W. Va. Code R. § 64-47-5 - Sewage Treatment Works
5.1.
General.
5.1.a. The design of sewage
treatment plants shall be to provide for an estimated population on July 1,
2042. The design of all treatment plants shall be so
that their capacity can readily be increased except when circumstances preclude
the probability of expansion.
5.1.b. Plant Location. A sewage treatment
plant site shall be as far as practical from any present area being built-up or
any area that shall probably be built up within a reasonable future period.
There shall be a buffer zone as indicated in Table 64-47-E. at the end of this
rule, from any surrounding occupied structure to any new plant site. These
buffer zone requirements do not apply to existing treatment works that are
being upgraded or expanded. The direction of prevailing winds shall be
considered when selecting the plant site. The location of the plants
operational units shall be at an elevation that is not subject to the 100-year
flood or shall otherwise be adequately protected against 100-year flood damage.
The plant shall remain fully operational during a 25-year flood. The plant
shall be readily accessible in all seasons. The site shall be of sufficient
size to accommodate expansion or addition of facilities to increase the degree
of treatment.
5.1.b.1. The Commissioner may
wave buffer zone requirements shown in Table 64-47-E. upon receipt of a written
request by the applicant and a detailed review by the Commissioner to determine
any public health impact. Health, safety, and nuisance considerations shall be
the basis of establishing a buffer zone.
5.1.b.2. The distances set forth in Table
64-47-E. are distances to sewage treatment units such as aeration basins,
clarifiers, sludge holding tanks, chlorination basins, chlorinator rooms,
blower houses and other units as stated in Table 64-47-E. Other buildings that
may be part of the plant but are only used for storage or as a laboratory and
do not contain chlorine cylinders or blowers, shall not be considered a sewage
treatment unit and shall not be subject to buffer zone requirements.
5.1.c. Quality of Effluent.
5.1.c.1. Surface Water Discharge. The stream
standards and water quality criteria established by the water resources board
and effluent limitations established by the division of water resources shall
be the basis of the required degree of wastewater treatment. The Commissioner
may establish more stringent requirements if the location of a public water
supply intake, a recreational water use area, or an aquaculture is downstream
from the discharge point.
5.1.c.2.
Land Discharge. See subsection 5.19 of this rule.
5.1.c.3. New Processes, Methods and
Equipment. The policy of the Commissioner is to encourage the development of
new processes, methods, and equipment for sewage treatment. The Commissioner
may require the following:
5.1.c.3.A.
Monitoring observations, including test results and engineering evaluations,
demonstrating the efficiency of these processes;
5.1.c.3.B. Detailed description of the test
methods;
5.1.c.3.C. Testing,
including appropriately composited samples, under various ranges of strength
and flow rates, including daily variations, and waste temperatures over a
sufficient length of time to demonstrate performance under climatic and other
conditions that the system may encounter in the area of the proposed
installations;
5.1.c.3.D. Testing
and evaluations made under the supervision of a competent process engineer
other than those employed by the manufacturer or developer; and
5.1.c.3.E. A performance bond.
5.1.d. Design.
5.1.d.1. Industrial Wastes. When treating
industrial and institutional wastes in a sewage treatment works, the character
of the wastes in the design of the plant shall be considered. In these cases,
the Commissioner may require treatability studies on the composite wastewater
prior to the plant design.
5.1.d.2.
Hydraulic Loading. The design of treatment plant units shall be based on the
average rate of sewage flow per 24 hours, except where there are notations of
significant deviations from the normal daily flow pattern.
5.1.d.3. Existing Sewage Systems. When there
are existing sewers, there shall be a determination as to the volume and
strength of sewage flow. Obtaining these data shall be from actual flow
measurements, preferably for both wet and dry weather periods. There shall be
laboratory analysis made on flow proportional composite samples taken over
24-hour periods. The design of plans and specifications for sewage works to
serve existing sewage systems shall be on the basis of characteristics and
strength of sewage as shown by results of composite samples examined and
gaugings of the present flow plus allowance for estimated increase in
population. In addition, they shall include non-excessive
infiltration/inflow.
5.1.d.4. New
Sewage Systems. For the construction of new sewers, design plans for sewage
treatment works shall be made on the basis of 70 gallons per capita per day or
estimates based upon a minimum one yearfully documented analysis of water use
records adjusted for consumption and losses.
5.1.d.5. Organic Loading. Computation of the
design organic loading shall be in the same manner used in determining design
flow. Generally, computation of organic loading shall be at 0.17 pounds of
five-day BOD per person per day. For package sewage treatment plants,
recirculating sand filter systems, stabilization ponds, aerated ponds, and
individual sewer systems, treating 50,000 G.P.D. or less, the organic loading
design shall increase if proposing garbage grinders.
5.1.d.6. Conduits. The design of all piping
and channels shall be to carry the maximum expected flows. The design of the
incoming sewer shall be for free discharge. Filleting bottom corners of the
channels is required. Eliminating pockets and corners where solids can
accumulate is also required. There shall be suitable gates in channels to seal
off unused sections that might accumulate solids. The use of shear gates or
stop planks shall receive approval when using them in place of gate valves or
sluice gates.
5.1.d.7. Arrangement
of Units. Arrangement of component parts of the plant shall be for greatest
operating convenience, flexibility, economy, and so as to facilitate
installation of future units. There shall be multiple treatment units for
plants greater than 100,000 gallons in size. There shall be a provision for
appurtenances in such a manner that it is possible to temporarily take any unit
of service. The remainder of the plant shall be operational with the unit or
units out of service. In the case of oxidation ditches, if multiple rotors
exist, the above requirements shall be met.
5.1.e. Miscellaneous.
5.1.e.1. Provisions for Taking Units Out of
Service. Diversion piping and structures shall be properly located and arranged
so that it is possible to independently remove either dual or multiple units of
the plant from service for inspection, maintenance, and repairs.
5.1.e.2. Dewatering. There shall be means to
dewater each unit. The possible need for hydrostatic pressure relief devices
shall be considered.
5.1.e.3.
Construction Materials. Because of the possible presence of hydrogen sulfide
and other corrosive gases, greases, oils, and similar constituents frequently
present in sewage, the materials selected for use in sewage treatment works
shall be considered. This is particularly important in the selection of metals
and paints. It is essential to avoid using dissimilar metals to minimize
galvanic action. Cathodic protection is a requirement for all steel
tanks.
5.1.e.4. Covering Units. The
use of properly vented covers shall receive approval.
5.1.e.5. Painting. It is important to avoid
the use of paints containing lead or mercury. In order to facilitate
identification of piping, this rule suggests that the different lines be
color-coded. The contents shall be stenciled on the piping in a contrasting
color. The color scheme is only required for plants of over 100,000 gallons in
size. For purposes of standardization, Table 64-47-F. at the end of this rule
contains the recommended color scheme.
5.1.e.6. Operating Equipment. The
specifications shall include a complete outfit of tools and accessories for the
plant operator's use, such as squeegees, wrenches, valve keys, rakes, shovels,
etc. A portable pump is recommended. There shall be readily accessible storage
space and work bench facilities and consideration given to provision of a
garage area that would also provide space for large equipment, maintenance, and
repair.
5.1.e.7. Grading and
Landscaping. There shall be concrete, asphalt or gravel walkways for access to
all units. Where possible, it is important to avoid steep slopes to prevent
erosion. Surface water shall not drain into any unit. There shall be particular
care taken to protect trickling filter beds, sludge beds, and intermittent sand
filters from surface water. There shall be a provision for landscaping,
particularly when a plant location must be near residential areas.
5.1.f. Plant Outfalls.
5.1.f.1. Outlet. The outfall sewer, where
practical, shall extend to the low water level of the receiving body of water
in a manner to insure satisfactory dispersion of the effluent. It shall not
have its outlet submerged and there must be provisions for taking samples of
the effluent discharge. This rule permits the use of headwalls where adequate
dispersion is obtained without carrying the outfall into the stream.
5.1.f.2. Design and Construction. The
construction of the outfall sewer shall be as to protect it against the effects
of flood water, ice, or other hazards as to reasonably insure its structural
stability and freedom from stoppage.
5.1.g. Essential Facilities.
5.1.g.1. Emergency Power.
5.1.g.1.A. General. All sewage treatment
facilities greater than 100,000 gallons in size that require electrical power,
shall have an alternate source of electric power to allow continuity of
operation during power failures, except as noted below. Methods of providing
alternate sources include:
5.1.g.1.A.1. The
connection of at least two independent public utility sources, such as
substations. This rule recommends a power line from each substation, and it
shall be a requirement unless the reviewing agency receives verifying
documentation and approves that a duplicate line is not necessary to minimize
water quality violations;
5.1.g.1.A.2. Portable or in-place internal
combustion engine equipment that shall generate electrical or mechanical
energy; and
5.1.g.1.A.3. Portable
pumping equipment when only emergency pumping is required.
