W. Va. Code R. § 38-3-9 - Permanent Excess Spoil Disposal, Temporary Spoil Storage Areas
9.1. Disposal of
Excess Spoil in Side of Hill Fills. -- Excess spoil or material to be placed in
permanent disposal sites shall be transported to and placed in a controlled
manner in disposal areas other than the mine workings or excavation only if all
the provisions of this section are met.
9.1.a.
Location of Disposal Sites. - Permanent excess spoil disposal areas shall be
identified on the proposal map, shall be located within the permit area, and
they must be approved by the Secretary as suitable for construction of fills.
The disposal area shall be located on the most moderate slopes and naturally
stable areas available.
9.1.b.
Certification. -- Certification of the fill shall be as follows:
9.1.b.1. The fill shall be designed using
recognized professional standards and certified by an approved registered
professional engineer; and
9.1.b.2.
The fill shall be inspected for stability by an approved registered
professional engineer after completion of the first fifty-foot (50') lift, to
assure the following requirements are met:
9.1.b.2.A. Removal of all organic material
and topsoil;
9.1.b.2.B. Placement
of under-drainage systems; and
9.1.b.2.C. Proper construction in accordance
with the approved permit.
9.1.b.3 The approved registered professional
engineer shall also provide a certified report upon completion of the fill that
the fill has been constructed as designed in the approved permit.
9.1.b.4. Any deviations from the approved
permit which result from unforeseen site specific circumstances arising during
construction, shall be reflected in as-built plans submitted by the operator
and approved by the Secretary immediately following construction. The as-built
plans shall include the following:
9.1.b.4.A.
The original design;
9.1.b.4.B. The
extent of the changes; and
9.1.b.4.C. The reference points.
9.1.b.4.C.1. If as built plans are submitted,
the certification shall:
9.1.b.4.C.1.(a)
Describe how and to what extent the construction deviates from the proposed
design; and
9.1.b.4.C.1.(b) Certify
that the fill will meet all the requirements of this rule.
9.1.c.
Stabilization. -- Where the slope in the disposal area exceeds 2.8 horizontal
to one (1) vertical (thirty-six (36%) percent), or where necessary to achieve a
static safety factor of 1.5, measures such as keyway cuts, rock toe buttresses
or other techniques shall be used. All organic material shall be removed from
the disposal area and the topsoil must be removed and segregated before the
overburden is placed in the disposal area. Suitable organic material may be
used as mulch or may be included in the topsoil. The spoil shall be transported
and placed in a controlled manner, concurrently compacted as necessary to
ensure long-term mass stability and prevent mass movement. The fill shall be
drained and graded to allow surface and subsurface drainage to be compatible
with the natural surroundings.
9.1.d. Drainage. -- The disposal area shall
not contain springs, natural water courses or wet weather seeps unless lateral
drains are constructed from the wet areas to the under drains in such a manner
that infiltration of the water into the fill shall be prevented. The drains
shall be designed and constructed of course rock. If no filter is designed for
the under drain, sufficient capacity shall be provided to allow for partial
plugging of the drain. No rock shall be used in under drains if it tends to
disintegrate or if it is acid-forming or toxic-forming.
9.1.e. Construction. -- Construction of the
fill shall be as follows:
9.1.e.1. All areas
upon which the fill is to be placed shall first be progressively cleared of all
trees, brush, and shrubs. This material shall be removed from the fill
area;
9.1.e.2. Depositing and
compacting the fill in layers shall begin at the toe of the fill. The layers
shall be constructed approximately parallel with proposed finish grade. All
material shall be deposited in uniform horizontal layers and compacted with
haulage equipment;
9.1.e.3. The
thickness of the layers shall not exceed four (4) feet;
9.1.e.4. The outer slope or face of the fill
shall be regraded to be no steeper than two (2) horizontal to one (1) vertical
(2:1) Provided, That constructed fill slopes may be steeper if they meet a
static safety factor of one point five (1.5) and are certified by a registered
professional engineer. Benches shall be constructed on the fill at a maximum of
every fifty feet (50') in vertical rise above the toe of the fill. The benches
shall be no less than twenty feet (20') in width and slope toward the fill at a
three (3) to five (5) percent grade and slope laterally at one (1) percent
grade to discharge channels capable of passing the peak runoff for a
one-hundred (100) year twenty-four (24) hour precipitation event; and
9.1.e.5. When construction of each lift
(maximum of every fifty feet (50') in vertical height) of the fill is
completed, topsoil or other suitable material which will support vegetation
shall be spread over the completed slope and bench. The slopes and benches
shall then be seeded and mulched immediately in accordance with the approved
revegetation plans.
