performance standards; performance standards applicable to
underground mining operations; subsidence control; small operator assistance
program; citizen's actions; designation of areas unsuitable for mining;
inspection and enforcement; Surface Mine Board; and Coal Refuse.
1.2. Authority. - W.Va. Code §
22-3-4,
22-3-12,
22-3-13(g),
22-3-23(1),
and
22-3-35.
1.3. Filing Date. -- June 1, 2020
1.4. Effective Date -- July 1, 2020
1.5. Applicability.
1.5.a. This rule applies to all prospecting
and surface mining operations in the State of West Virginia, except the
applicable subsections in W. Va. Code §
22-3-26.
The provisions of this subdivision do not constitute the issuance of a new
permit for purposes of permit renewal or mid-term review of existing
permits.
1.5.b. Permits issued
after the effective date of this rule shall incorporate in the application all
of the requirements of this rule.
1.5.c. The Secretary may terminate
jurisdiction over a reclaimed site of a completed surface mining and
reclamation operation, or increment thereof, when:
1.5.c.1. The Secretary determines in writing
that under the initial program all applicable requirements imposed by the Act,
this rule, and the terms and conditions of the permit have been successfully
complied with; or
1.5.c.2. The
Secretary determines in writing that under the permanent program, all
requirements imposed under the Act, this rule, and the terms and conditions of
the permit have been successfully complied with or, where a bond was required,
the Secretary has made a final decision to release the bond fully.
1.5.d. following termination under
subdivision 1.5.c of this section, the Secretary shall reassert jurisdiction
over a site if it is demonstrated that the bond release or written
determination referred to in subdivision 1.5.c. was based upon fraud,
collusion, or misrepresentation of a material fact.