5.1.g.1.B. Power for Aeration. Standby
generating capacity is not a requirement for aeration equipment used in the
activated sludge process. When power outages of four hours or more are common,
auxiliary power for minimum aeration of the activated sludge is a requirement.
The reviewing authority may require full power generating capacity on certain
critical stream segments.
5.1.g.1.C. Power for Disinfection. There
shall be continuous disinfection, when required, during all power
outages.
5.1.g.2.
Electrical Equipment. The location of all electrical equipment such as motors
and local controls, and electrical conduits shall either be at an elevation
above the 100-year flood level or be of waterproof design. There shall be
adequate protection for all outdoor equipment from the weather. Motors located
indoors, and near liquid handling piping and equipment, shall be of splashproof
design. All electrical wires in underground conduits or in conduits that can
flood shall have water resistant insulation as identified in the National
Electrical Code.
5.1.g.3. Water
Supply.
5.1.g.3.A. General. There shall be an
adequate supply of drinking water for use in the laboratory and general
cleanliness around the plant. No piping or other connections shall exist in any
part of the treatment works that, under any condition, might cause the
contamination of a drinking water supply. There shall be an examination of the
chemical quality for suitability for the intended use in heat exchangers,
chlorinators, and other units.
5.1.g.3.B. Direct Connections. The drinking
water supply line to each treatment plant shall have, as a minimum, an approved
reduced pressure type backflow preventer. The installation of these devices
shall be in a location to prevent flooding, corrosion and allow for adequate,
quick service and periodic inspections. Installation in below-grade meter type
vaults is not acceptable. All water supply take-off points shall follow the
devices and, there shall be no allowance for extension of this line to serve
the public.
5.1.g.3.C. Indirect
Connection. When using a potable water supply for any purpose in a plant, there
shall be provisions for a break tank, pressure pump, and pressure tank. Water
shall discharge to the break tank through an air-gap at least six inches above
the maximum flood line or the spill line of the tank, whichever is higher.
There shall be a permanently posted sign at every hose bibb, faucet, or stop
clock located on the water system beyond the break tank to indicate that the
water is not safe for drinking.
5.1.g.3.D. Separate Drinking Water Supply.
When it is not possible to provide drinking water from a public water supply,
there shall be a separate well. Location, construction, and testing of the well
shall comply with requirements of the Bureau. Requirements governing the use of
the supply are those contained in subparagraphs 5.1.g.3.B. and 5.1.g.3.C. of
this rule. Prior to construction, an applicant shall obtain approval of the
supply from the Commissioner.
5.1.g.3.E. Separate Non-Drinking Water
Supply. When there is a provision for a separate non-drinking water supply,
there shall be posting of a permanent sign indicating the water is not safe for
drinking to stop cocks, hose bibbs, and other water outlets.
5.1.g.4. Sanitary Facilities. All
sewage treatment plants with laboratory facilities shall have a shower, toilet,
and lavatory. There shall also be a provision for locker facilities.
5.1.g.5. Sewage Flow Measurement. There shall
be facilities for measuring the volume of sewage flows at all treatment works
greater than 100,000 gallons in size. All plants having a capacity of greater
than 100,000 gallons per day shall equip indicating, recording, and totalizing
equipment for effluent flow measurement.
5.1.g.6. Floor Slope. There shall be adequate
floor surface slope to a point of drainage.
5.1.g.7. Stairways. The installation of
stairways shall be with a slope of 30 to 35 degrees from the horizontal to
facilitate carrying samples, tools, and other necessaries. All risers in a
stairway should be of equal height. All stairways shall have
handrails.
5.1.h. Safety.
Following are the minimum requirements for all plants:
5.1.h.1. Enclosure of the wastewater
treatment works with a minimum six feet high chain link fence with a locked
entrance gate designed to discourage the entrance of unauthorized persons and
animals. In lieu of a chain link fence, a barbed wire fence with a locked
entrance gate can enclose natural systems, such as stabilization ponds,
polishing ponds, and wetlands.
5.1.h.2. There shall be handrails, grating,
and guardrails installed for safety when installed in open basins, screen
channels, mechanical equipment, and other hazardous places. For all extended
aeration plants of 50,000 gallons per day or less grating is a
requirement.
5.1.h.3. Provision of
first-aid equipment.
5.1.h.4.
Posting of "No Smoking" signs in hazardous locations.
5.1.h.5. Provision of protective clothing and
equipment such as SCBA's, atmospheric testers and gloves.
5.1.h.6. Provision of portable blower and
sufficient hose.
5.1.h.7. There
shall be explosion proof electrical equipment and non-sparking tools in work
areas where hazardous conditions may exist, such as digester vaults and other
locations where potentially explosive atmospheres of flammable gas or vapor
accumulate.
5.1.h.8. Proper
grounding and insulation of all electrical wiring is a requirement. There shall
be no part of the plant piping used for grounding.
5.1.h.9. There shall be a provision for
portable lighting equipment.
5.1.h.10. All manhole steps shall have
slip-proof rungs and the steps shall be of the railroad type that shall help
prevent foot slippage off the ends of the rungs.
5.1.h.11. There shall be a provision for
separate storage located remotely from the plant for flammable and hazardous
material.
5.1.h.12. The location of
heating devices with open flames shall be in separate rooms with outside
entrances and at grade or above.
5.1.h.13. Installation of particular safety
precautions for gas-collection piping is a requirement.
5.1.h.14. There shall be adequate
ventilation.
5.1.h.15. Chlorinator
rooms and chlorine storage areas shall have heat, light, and a ventilation fan
that is capable of being turned on from outside the room. The room shall be at
grade or above. There shall be a provision a viewing window from the plant
interior; and
5.1.h.16. The
treatment works shall comply with the provisions of the Occupational Safety and
Health Act (OSHA).
5.1.i.
Laboratory Space. All treatment works shall have facilities, either contractual
or on-site, for making the necessary analytical determinations and operating
control tests. When using an on-site laboratory, isolation shall be done to
render the laboratory reasonably free from the adverse effects of noise, heat,
vibration, and dust. Minimum laboratory space for facilities not performing BOD
and suspended solids testing on-site shall be 100 square feet floor space with
35 square feet bench area. Facilities providing on-site BOD, suspended solids,
and fecal coliform analysis shall provide a minimum of 400 square feet of floor
space and 150 square feet of bench space. If more than two persons shall be
working in the laboratory at any given time, there shall be a provision of 100
square feet of additional space for each additional person. Advanced wastewater
treatment plants shall provide a minimum of 100 additional square feet of floor
space with proportionate increase in bench space. Lists of laboratory equipment
shall be compiled from USEPA approved latest edition of Standard Methods for
the Examination of Water & Wastewater, by APHA - AWWA - WPCF.
5.1.j. Laboratory Equipment. All treatment
works shall have laboratory equipment determined by the commissioner based upon
type and complexity of the treatment process. However, all extended aeration
treatment plants of 100,000 gallons per day or less shall have the following:
5.1.j.1. A test kit for pH and for chlorine
residual. This test kit shall be of the comparator type as manufactured by
Hach, Taylor, Hellige, or Wyandotte;
5.1.j.2. Two one-liter graduated
beakers;
5.1.j.3. A secchi disk;
and
5.1.j.4. A squeegee with proper
length of handle, five-quart bucket and rubber gloves.
5.2. Screening Devices and
Comminutors.
5.2.a. Bar Racks and Screens.
5.2.a.1. Either coarse bar racks or bar
screens shall provide protection for pumps and other equipment. Coarse bar
racks shall provide protection for comminutors.
5.2.a.2. Location.
5.2.a.2.A. Indoors. Screening devices,
installed in a building where there is other equipment or offices located,
should be accessible only through a separate outside entrance.
5.2.a.2.B. Outdoors. Screening devices
installed outside shall have protection from freezing.
5.2.a.2.C. Access. Screening areas shall have
stairway access, lighting and ventilation, and a convenient means for removing
the screenings.
5.2.a.3.
Design and Installation.
5.2.a.3.A. Bar
Spacing. Clear openings between bars shall be no less than one inch for
manually cleaned screens. Clear openings for mechanically cleaned screens may
be as small as 0.5 inch. Maximum clear openings shall be 1.75 inches.