9.2. Disposal of Excess Spoil Material in
Valley Fills. -- Excess spoil or material to be placed in permanent overburden
disposal sites shall be transported to and placed in a controlled manner; spoil
to be disposed of in natural valleys must be placed in accordance with the
following requirements:
9.2.a. Location of
Excess Spoil Areas. - Permanent excess spoil disposal areas shall be identified
on the proposal map, shall be within the permit area and they must be approved
by the Secretary as suitable for construction of fills. The disposal area shall
be located on the most moderate slopes and naturally stable areas
available.
9.2.b. Certification. --
Certification of the fill shall be as follows:
9.2.b.1. The fill shall be designed using
recognized professional standards and certified by an approved registered
professional engineer; and
9.2.b.2.
The fill shall be inspected for stability by an approved registered
professional engineer after completion of the first fifty foot (50') lift to
assure the following requirements are met:
9.2.b.2.A. Removal of all organic material
and topsoil;
9.2.b.2.B. Placement
of under-drainage systems; and
9.2.b.2.C. Proper construction is in
accordance with the approved permit.
9.2.b.3. The approved registered professional
engineer shall also provide a certified report upon completion of the fill that
the fill, has been constructed as designed in the approved permit.
9.2.b.4. Any deviations from the approved
permit which result from unforeseen site specific circumstances arising during
construction, shall be reflected in as-built plans submitted by the operator
and approved by the Secretary immediately following construction. The as-built
plans shall include the following:
9.2.b.4.A.
The original design;
9.2.b.4.B. The
extent of the changes; and
9.2.b.4.C. The reference points.
9.2.b.4.C.1. If as built plans are submitted,
the certification shall:
9.2.b.4.C.1.(a)
Describe how and to what extent the construction deviates from the proposed
design; and
9.2.b.4.C.1.(b) Certify
that the fill will meet all the requirements of this
rule.
9.2.c. Stabilization. -- Where the slope in
the disposal area exceeds 2.8 horizontal to one (1) vertical (thirty-six
percent (36%)) or where necessary to achieve a static safety factor of 1.5,
measures such as keyway cuts, rock toe buttresses or other techniques shall be
used. All organic material shall be removed from the disposal area and the
topsoil must be removed and segregated before the overburden is placed in the
disposal area. Suitable organic material may be used as mulch or may be
included in the topsoil. The spoil shall be transported and placed in a
controlled manner, concurrently compacted as necessary to insure long-term mass
stability and prevent mass movement. The fill shall be drained and graded to
allow surface and subsurface drainage to be compatible with the natural
surroundings.
9.2.d. Drainage. --
The disposal area shall not contain springs, natural water courses or wet
weather seeps unless lateral drains are constructed from the wet areas to the
under drains in such a manner that infiltration of the water into the fill
shall be prevented. If springs, natural watercourses or wet weather seeps are
encountered, a system of under drains shall be constructed from each spring or
seepage area as lateral drains to the rock core. If no filter is designed for
the under drain, sufficient capacity shall be provided to allow for partial
plugging of the drain. No rock shall be used in under drains if it tends to
disintegrate or if it is acid-forming or toxic-forming.
9.2.e. Construction. -- Construction of the
fill shall be as follows:
9.2.e.1. All areas
upon which the fill is to be placed shall first be progressively cleared of all
trees, brush, and shrubs. This material shall be removed from the fill area. No
more than three (3.0) acres, excluding roadway for construction of fill, shall
be cleared in the valley fill site until the first lift is completed;
9.2.e.2. A rock core shall be progressively
constructed as the layers are brought up through the valley fill. The rock core
shall be a minimum of sixteen feet (16') in width and composed of rock with a
minimum dimension of twelve inches (12"). The rock core shall consist of no
more than ten percent (10%) fines as determined by visual inspection (fines
being a material with a dimension of less than twelve inches) (12");
9.2.e.3. Depositing and compacting the fill
in layers shall begin at the toe of the fill. The layers shall be constructed
approximately parallel with proposed finish grade. All material shall be
deposited in uniform horizontal layers and compacted with haulage
equipment;
9.2.e.4. The thickness
of the layers shall not exceed four feet (4');
9.2.e.5. During and after construction, the
top of the fill shall be graded to drain back to the head of the fill on a
slope no greater than three percent (3%). A drainage pocket shall be maintained
at the head of the fill at all times to intercept surface runoff. Maximum size
of the drainage pocket shall be ten thousand (10,000) cubic feet;
9.2.e.6. The outer slope or face of the fill
shall be regraded to be no steeper than two (2) horizontal to one (1) vertical
(2:1) Provided, That constructed fill slopes may be steeper if they meet a
static safety factor of one point five (1.5) and are certified by a registered
professional engineer. Benches shall be constructed on the fill at a maximum of
every fifty feet (50') in vertical rise above the toe of the fill. The benches
shall be no less than twenty feet (20') in width and slope toward the fill at a
three (3) to five (5) percent grade and slope laterally at one (1) percent
grade to discharge channels capable of passing the peak runoff for a
one-hundred (100) year twenty-four (24) hour precipitation event.
9.2.e.7. When construction of each lift
(maximum of every fifty feet (50') in vertical height) of the valley fill is
completed, topsoil or other suitable material which will support vegetation
shall be spread over the completed slope and bench excluding the rock core. The
completed slope and bench shall then be seeded and mulched immediately in
accordance with the approved revegetation plans.
9.3. Disposal of Excess Spoil Material in
Durable Rock Fills. -- The Secretary may approve the design, construction, and
use of a single lift fill consisting of at least eighty percent (80%) durable
rock if it can be determined, based on information provided by the operator,
that the following conditions exist:
9.3.a.
Permanent excess disposal areas shall be identified on the proposal map, be
within the permit area, and they must be approved by the Secretary as suitable
for construction of fills. The disposal area shall be located on the most
moderate slopes and naturally stable areas available.
9.3.b. Geotechnical Information. --
Examination of core borings and the geologic column show that the overburden
consists of durable sandstone, limestone, or other durable material in
sufficient thickness and amounts to generate spoil material that is eighty
percent (80%) or greater durable rock. Where the fill will contain non-cemented
clay shale, clay spoil, or other nondurable material, such material must be
mixed with durable rock in a controlled manner such than no more than twenty
percent (20%) of the fill volume is not durable rock. Tests shall be performed
by a qualified laboratory, and approved by the Secretary to demonstrate that no
more than twenty percent (20%) of the fill is not durable rock.
9.3.b.1. The durable rock shall not consist
of acid-producing or toxic-forming material, will not slake in water, or will
not degrade to soil material. For purposes of this paragraph only, soil
material means material of which at least fifty percent (50%) is finer than
0.074 mm, which exhibits plasticity, and which meets the criteria for group
symbol ML, CL, OL, MH, CH, or OH, as determined by the United Soil
Classification System (ASTM D-2487).
9.3.b.2. The toe of the fill shall rest on
natural slopes no steeper than twenty percent (20%).
9.3.c. The fill shall be designed based on
the results of sufficient geotechnical investigations of the construction site.
The investigation shall include such factors as geologic conditions, soil
characteristics, depth to bedrock location of springs, seeps and groundwater
flow, potential effects of subsidence and a description of materials to be
placed in rock cores and drains.
9.3.d. The design and construction of all
durable rock fills must be certified by a registered professional engineer
experienced in design and construction of earth and rock embankments.
9.3.e. The foundation of the fill and the
fill shall be designed to assure a long-term static safety factor of 1.5 or
greater, and meet an earthquake safety factor of 1.1.
9.3.f. All areas upon which the fill is to be
placed shall first be progressively cleared of all trees, brush, and shrubs
which are above ground level; provided; that in critical foundation areas,
including, but not limited to, the toe of the fill, seepage or underdrain
areas, and downstream portions of the fill that provide resisting force against
massive slope failure, all organic material both above and below that ground
surface must be removed. This material shall be disposed of outside the fill
area.
9.3.g. The underdrain system
may be constructed simultaneously with excess spoil placement by natural
segregation of dumped materials; provided, that the resulting underdrain system
shall be capable of carrying anticipated seepage of water due to rainfall away
from the excess spoil fill, and from seeps and other springs in the foundation
of the disposal area, and the other requirements for drainage control shall be
met. If the underdrain system is not constructed by natural segregation of
dumped material, it shall be designed and constructed in accordance with
subdivision 9.1.d. of this rule.