5.2.a.3.B. Slope. The placement of manually
cleaned screens, except those for emergency use, shall be on a slope of 30 to
45 degrees from the horizontal.
5.2.a.3.C. Velocities. At normal operating
flow conditions, approach velocities shall be no less than 1.25 feet per
second, to prevent settling; and no greater than 3 feet per second through the
bar screen to prevent forcing material through the openings.
5.2.a.3.D. Channels. For plants of greater
than 100,000 gallons per day, there shall be a provision for dual channels and
equipped with the necessary gates to isolate flow from any screening unit.
There shall also be provisions to facilitate dewatering each unit. The shape of
the channel preceding and following the screen shall be to eliminate stranding
and settling of solids. Channels shall be three to six inches below the invert
of the incoming sewer.
5.2.a.3.E.
Mechanical Devices. A positive means of locking out each mechanical device
shall be a provision.
5.2.a.4. Control Systems.
5.2.a.4.A. Timing Devices. All mechanical
units without timing devices shall run continuously. All mechanical units
operated by timing devices shall have auxiliary control that shall set the
cleaning mechanism in operation at predetermined high-water
elevations.
5.2.a.4.B. Electrical
Fixtures and Controls. Electrical fixtures and controls in screening areas
where explosive gases may accumulate shall meet the requirements of the
National Electrical Code for Class 1, Group D, Division 1 locations.
5.2.a.4.C. Manual Override. A manual override
shall supplement automatic controls.
5.2.a.5. Auxiliary Screens. When using
mechanically operated screening or comminuting devices, there shall be a
provision for auxiliary manually cleaned screens. Design shall include
provisions for automatic diversion of the entire sewage flow through the
auxiliary screens should the regular units fail.
5.2.a.6. Fine Screens. The use of fine
screens in lieu of sedimentation is not permitted. In special cases, if
demonstrated that the features peculiar to fine screens may be advantageous,
the Bureau may approve the proposed installation on a case-by-case
basis.
5.2.a.7. Disposal of
Screenings. There shall be facilities for removal, handling, storage, and
disposal of screenings in a sanitary manner. Manually cleaned screening
facilities shall include an accessible platform from which the operator may
rake screenings easily and safely. There shall be a provision for suitable
drainage facilities for both the platform and storage areas. This rule
prohibits grinding of screenings and return to the sewage flow. This rule
prohibits open area disposal. The commissioner shall approve the manner in
which applicant buries screens or if permitted, applicant may place them in a
landfill.
5.2.b.
Comminutors.
5.2.b.1. Location. The location
may be a requirement at sewage treatment plants forty thousand (40,000) gallons
or greater in size. The location of comminutors shall downstream of any grit
removal equipment.
5.2.b.2. Size.
The design of comminutors shall be to handle peak flow.
5.2.b.3. Installation. There shall be a bar
screen bypass channel. The use of the bypass channel should be automatic at
depths of flow exceeding the design capacity of the comminutor.
5.2.b.4. Servicing. There shall be a
provision to facilitate servicing units in place and removing units from their
location for servicing.
5.2.b.5.
Macerators and Grinder Pumps. In lieu of comminutors, applicant may use
macerators and grinder pumps or similar devices upon approval by the
Commissioner.
5.3. Grit Removal.
5.3.a. General. There shall be grit removal
facilities for all sewage treatment plants serving combined sewer systems.
There shall be provision made for future installation of grit removal
facilities for all plants of greater than 100,000 gallons in size serving new
sanitary sewer systems. Grit removal facilities may be a requirement for new
plants serving existing sewer systems. All sewage treatment plants having
anaerobic digesters require grit removal.
5.3.b. Location. The location of grit removal
facilities, except in unusual circumstances shall be ahead of pumps and
comminuting devices, and coarse bar racks should be placed ahead of
mechanically cleaned grit removal facilities.
5.3.c. Type and Number of Units. Grit removal
facilities for plants treating wastes from combined sewers shall have at least
two manually cleaned units or one mechanically cleaned unit and one manually
cleaned unit. Facilities other than channel-types are desirable for plants
100,000 gallons or greater in size, if provided with flexible controls for
agitation or air supply devices and with grit removal equipment.
5.3.d. Velocity-Controlled Grit Removal.
5.3.d.1. Inlet. Inlet turbulence shall be
minimal.
5.3.d.2. Velocity and
Detention. Design of channel-type chambers shall be to provide a velocity of
one foot per second. The detention time shall be based on the size of particles
(0.21 mm) to be removed. The design should take into consideration undesirable
turbulence and velocities at inlets and outlets.
5.3.d.3. Grit Washing. The method of final
grit disposal should determine the need for grit washing.
5.3.d.4. Drains. There shall be a provision
for dewatering each unit.
5.3.d.5.
Water. For clean up purposes, there shall be an adequate supply of water under
pressure.
5.3.d.6. Grit Removal.
Grit removal facilities located in deep pits shall have mechanical equipment
for pumping or hoisting grit to ground level. The pits shall have a stairway,
elevator or manlift, ventilation, and lighting, and have a means of
drainage.
5.3.e. Aerated
Grit Removal.
5.3.e.1. Air Diffusers. The
location of air diffusers shall be on one side of the tank, two to three feet
above the tank bottom.
5.3.e.2. Air
Supply Rate. There shall be a detention time of three minutes.
5.3.e.3. Inlet and Outlet. Design of the
aerated grit chamber shall be such as to prevent short circuiting at the inlet
and outlet. The inlet to the chamber shall introduce the wastewater directly
into the circulation pattern caused by the air diffusion. The outlet shall be
at a right angle to the inlet and a baffle installed near the outlet.
5.3.e.4. Grit Removal. The aerated grit
chambers shall have mechanical grit removal equipment.
5.3.f. Grit Handling. Grit handling areas
should have impervious surfaces with drains. If transporting grit, the design
of the conveying equipment should be to avoid loss of material and to provide
protection from freezing.
5.3.g.
Grit Disposal. The Commissioner shall approve in advance the manner in which an
applicant buries grit or if permitted, applicant may place it in a
landfill.
5.4.
Pre-aeration.
5.4.a. General. Pre-aeration of
sewage to reduce septicity may be a requirement in special cases.
5.5. Flow Equalization.
5.5.a. General. There shall be flow
equalization when there are expectations of large daily variations in organic
or hydraulic loadings.
5.5.b.
Location. The location of equalization basins shall be downstream of
pretreatment facilities such as bar screens, comminutors, and grit
chambers.
5.5.c. Type. There may be
a provision for flow equalization by using separate basins or on-line treatment
units, such as aeration tanks. The design of equalization basins may be as
either in-line or side-line units.
5.5.d. Design.
5.5.d.1. Mixing. Mixing requirements for
normal raw domestic wastewaters shall range from 0.02 to 0.04 hp/1000 gallons
of maximum storage volume.
5.5.d.2.
Aeration. Maintaining a minimum of 1.0 mg/1 of dissolved oxygen in the mixing
basin at all times is required. Air supply rates shall be a minimum of 1.25
cfm/1000 gallons of storage capacity.
5.5.d.3. Storage. There shall be sufficient
storage to allow the sections of the plant that follow the storage to operate
at or at less than their rated design capacity.
5.5.d.4. Detention/Equalization. Basins
designed for a combination of storage of wet weather flows and equalization
shall have compartments to allow utilization of a portion of the basins for dry
weather flow equalization.
5.5.d.5.
Flow Discharge Control. There shall be multiple pumping units capable of
delivering the desired flow rate from the equalization basin with the largest
pumping unit out of service. All pumps, ejectors and air lifts shall be easily
removable.
5.5.d.6. Aeration
Support. When pumps have floating surface aerators, there shall be provisions
to protect the units when dewatering the tank.
5.5.d.7. Basin Cleaning. There shall be
facilities to flush solids and grease accumulations from the basin
walls.
5.5.d.8. Scum Control. For
plants greater than 100,000 gallons in size there shall be a provision for a
high-water-level takeoff for withdrawing floating material when using
subsurface diffusers.
5.5.d.9.
Controls. Controls shall be a provision for plants greater than 100,000 gallons
per day. Inlets and outlets for all basin compartments shall suitably equip
accessible external valves, stop plates, weirs, or other devices to permit flow
control, level control, and the removal of an individual unit from service.
Also, there shall be a provision for facilities to measure and indicate liquid
levels and flow rates.
5.6. Settling.
5.6.a. Inlets. The design of inlets should be
to dissipate the inlet velocity, to distribute the flow equally, and to prevent
short-circuiting. The design of channels should be to maintain a velocity of at
least one foot per second at one-half design flow. There shall be provisions
for eliminating corner pockets and dead ends and use corner fillets or
channeling where necessary. There shall be provisions for elimination or
removal of floating materials in inlet structures having submerged
ports.
5.6.b. Dimensions. The
minimum length of flow from inlet to outlet shall be 10 feet unless special
provisions are made to prevent short-circuiting. The liquid depth of
mechanically cleaned settling tanks shall be as shallow as practicable, but not
less than seven feet. Sidewater depth for final clarifiers for activated sludge
shall not be less than 12 feet for plants greater than 100,000 gallons in
size.
5.6.c. Scum Removal. There
shall be effective scum collection and removal facilities, including baffling,
ahead of the outlet weirs on all settling tanks. There may be provisions for
discharge of scum with the sludge; other provisions may be necessary to dispose
of floating materials that may adversely affect sludge handling and
disposal.
5.6.d. Weirs. Overflow
weirs shall be adjustable. Weir loadings shall not exceed ten thousand 10,000
gallons per day per linear foot for plants designed for average flows of 1.0
mgd or less. Weir loadings for plants designed for flows in excess of 1.0 mgd
shall receive special consideration, but these loadings should not exceed
15,000 gallons per day per linear foot. If pumping is a requirement, pump
capacity shall relate to tank design to avoid excessive weir loading.
5.6.e. Submerged Surfaces. The tops of beams
and similar construction features submerged shall have a minimum slope of 1.4
vertical to 1 horizontal. The underside of these features shall have a slope of
one to one to prevent the accumulation of scum or solids.
5.6.f. Multiple Units. Multiple units capable
of independent operation shall exist at all plants having a capacity greater
than 100,000 gallons per day.
5.6.g. Protective and Servicing Facilities.
In plants greater than 100,000 gallons in size all settling tanks shall have a
provision for easy access for maintenance, and protection of operators. These
features include stairways, walkways, handrails, etc. If side walls extend some
distance above the liquid level to provide flood protection for other purposes,
there shall be convenient walkways to facilitate housekeeping and maintenance
of weirs.
5.6.h. Surface Settling
Rates.
5.6.h.1. Primary Settling Tanks.
Surface settling rates for primary tanks shall not exceed 1,000 gallons per day
per square foot at design flow or 1,500 gallons per day per square foot for
peak hourly flows, whichever is larger, for plants having a design flow of 1.0
mgd or less. The Commissioner may permit higher surface settling rates for
larger plants.
5.6.h.2.
Intermediate Settling Tanks. Surface settling rates for intermediate settling
tanks, when using following fixed film reactors, shall not exceed 1,500 gallons
per day per square foot based on their design flow.
5.6.h.3. Final Settling Tanks. Surface
settling rates for final settling tanks, based on maximum flow rates, shall be
as follows:
5.6.h.3.A. Fixed Film Biological
Reactors. Surface settling rates for settling tanks following trickling filters
or rotating biological contactors shall not exceed 1,200 gallons per day per
square foot based on peak hourly flow.
5.6.h.3.B. Activated Sludge. The hydraulic
design of intermediate and final settling tanks following the activated sludge
process shall be based upon the anticipated peak hourly rate for the area
downstream of the inlet baffle. The hydraulic loadings shall not exceed: 1,200
gallons per day per square foot for conventional, step aeration, contact
stabilization and the carbonaceous stage of separate-stage nitrification; 1,000
gallons per day per square foot for extended aeration; and 800 gallons per day
per square foot for the separate nitrification stage. The solids loading, that
includes the return activated sludge (RAS) concentration volume, for all
activated sludge processes shall not exceed 50 pounds of solids per day per
square foot at the peak rate. Package plants equal to or smaller than 5,000
gallons per day shall have a minimum of eight hours detention time in the
clarifier and plants between five thousand 5,000 and 40,000 gallons per day
shall have a minimum six-hours detention time in the clarifier, excluding the
bottom 2/3 of the hopper.
5.6.i. Freeboard. The walls of settling tanks
shall extend at least six inches above the surrounding ground surface and shall
provide not less than 12 inches freeboard. Additional freeboard or the use of
wind screens is recommended where larger settling tanks are subject to high
velocity wind currents that would cause tank surface waves and inhibit
effective scum removal.
5.6.j. Scum
Removal. Effective scum collection and removal facilities, including baffling,
shall exist for all settling tanks. The design shall recognize unusual
characteristics of scum that may adversely affect pumping, piping, sludge
handling and disposal. There may be provisions for the discharge of scum with
the sludge; however, other special provisions for disposal may be
necessary.
5.6.k. Sludge Removal.
There shall be provisions to permit continuous sludge removal from settling
tanks. Final clarifiers in activated sludge plants greater than 0.25 mgd shall
have positive scraping devices except for in-basin clarifiers. Each sludge
withdrawal line shall be at least four inches in diameter, if pumped, and, if
gravity flow, at least six inches in diameter and individually valved. This
does not apply to air lift methods of sludge removal rate. Head available for
withdrawal of sludge shall be at least thirty 30 inches. There shall be
adequate provisions for rodding or backflushing individual pipe runs. Piping
shall also exist to return waste sludge to primary clarifiers.
5.6.l. Sludge Hopper. The minimum slope of
the side walls shall be 1.7 vertical to 1 horizontal. Hopper wall surfaces
shall be smooth with rounded corners to aid in sludge removal. Hopper bottoms
shall have a maximum dimension of two feet.
5.7. Activated Sludge.
5.7.a. General. The use of activated sludge
process, and its various modifications, shall be permitted where sewage is
amenable to biological treatment.
5.7.b. Settling Tanks. The following
requirement is in addition to those set forth in subsection 5.6 of this rule:
5.7.b.1. Bypass. When using a primary
settling tank, there also shall be a provision for discharging raw sewage
directly to the aeration tanks to facilitate plant start-up and operation
during the initial stages of the plant design life.
5.7.c. Aeration.
5.7.c.1. Aeration Tanks.
5.7.c.1.A. General. There shall be multiple
tanks capable of independent operation for all plants rated at greater than
100,000 gallons per day. The size of the aeration tank for any particular
adaptation of the process shall be based on such factors as the size of the
plant, degree of treatment desired, sludge age, mixed liquor suspended solids
(MLSS) concentration, BOD loading and food to microorganism ratio (F/M). There
shall be calculations submitted to justify the basis of the aeration tank
capacity and process efficiency. When not submitting process design
calculations, it is a requirement to use the aeration tank capacities and
permissible loadings for the several adaptations of the processes shown in
Table 64-47-G., found at the end of this rule. These values apply to plants
receiving peak to average daily load ratios ranging from about 2-to-1 to
4-to-1. Thus, the Commissioner may consider the utilization of flow
equalization facilities to reduce the daily peak organic load as justification
to approve organic loading rates that exceed those specified in Table
64-47-G.
5.7.c.1.B. Arrangement of
Aeration Tanks. The dimensions of each independent mixed liquor aeration tank
shall be such as to maintain effective mixing and utilization of air. Liquid
depths shall not be less than 10 feet for plants greater than 100,000 gallons
per day. For very small tanks or tanks with special configuration, the shape of
the tank and the installation of aeration equipment should provide for
elimination of short-circuiting through the tank. Table 64-47-G. at the end of
this rule contains Permissible Aeration Tank Capacities and Loadings.
5.7.c.2. Inlets and Outlets.
Inlets and outlets for each aeration tank unit shall suitably equip valves,
gates, stop plates, weirs, or other devices to permit control of the flow and
to maintain reasonably constant liquid level. The hydraulic properties of the
system shall permit any single aeration tank unit out of service to carry the
maximum instantaneous hydraulic load.
5.7.c.3. Conduits. Design of channels and
pipes carrying liquids with solids in suspension shall be to maintain
self-cleaning velocities or shall agitate to keep the solids in suspension at
all rates of flow within the design limits.
5.7.c.4. Measuring Devices. For plants
designed for greater than 100,000 gallons per day, there shall be devices
installed for indicating flow rates of influent sewage, return sludge and air
to each aeration tank. For plants designed for greater than 1,000,000 gallons
per day, there shall be devices installed for totalizing, indicating, and
recording influent sewage and returned sludge to each aeration tank. Where the
design provides for mixing all returned sludge with the raw sewage, or primary
effluent, at one location, then measuring the mixed liquor flow rate to each
aeration unit is a requirement.
5.7.c.5. Freeboard and Foam Control.
5.7.c.5.A. Aeration tanks shall have a
freeboard of at least 18 inches.
5.7.c.5.B. Aeration tanks shall have foam
control devises on all plants greater than 10,000 gallons in size. Suitable
spray systems or other appropriate means is acceptable. The spray lines shall
have provisions for draining to prevent damage by freezing.