9.3.h. Surface water runoff from areas above
and adjacent to the fill shall be diverted into properly designed and
constructed stabilized diversion channels which have been designed using the
best current technology to safely pass the peak runoff from a one hundred (100)
year, twenty four (24) hour precipitation event. The channel shall be designed
and constructed to ensure stability of the fill, control erosion, and minimize
water infiltration into the fill.
9.3.i. The grade of the top surface of the
completed fill shall not exceed five percent (5%) and shall slope toward the
drainage channel.
9.3.j. The outer
slope or face of the fill shall be regraded to be no steeper than two (2)
horizontal to one (1) vertical (2:1) Provided, That constructed fill slopes may
be steeper if they meet a static safety factor of one point five (1.5) and are
certified by a registered professional engineer. Benches shall be constructed
on the fill at a maximum of every fifty feet (50') in vertical rise above the
toe of the fill. The benches shall be no less than twenty feet (20') in width
and slope toward the fill at a three (3) to five (5) percent grade and slope
laterally at one (1) percent grade to discharge channels capable of passing the
peak runoff for a one-hundred (100) year twenty-four (24) hour precipitation
event.
9.3.k. No permanent
impoundments may be constructed on the completed fill except small depressions
may be allowed if they are needed to retain moisture, minimize erosion, create
and enhance wildlife habitat, or assist revegetation; and if they are not
incompatible with the stability of the fill.
9.3.l. Notwithstanding any other provisions
of this rule or terms and conditions of a permit to the contrary, additional
storage capacity or sediment control measures may be required through permit
revision if sediment removal performance of the structure(s) during operation
and construction of the fill is found to be deficient to the point that
significant non-compliance with applicable effluent limits or water quality
standards results.
9.3.m. The
following materials are hereby prohibited from being placed, deposited, or
disposed of into a durable rock fill or durable rock fill area:
9.3.m.1. Surface soils, provided that such
soils used to establish vegetation on the surface of the fill are not
prohibited; provided, however, such soils may be placed in the fill if
accounted for in design and construction as nondurable material, and such soils
are not deposited in critical zones of the fill;
9.3.m.2. Mud, silt, or sediment cleaned or
removed from mining pits, roadways, sediment control structures and/or other
areas of the operation;
9.3.m.3.
Vegetative or organic materials cleared or grubbed from the permit or other
areas; and
9.3.m.4. Coal
refuse.
9.3.n. Inspection
and Certification of Durable Rock Fills. -- Certification of all durable rock
fills shall be required as follows:
9.3.n.1.
The fill and appurtenant structures shall be designed in accordance with
professional design standards, which meet the requirements of this subsection,
and certified by a registered professional engineer experienced in the design
of earth and rock fill embankments;
9.3.n.2. During construction, the fill shall
be inspected quarterly for stability by a registered professional engineer
experienced in the construction of earth or rock fills or other qualified
professional specialist working under the direction of a professional engineer
experienced in the construction of earth or rock fills. Regular inspections are
also required during placement and compaction of fill materials and during
critical construction periods such as foundation preparation, underdrain
placement, installation of surface drainage systems, and construction of rock
toe buttresses. Within two (2) weeks following completion of the inspections, a
report certified by the registered professional engineer shall be submitted to
the Secretary. The certified report shall contain a statement that the fill is
being constructed and maintained as designed in accordance with the approved
plan and this rule. The report shall also note any instances of apparent
instability, structural weaknesses, and other hazards. The report on the
drainage system and protective filters shall include color photographs taken
during and after construction, but before the underdrains are covered with
excess spoil. Color photographs shall be of sufficient size and number to
provide a relative scale and to clearly identify the site. If the underdrains
are constructed in phases, each phase must be certified separately. If excess
durable rock spoil is placed such that the underdrain system is constructed
simultaneously with excess spoil placement by the natural segregation of dumped
materials, color photographs of the underdrains must be taken as they are
formed. All color photographs shall be of adequate size and number to provide a
relative scale and to clearly identify the site. A copy of the certified report
shall be maintained at the mine site;
9.3.n.3. After total completion of the fill,
a certification form shall be completed and submitted to the Secretary by the
registered professional engineer overseeing construction of the fill;
and
9.3.n.4. In addition to the
requirements of subparagraph (2) of this paragraph, certification forms for
durable rock fills shall be accompanied by the following:
9.3.n.4.A. A statement attesting that the
fill contains no more than twenty percent (20%) non-durable material;
9.3.n.4.B. A statement attesting that
foundation preparation is proceeding in accordance with the design
plans;
9.3.n.4.C. A statement that
prohibited materials are not being placed, deposited, or disposed of into the
fill area; and
9.3.n.4.D. A
statement that sediment control measures are constructed and being maintained
in accordance with the approved design plans, and the terms and conditions of
the permit.