5.7.d. Aeration
Equipment.
5.7.d.1. General. Design of
aeration equipment shall be to supply sufficient oxygen to maintain a minimum
dissolved oxygen concentration of 2 mg/l throughout the mixed liquor at all
times. Aeration equipment shall be capable of transferring 1.1 lbs. of oxygen
per pound of peak BOD applied to the aeration tank with the exception of the
extended aeration process for which the value shall be 1.8. There shall be
calculations submitted to justify the oxygen requirements and the aeration
equipment capacity for plants greater than 100,000 gallons in size.
5.7.d.2. Nitrification. In the case of
nitrification, the oxygen requirement for oxidizing ammonia shall be added to
the above requirement for carbonaceous BOD removal. Taking the nitrogen oxygen
demand (NOD) as 4.6 times the daily peak TKN content of the influent is a
requirement. In addition, there shall be consideration given to the oxygen
demands due to recycle flows, heat treatment supernatant, vacuum filtrate,
elutriates, and others due to high concentrations of BOD and TKN associated
with the flows.
5.7.d.3. Controls.
There shall be variable air controls to aeration basins. There may be time
clocks, variable speed devices or variable depth weirs for the blowers or
aerators used. All extended aeration plants shall have a 24-hour time clock
graduated in 15-minute intervals.
5.7.d.4. Diffused Air Systems.
5.7.d.4.A. The design of aeration equipment
shall be to provide oxygen requirements as set forth in Table 64-47-H. at the
end of this rule.
5.7.d.4.B. The
requirements above shall include air volume standards for channels, pumps or
other air-use demands.
5.7.d.4.C.
The specified capacity of blowers or air compressors, particularly centrifugal
blowers, shall take into account that the air intake temperature may reach 40
degrees Celsius or 104 degrees Fahrenheit or higher and the pressure shall be
less than atmospheric.
5.7.d.4.D.
The blowers shall exist in multiple units, for plants of a capacity greater
than 20,000 gallons per day in size, so arranged and in such capacities as to
meet the maximum air demand with the single largest unit out of service. The
design shall also provide for varying the volume of air delivered in proportion
to the load demand of the plant.
5.7.d.4.E. The spacing of diffusers shall be
in accordance with the oxygenation requirements through the length of the
channel or tank and designed to facilitate adjustments of their spacing without
major revision to air header piping. The arrangement of diffusers shall also
permit their removal for inspection, maintenance, and replacement without
dewatering the tank and without shutting off the air supply to other diffusers
in the tank.
5.7.d.4.F. Individual
assembly units of diffusers shall equip control valves, preferably with
indicator markings for throttling or for complete shut-off. Diffusers in any
single assembly shall have substantially uniform pressure loss.
5.7.d.4.G. There shall be air filters to
prevent clogging of the diffuser system used and to protect the
blowers.
5.7.d.5.
Mechanical Aeration System.
5.7.d.5.A. The
design of the mechanism and drive unit shall be for the expected conditions in
the aeration tank in terms of the power performance. Certified testing shall
verify mechanical aerator performance.
5.7.d.5.B. A mechanical aeration system shall
also accomplish the following:
5.7.d.5.B.1.
Maintain all biological solids in suspension.
5.7.d.5.B.2. Meet maximum oxygen demand and
maintain process performance with the largest unit out of service. When system
capacity is greater than 20,000 gallons per day and when proposing single unit
installations, there shall be a provision for a spare aeration mechanism;
and
5.7.d.5.B.3. Provide for
varying the amount of oxygen transferred in proportion to the load demand on
the plant.
5.7.e. Return Sludge Equipment.
5.7.e.1. Return Sludge Rate. The rate of
sludge return shall vary by means of variable speed motors, drivers, air lifts
or timers to pump sludge. The rate of sludge return expressed as a percentage
of the average design flow of sewage shall generally be variable between the
limits shown in Table 64-47-I at the end of this rule.
5.7.e.2. Return Sludge Pumps. If using motor
driven return sludge pumps, the largest pump out of service shall obtain the
maximum return sludge capacity. Pump suctions shall equip a positive head.
Pumps shall have at least three-inch suction and discharge openings. If using
air lifts for returning sludge from each settling tank hopper, a standby unit
is not a requirement provided the design of the air lifts facilitate rapid and
easy cleaning and removal and applicant is providing other standby measures.
Air lifts shall be at least 2.5 inches in diameter.
5.7.e.3. Return Sludge Piping. Discharge
piping shall be at least three inches in diameter and the design shall be to
maintain a velocity of not less than two feet per second when return sludge
facilities are operating at normal return sludge rates.
5.7.e.4. Waste Sludge Facilities. Waste
sludge control facilities shall have a maximum capacity of not less than 25% of
the average rate of sewage flow and function satisfactorily at rates of 0.5% of
average sewage flow or a minimum of 10 gallons per minute, whichever is larger,
for plants greater than 100,000 gallons per day in size. Aerated sludge holding
tanks shall exist for all extended aeration plants up to 100,000 gallons per
day in size. The design of sludge holding tanks shall be with a minimum
capacity of 10% of the average daily design flow.
5.8. Trickling Filters.
5.8.a. Design. The design of filters shall be
so as to provide the reduction in carbonaceous and nitrogenous oxygen demand
required, and to properly condition the sewage for subsequent treatment
processes. The hydraulic loading on standard rate trickling filters shall be
between 2,000,000 and 4,000,000 gallons per acre per day with an organic
loading equal to or less than 400 pounds of BOD5 per
acre foot per day.
5.8.b. Dosing
Equipment.
5.8.b.1. Distribution. The sewage
distribution may be over the filter by rotary distributors or other suitable
devices that permit reasonably uniform distribution to the surface area. At
design average flow, the deviation from a calculated uniformly distributed
volume per square foot of the filter surface shall not exceed plus or minus 10%
at any point.
5.8.b.2. Dosing.
Sewage application to the filters may be by siphons, pumps, or by gravity
discharge preceding treatment units when suitable flow characteristics have
been developed. Application of sewage shall be practically continuous. A piping
system that permits recirculation shall be considered.
5.8.b.3. Hydraulics. There shall be careful
calculation of all hydraulic factors involving proper distribution of sewage on
the filters. For reaction type distributors, a minimum head of 25 inches
between low water level in siphon chamber and center of arms is a requirement.
There shall be surge relief to prevent damage to distributor seals, where
pumping sewage directly to the distributors.
5.8.b.4. Clearance. There shall be a minimum
clearance of six inches between media and distributor arms. This rule requires
greater clearance where icing occurs.
5.8.c. Media.
5.8.c.1. Quality. The media may be crushed
rock, slag, or plastic, or specially manufactured material. The media shall be
durable, resistant to spalling or flaking and relatively insoluble in sewage.
The top 18 inches shall have a loss by the 20-cycle, sodium sulfate soundness
test of not more than 10%, as prescribed by ASCE Manual of Engineering Practice
No. 13, "Filtering Materials for Sewage Treatment Plants." The balance to pass
a 10-cycle test using the same criteria. Slag media shall be free from iron.
Manufactured media shall be structurally stable and chemically and biologically
inert.
5.8.c.2. Rock or slag filter
media shall have a minimum depth of five feet above the underdrains.
Manufactured filter media shall have a minimum depth of 10 feet to provide
adequate contact time with the wastewater. Rock or slag filter media depths
shall not exceed 10 feet and manufactured filter media depths shall not exceed
30 feet.
5.8.c.3. Size and Grading.
5.8.c.3.A. Rock, slag and similar media shall
not contain more than 5% by weight of pieces whose longest dimension is three
times the least dimension. They shall be free from thin elongated flat pieces,
dust, clay, sand, or fine material and shall conform to the size and grading
when mechanically graded over vibrating screens with square openings according
to Table 64-47-J at the end of this rule.
5.8.c.3.B. Hand Picked Field Stone. The
maximum dimensions of stone shall be five inches; and minimum dimensions of
stone shall be three inches.
5.8.c.3.C. Manufactured Media. On a
case-by-case basis, the Commissioner shall evaluate applications of
manufactured media.
5.8.c.3.D.
Handling and Placing of Media. Storage of material delivered to the filter site
shall be on wood planks or other approved clean, hard surfaced areas.
Rehandling of all material shall take place at the filter site and there shall
be no dumping of material into the filter. Rescreening and forking crushed
rock, slag, and similar media at the filter site to remove all fines is
required. Placement of these material shall be by hand to a depth of 12 inches
above the tile so as not to damage the underdrains. The engineer may place the
remainder of the material. The engineer shall approve how applicant handles and
places manufactured media. There shall be no trucks, tractors, or other heavy
equipment driven over the filter during or after construction.
5.8.d. Underdrainage
System.
5.8.d.1. Arrangement. Underdrains with
semi-circular inverts shall exist and the underdrainage system shall cover the
entire floor of the filter. Inlet openings into the underdrains shall have an
unsubmerged gross combined area equal to at least 15% of surface area of the
filter.
5.8.d.2. Slope. The
underdrains shall have a minimum slope of 1%. The design of effluent channels
shall be to produce a minimum velocity of two feet per second at average daily
rate of application to the filter.
5.8.d.3. Flushing. There shall be a provision
for flushing the underdrains. The use of a peripheral head channel with
vertical vents is acceptable for flushing purposes. There shall be inspection
facilities.
5.8.d.4. Ventilation.
The design of the underdrainage system, effluent channels and effluent pipe
shall be to permit free passage of air. The size of drains, channels, and pipe
shall be such that not more than 50% of their cross-sectional area shall be
submerged under the design hydraulic loading. There shall be a provision in the
design of the effluent channels to allow the possibility of increased hydraulic
loading.
5.8.e. Special
Features.
5.8.e.1. Flooding. There shall be
provisions in the design of filter structures so that they may flood.
5.8.e.2. Maintenance. The installation of all
distribution devices, underdrains, channels, and pipes shall be so that an
applicant may properly maintain, flush, or drain them.
5.8.e.3. Freeboard. There shall be a
freeboard of four feet or more for tall, manufactured media filters to minimize
windblown spray.
5.8.e.4. Flow
Measurement. There shall be devices to permit measurement of flow to filter,
including recirculated flows.
5.8.e.5. Recirculation. The merits of
recirculation for various purposes; for example, to prevent drying of a
standard rate filter between dosings shall be considered.
5.8.f. Two-Stage Filters. The use of
two-stage filters when single stage filters may not accomplish the required
removals shall be considered.
5.8.g. Efficiencies. Calculating and
documenting expected efficiencies is required. The effect of climatic
conditions on the overall filter performance shall be considered.
5.8.h. Rotary Distributor Seals. This rule
does not permit the use of mercury seals. Ease of seal replacement shall be a
consideration in design.
5.9. Rotating Biological Contactors (RBCs).
5.9.a. Winter Protection. Year-round
operation requires covering of rotating contactors to protect the biological
growth from cold temperatures and the excessive loss of heat from the
wastewater with the resulting loss of performance. Construction of enclosures
shall be of a suitable corrosion resistant material. Windows or simple louvered
mechanisms shall be installed that can be opened in the summer and closed in
the winter to provide ventilation. To minimize condensation, the enclosure
shall have insulation or heat.
5.9.b. Required Pretreatment. Primary
settling tanks equipped with scum and grease collecting devices shall precede
RBCs. Bar screening or comminution are not suitable as the sole means of
pretreatment.
5.9.c. Unit Sizing.
Unit sizing shall be based on experience at similar full-scale installations or
thoroughly documented pilot testing with the particular wastewater. In
determining design loading rates, expressed in units of volume per day per unit
area of media covered by biological growth, the following parameters shall be
considered:
5.9.c.1. Design flow rate and
influent waste strength;
5.9.c.2.
Percentage of BOD to be removed;
5.9.c.3. Media arrangement, including number
of stages and unit area in each stage;
5.9.c.4. Rotational velocity of the
media;
5.9.c.5. Retention time
within the tank containing the media;
5.9.c.6. Wastewater temperature;
5.9.c.7. Percentage of influent BOD that is
soluble; and
5.9.c.8. In addition
to the above parameters, loading rates for nitrification shall depend upon
influent total Kjeldahl nitrogen (TKN), influent ammonia nitrogen
concentration, pH, and the allowable effluent ammonia nitrogen
concentration.
5.9.d.
Design Safety Factor. Daily load variations affect effluent concentrations of
ammonia nitrogen from the RBC process designed for nitrification. Therefore, it
may be necessary to increase the design surface area proportional to the
ammonia nitrogen daily peaking rates to meet effluent limitations. An
alternative is to provide flow equalization sufficient to insure process
performance within the required effluent limitations.
5.9.e. Air Driven Units. This rule does not
permit air driven units.
5.10. Sequential Batch Reactor (SBR) and
Intermittent Wastewater Treatment Systems.
5.10.a. Batch Reactor. Batch reactor and
intermittent treatment technologies shall use an alternating multiple-tank
system for new installations. Tank applications for renovating existing
treatment works or for facilities with flows equal to or less than 50,000
gallons per day shall be considered on a case-by-case basis, by the
Commissioner.
5.10.b. Aeration
Devises. Blowers or other aeration devices shall exist in multiple units for
treatment works that have a capacity of greater than 20,000 gallons per day.
The arrangement and capacity of blowers or other aeration devices shall be as
to meet the maximum air demand with the largest single unit out of
service.
5.10.c. Diffusers.
Individual assembly units of diffusers shall have control valves, preferably
with indicator markings for throttling or for complete shutoff.
5.10.d. Design Loadings. Five-day biochemical
oxygen demand loading and aeration requirements shall be no less than the
requirements specified by the manufacturer for each particular proprietary
sequencing batch reactor (SBR) process. An applicant shall obtain written
concurrence with the proposed design and specifications for a particular
installation from the manufacturer of a proprietary system or technology and
shall provide it with the project plans. Generally, an applicant should use an
average hydraulic detention time of 24 hours as a basis for design.
5.10.e. Operation. Each unit shall be capable
of independent operation during low, average, peak, and storm flow.
5.10.f. Decanting. There shall be provisions
to ensure that decanting cannot in any way occur during any phase of operation
except at the end of the "settle" or the "idle" phase or period.
5.10.g. Pre-treatment. A mechanically cleaned
bar screen having maximum clear openings between the bars of a half inch
(closer spacings are encouraged) shall precede SBR treatment plants.
Comminutors or other sewage grinders are not acceptable substitutes for this
requirement.
5.10.h. Scum Removal.
Each unit shall have a means of excluding scum and other floatables from
entering the decanter.
5.10.i.
Design Flow Rate. The design of downstream units and piping shall be based upon
the decanter flow rate, not the design flow of the treatment
facilities.
5.11.
Recirculating Sand Filters (RSF). The design of RSF systems can be to treat
flows as small as those generated by the individual home, up to any size for
which engineering considerations and economics would indicate the RSF system to
be the optimum choice, when comparing the RSF technology to other candidate
technologies.
5.11.a. Design Considerations.
All piping used in RSF systems shall comply with collection system piping
standards. Appropriate cleanouts or access ports shall be available in all
piping, to allow operator access for inspection and maintenance
purposes.
5.11.b. General
Description. The recirculating sand filter treatment system consists of a
septic tank, or Imhoff tank, followed by a recirculation tank, and then an open
sand filter. An applicant shall provide a pumping system with time clock
control mechanisms to provide a recirculation rate that results in fresh liquid
being dosed onto the surface of the sand filter. An applicant shall provide
float controls to override the time clocks, if flows increase to the point
where overflow is imminent, but the time clock is not yet ready to provide
power to the pumps.
5.11.c. Septic
Tank/Imhoff Tank Design. The design of septic tanks or Imhoff tanks are to be
in accordance with established design standards.
5.11.d. Recirculation Tank. Septic tank or
Imhoff tank effluents are directed, by gravity if possible, to a recirculation
tank. Normally, the tank size is to be equal to the incoming 24-hour flow,
assuming that the organic concentrations are within the range of normal
domestic sewage i.e., 150 350 mg/l BOD5. The primary
purpose of the recirculation tank is to receive underdrain flows from the sand
filter(s), to mix with the septic tank or Imhoff tank effluent. This maintains
a positive dissolved oxygen concentration in the recirculation tank, thus
eliminating any septic odors from being released when dosing the filters. There
shall be a provision for pumps in the recirculation tank to dose the filter(s)
on an intermittent basis.
5.11.e.
Dosing. A means of dosing the filters can be dosing troughs, spray nozzles, or
a central splash pad in the middle of the filter, or a dosing grid system. This
rule recommends spray nozzles to optimize distribution onto the filter. All
exposed dosing lines shall be self draining to prevent freezing during cold
weather periods.
5.11.e.1. Filter dosing
normally lasts for several minutes each hour, or half-hour periods. Dosing less
frequently than once every two hours is not a recommendation, although
applicant may vary the dose interval and dose volume. Dosing shall not occur
for more than 50% of a dosing cycle to allow aeration to occur between cycles.