9.3.n.4.E. Any
deviations from the approved drainage plan which result from unforeseen site
specific circumstances arising during construction, shall be reflected in
as-built plans submitted by the operator and approved by the Secretary
immediately following construction. The as-built plans shall include the
following:
9.3.n.4.E.1. The original
design;
9.3.n.4.E.2. The extent of
the changes; and
9.3.n.4.E.3. The
reference points.
9.3.n.4.F. If as built plans are submitted,
the certification shall:
9.3.n.4.F.1. Describe
how and to what extent the construction deviates from the proposed design;
and
9.3.n.4.F.2. Certify that the
fill will meet all the requirements of this rule.
9.4. Disposal
of Excess Spoil Material in Spoil Piles. -- Excess spoil being placed in
permanent overburden disposal sites on natural ground with an original slope of
less than twenty (20) degrees shall be transported to and placed in a
controlled manner; spoil piles must be placed in accordance with the following
requirements:
9.4.a. Location of Disposal
Sites. - Permanent excess disposal areas shall be identified on the proposal
map, be within the permit area, and they must be approved by the Secretary as
suitable for construction of spoil piles. The disposal area shall be located on
the most moderate slopes and naturally stable areas available.
9.4.b. Drainage. -- The disposal area shall
not contain springs, natural water courses or wet weather seeps unless lateral
drains are constructed from the wet areas to under drains in such a manner that
infiltration of the water into the spoil pile shall be prevented. The drains
shall be designed and constructed of coarse rock. If no filter is designed for
an under drain, sufficient capacity shall be provided to allow for partial
plugging of the drain. No rock shall be used in under drains if it tends to
disintegrate or if it is acid-forming or toxic-forming.
9.4.c. Construction. -- Construction of the
spoil pile shall be as follows:
9.4.c.1. All
areas upon which the spoil pile is to be placed shall first be progressively
cleared of all trees, brush, and shrubs. This material shall be removed from
the area of the spoil pile;
9.4.c.2. All material shall be deposited in
uniform horizontal layers and compacted with haulage equipment;
9.4.c.3. Unless waived by the Secretary based
upon a stability analysis of the spoil pile, the thickness of the layers shall
not exceed four (4) feet; and
9.4.c.4. The outer slope or face of the spoil
pile shall be regraded to be no steeper than two (2) horizontal to one (1)
vertical (2:1) Provided; that constructed slopes may be steeper if they meet a
static safety factor of one point five (1.5) and are certified quarterly during
construction by a registered professional engineer. The spoil pile shall be
considered dormant and shall not need to be certified during periods of
inactivity that exceed ninety (90) days in length. Benches shall be constructed
on the spoil pile at a maximum of every fifty feet (50') in vertical rise above
the toe of the spoil pile. The benches shall be no less than twenty feet (20')
in width, and slope toward the pile at a three (3) to five (5) percent grade,
and slope laterally at one (1) percent grade to discharge channels design in
accordance with section 7 of this rule; and
9.4.c.5. When construction of a spoil pile is
completed, topsoil or other suitable material which will support vegetation
shall be spread over the completed slopes and benches. The slopes and benches
shall then be seeded and mulched immediately in accordance with the approved
revegetation plans.
9.5. Temporary Spoil Storage Areas -
Temporary spoil storage areas must be approved by the Secretary as suitable for
construction of a fill. The storage area shall be located on the most moderate
slopes and naturally stable areas available. Temporary spoil storage areas
constructed on slopes steeper than twenty (20) degrees shall be designed using
those same requirements as permanent excess spoil disposal sites.
9.6. Variance. -- Where it can be
demonstrated that other design criteria are justified, certain requirements of
this section may be waived. The basis for justification is, but not limited to,
land use potential, access to mineral reserves, unavailability of durable rock,
and site stability.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.