This rule recommends a recirculation ratio of at least 12-to-1 (i.e.,
recirculation ratio equals daily flow dosed onto the filter(s) divided by the
average daily flow of sanitary wastes entering the treatment facility).
Recirculation ratios up to 25-to-1 may be appropriate, depending on the nature
of the wastes being treated.
5.11.e.2. The activation of the recirculation
pump(s) shall be by means of a time clock with not greater than 15-minute
increment settings. An applicant shall use a 96 pin, 24-hour clock, or another
timer approved by the Commissioner.
5.11.e.3. A single recirculation pump is
acceptable for a single-family home or smaller RSF system. An RSF system
serving a greater design load than a single-family home shall have duplex
pumps.
5.11.e.4. This rule
recommends volumes equal to one to four inches of depth over the filter during
each dosing cycle.
5.11.e.5. Piping
between the recirculation tank and filters shall allow dosing of any filter by
either duplex pump, via actuation of appropriate valves.
5.11.f. Electrical Controls. All electrical
wiring shall be in compliance with the National Electrical Code. This rule
recommends a control panel in a NEMA IV housing to preclude damage due to
inclement weather conditions unless the location of the controls is inside a
secure building.
5.11.f.1. There shall be high
and low liquid level control switches (i.e., mercury float switches, or
similar) installed in the recirculation tank. The high-level switch shall
activate at least one pump by overriding the timer control. The low-level
switch shall override the timer control to turn all pumps off. Placement of the
high-level switch should be several inches above the normal operating level in
the recirculation tank. Placement of the low-level switch should be several
inches above the pump intake. Actuation of either the high- or low-level
switches shall also cause activation of a visual or audible, or both, alarm
indicator to notify the operator of a potential operational problem.
5.11.f.2. Removing pumps and electrical
controls (i.e., high- and low-level switches, etc.) located in the
recirculation tank, shall be easy via "quick disconnect" piping and electrical
connections.
5.11.g.
Discharge Valving. The dischargement of treated sewage is only from the filter
underdrain piping. All underdrain piping is directed back into the
recirculation tank. There shall be a floating ball valve installed inside the
recirculation tank. At the maximum operating liquid level in the recirculation
tank, the ball valve shall close, and filter effluents shall bypass the tank to
disinfection. At lower operating liquid levels, filter effluents shall re-enter
the recirculation tank for further treatment.
5.11.h. Filter. Except for a single-family
home, all RSF systems shall include at least two filters, with filter
alternation accomplished manually. The overall filter area shall be based on a
design of [LESS THAN EQUAL TO] four gallons per day per square foot, based on
the average daily sewage flow entering the treatment facility.
5.11.h.1. The filter media shall be silica
sand, Black Beauty, graded bottom ash from coal-fired power plants, or other
media approved by the Commissioner. Filter media shall have a uniformity
coefficient of [LESS THAN EQUAL TO] 2.5 with an effective particle size of 0.5
to 1.5 mm.
5.11.h.2. The filter
media depth shall be [GREATER THAN EQUALS TO] 24 inches, with three layers of
support gravel in the underdrain. Support gravel layers shall be [GREATER THAN
EQUALS TO] 3 inches for each layer, with support gravel sizes as follows:
bottom layer, 1.5 inches to 0.75 inch; middle layer, 0.75 inch to 0.25 inch;
top layer 0.25 inch to 0.125 inch.
5.11.h.3. This rule does not recommend the
use of a filter fabric between the filter media and support gravel. A filter
fabric placed on top of the filter media may reduce maintenance
requirements.
5.11.h.4. Placement
of perforated underdrain piping shall be at the bottom of the filter prior to
placement of the gravel support material. Underdrain piping shall be [GREATER
THAN EQUALS TO] 4 inches in diameter or sized based on system hydraulics.
Underdrain piping shall lay on a 1% slope, at a spacing of no greater than 10
feet apart. The upper ends of all underdrain piping shall contain an elbow and
non-perforated riser pipe that shall terminate halfway between the top of the
filter media and the top of the filter sidewalls. The riser pipe shall be
available for inspection and maintenance to the underdrain without
necessitating excavation of the filter.
5.11.h.5. There shall be a filter sidewall
freeboard of 12 inches above the filter media. Filter sidewalls and bottoms
shall be impermeable. The slope of the filter bottoms shall be toward the
perforated underdrain piping at a grade of one inch vertical to one foot
horizontal.
5.11.h.6. Normal
operation of a multiple filter RSF system would allow one or more filters to be
"at rest" while the filter-in-use operates until "ponding" occurs; after that
the applicant manually alternates the filter-in-use. If ponding of a filter
does not occur within a one- to two-month period, this rule recommends manual
alternation. After ponding occurs on a filter, there shall be an allowance for
the filter to rest, the removal of clogging material from the top of the
filter, raking the media, and then releveling it as necessary.
5.11.i. Disinfection. Disinfection
of the RSF system effluent is required.
5.12. Constructed Wetlands Wastewater
Treatment Systems.
5.12.a. The Commissioner
shall review constructed wetlands wastewater treatment systems on a
case-by-case basis. Recommended design shall be on the basis of the latest
edition of the Tennessee Valley Authority's "General Design, Construction, and
Operation Guidelines Constructed Wetlands Wastewater Treatment Systems for
Small Users Including Individual Residences." Other acceptable designs are the
USEPA and NASA wetlands designs.
5.13. Other Biological & Mechanical
Systems.
5.13.a. New Biological &
Mechanical Treatment Schemes. New biological and mechanical treatment schemes
with promising applicability in wastewater treatment may be considered if the
applicant provides the required engineering data for new process evaluation in
accordance with paragraph 5.1.c.3. of this rule.
5.14. Sewage Stabilization Ponds, Anaerobic
Lagoons, and Aerated Lagoons. This rule does permit the use of stabilization
ponds, anaerobic lagoons, and aerated lagoons for treatment of raw sewage,
primary sewage effluent or secondary sewage effluent.
5.14.a. Stabilization Ponds.
5.14.a.1. Sizing. Stabilization ponds shall
have a minimum capacity of 65,000 gallons.
5.14.a.2. Wind Sweep. The location of
stabilization ponds shall be to permit an unobstructed wind sweep across the
ponds.
5.14.a.3. Water Supply. The
location of stabilization ponds shall be a minimum of 300 feet from public
water supplies using wells or springs. Maintaining a minimum distance of 600
feet if the public water supply well is down gradient from or lower in
elevation than the bottom of the sewage pond is required.
5.14.a.4. Geology and Soils. An applicant
shall obtain borings to determine surface and subsurface characteristics of the
pond site for all ponds greater than 2.5 acres in size or where required by the
commissioner. The soil conservation service, the U.S. Department of
Agriculture, requires a soil report for all pond sites.
5.14.a.5. Pond Shape. The shape of all ponds
should be such as to produce a uniform perimeter with no coves, islands or
peninsulas permitted. Corners of ponds are required to be round. The most
desirable shape of ponds is round, square, or rectangular with the length not
exceeding three times the width.
5.14.a.6. Design.
5.14.a.6.A. Loading. The design of
stabilization ponds shall be on the basis 34 pounds per day of five-day BOD per
acre.
5.14.a.6.B. Ponds in Series.
If one or more ponds are added in series with the primary pond, the primary
pond shall have a minimum volume of 65,000 gallons.
5.14.a.6.C. Depth. Liquid depth of ponds
shall be no less than 3.5 feet or greater than five feet. There shall be a
three-foot minimum freeboard.
5.14.a.7. Influent Lines.
5.14.a.7.A. Location of Discharge. Influent
lines shall extend 10 feet beyond the maximum pond depth and in no case, more
than one-fourth the length of the primary stabilization pond. Ponds following
the primary pond or secondary treatment facilities in multiple unit systems
shall be edge discharging.
5.14.a.7.B. Gravity. Influent lines from
gravity collection systems shall discharge at a point 12 to 18 inches above the
pond surface.
5.14.a.7.C. Pressure.
Pressure influent lines may discharge either above the pond surface or at a
point one foot above the pond bottom. When discharging below the pond surface,
the end of the pressure line shall rest upon a concrete apron of two square
feet minimum size.
5.14.a.7.D. Pipe
Support. Piers or other open structures shall support influent lines. This rule
does not permit dikes for pipe support.
5.14.a.8. Pond Details.
5.14.a.8.A. Embankments. The construction of
embankments shall be of compacted impervious materials with a minimum top width
of eight feet. This rule requires the removal of all vegetation from the area
upon which the embankment is to be placed.
5.14.a.8.B. Slope. Embankment slopes shall
not be steeper than two feet horizontal to one foot vertical. Minimum slopes
shall not be flatter than four feet horizontal to one foot vertical.
5.14.a.8.C. Pond Bottom. Pond bottoms shall
be level and cleared of all vegetation and debris.
5.14.a.8.D. Watertightness. If soil
characteristics are such that seepage shall take place, ponds shall be
watertight through use of a pond liner of man-made materials with a minimum
thickness of 60 mil required, or clay or through use of a soil additive,
approved by the Commissioner.
5.14.a.9. Effluent Lines.
5.14.a.9.A. Discharge. The design of the
effluent line shall be to discharge from a point 18 inches below the surface of
the pond. There may be a provision to vent the effluent line to prevent
siphoning. The effluent line shall discharge on a concrete slab or rip-rap
apron. The placement of effluent lines shall be at the furthest point from the
influent line discharge.
5.14.a.9.B. Discharge Structure. For ponds
greater than 2.5 acres in size, there shall be discharge structures capable of
variable depth control. Depth shall be adjustable between 3.5 and five feet in
increments of 0.5 foot or less. Spacing of withdrawal points shall be from 18
inches below the surface to 12 inches above the pond bottom discharge
structures. Placement of these structures shall be at a point farthest from the
influent line discharge and be readily accessible from the
embankment.
5.14.a.9.C.
Recirculation. Recirculation should be a consideration for multiple pond
facilities. When proposing recirculation, thereby reducing pond size, applicant
shall submit calculations justifying the proposed reduction to the commissioner
for approval.
5.14.a.10.
Drain Lines. This rule does not permit drain lines.
5.14.a.11. Miscellaneous.
5.14.a.11.A. Surface Runoff. There shall be a
provision to divert storm and surface water around stabilization
ponds.
5.14.a.11.B. Fencing.
Enclosing ponds with a stock-tight fence a minimum of six feet in height with a
locked entrance gate is a requirement.
5.14.a.11.C. Signs. There shall be several
signs stating the nature of the facility installed on the fence.
5.14.a.11.D. Prefilling. This rule requires
prefilling stabilization ponds with water to a minimum depth of two feet prior
to use.
5.14.a.11.E. Access Road.
There shall be an all-weather access road to the pond site.
5.14.b. Anaerobic
Lagoons.
5.14.b.1. General. Anaerobic lagoons
shall generally be used for animal waste treatment.
5.14.b.2. Location. The location of anaerobic
lagoons shall be a minimum of 1,500 feet from the nearest occupied
structure.
5.14.b.3. Water Supply.
Distance from a drinking water supply shall comply with paragraph 5.14.a.3. of
this rule.
5.14.b.4. Geology and
Soils. These shall comply with paragraph 5.14.a.4. of this rule.
5.14.b.5. Lagoon Shape. This shall comply
with paragraph 5.14.a.5. of this rule.
5.14.b.6. Design. Design shall comply with
the Waste Treatment Lagoon Code 359, published October 2017 by the USDA Natural
Resources Conservation Service.
5.14.c. Aerated Lagoons.
5.14.c.1. General. Aerated lagoon sewage
treatment facility shall consist of the following:
5.14.c.1.A. Pretreatment;
5.14.c.1.B. Aeration basin;
5.14.c.1.C. Settling basin, if required;
and
5.14.c.1.D. Supplementary
treatment, if required.
5.14.c.2. Water Supply. Distance from a
drinking water supply shall comply with paragraph 5.14.a.3. of this
rule.
5.14.c.3. Geology and Soils.
These shall comply with paragraph 5.14.a.4. of this rule.
5.14.c.4. Shape. The shape shall comply with
paragraph 5.14.a.5. of this rule.
5.14.c.5. Design.
5.14.c.5.A. Method. The design of aeration
basins is normally based upon the aerated lagoon theory using a
Ke of 0.5 (at 20 degrees C). Formulas to be used are: t
= % removal/(100-% removed) KT = days detention where:
KT = 0.5 (1.075)T-20
T = average year-round air temperature at the site in degrees C.
The dissolved oxygen level should be a minimum of 2 ppm and assumed that ratio of oxygen transfer should be at (0.9). The oxygen requirement should be based upon the removal of 1.5 pounds/pound of BOD5.
5.14.c.5.B. Depth. The aeration basin shall
be of a depth ranging from six to 15 feet. Supplying air to the aeration basin
shall be by means of surface aerators or subsurface air diffusers. A 96-pin
time clock shall operate each surface aerator. The design of basins shall be to
distribute oxygen throughout, but not to keep solids in suspension.
5.14.c.5.C. Settling. A settling pond shall
follow the aeration basin. The size of the settling pond shall be based upon
BOD5 remaining after aeration at the loading rate of 34
pounds of BOD5 per surface acre per day.
5.14.c.6. Lagoon Details. Lagoon
shape, dikes, embankments, construction, and effluent lines shall comply with
paragraph 5.14.b.6. of this rule.
5.15. Disinfection.
5.15.a. General. There shall be adequate
disinfection of all sewage treatment plant effluents prior to discharge. All
wastewater treatment works using gas chlorination shall have a Chlorine
Institute chlorine repair kit.
5.15.b. Chlorination.
5.15.b.1. Chlorine Terminology. The word
"chlorine" whenever used in this section refers to dry chlorine unless
otherwise indicated.
5.15.c. Equipment.
5.15.c.1. Feed Equipment Type. This rule
generally prefers solution-feed vacuum-type chlorinators for plants greater
than 100,000 gallons per day in size. There shall be consideration given to the
use of hypochlorite solution feeders of the positive displacement type. For
plants of 100,000 gallons per day or less in size, using tablet type
chlorinators shall receive approval.
5.15.c.2. Feed Equipment Capacity.
Chlorinator capacities required may vary, depending on the use and point of
application of the chlorine. For disinfection, the capacity shall be such to
produce a residual of 0.5 ppm maximum in the final effluent at peak flow
rates.
5.15.c.3. Chlorination
Equipment and Spare Parts. It is a requirement to maintain an inventory of
parts subject to wear and breakage at all times. This rule requires dual
chlorinators for plants over 100,000 gallons per day in size. Each chlorinator
shall be able to provide the required chlorination at peak flow rates. If the
discharge is within a five-mile distance up-stream from a public water supply,
chlorination of the sewage effluent shall be a requirement unless a written
waiver is granted by the Commissioner.
5.15.c.3.A. Water Supply. A supply of water
shall be available for operating the chlorinators. When a booster pump is
required, there shall be duplicate pumping equipment. When a connection is made
from the domestic water supplies, there shall be a provision for equipment for
backflow prevention. There shall be pressure gauges on chlorinator water supply
lines.
5.15.c.3.B. Measurement
Equipment. There shall be equipment for measuring the amount of chlorine
use.
5.15.c.4.
Evaporators. When manifolding of several cylinders is required to feed
sufficient chlorine, there shall be consideration given to the installation of
evaporators.
5.15.c.5. Leak
Detection and Controls. A bottle of ammonium hydroxide solution shall be
available for detecting chlorine leaks. Also, there shall be consideration
given to the provision of caustic soda solution reaction tanks for absorbing
the contents of leaking one-ton cylinders where the cylinders are in use. There
shall be installation of automatic leak detectors wherever using gas
chlorination.
5.15.d.
Piping and Connections.
5.16.d.1. General.
Piping systems shall be well supported, adequately sloped to allow drainage and
protection from mechanical damage. Due to changes in temperature, there shall
be allowance for pipe expansion.
5.15.d.2. Condensation. When a vaporizer does
not provide adequate superheat, a pressure reducing valve shall be used to
prevent condensation.
5.15.d.3. The
arrangement of chlorine solution piping shall be such that any or all
chlorinators may pre-chlorinate and post-chlorinate.
5.15.e. Housing.
5.15.e.1. Building. The design and
construction of any building to house chlorine equipment or containers shall be
to protect all elements of the chlorine system from fire hazards. If storing or
processing flammable materials in the same building with chlorination equipment
other than that using hypochlorite solutions, there shall be a fire wall
erected to separate the two areas.
5.15.e.1.A.
If gas chlorination equipment and chlorine cylinders are to be in a building
used for other purposes, a gas-tight partition shall separate this room from
any other portion of the building. Doors to this room shall equip panic
hardware and applicant shall install a chlorine detector/alert system. The
rooms shall be at ground level and shall permit easy access to all equipment.
Storage area shall be separated from the feed area. This rule does not permit a
basement.
5.15.e.1.B. There shall
be a means of exit to the outside of the building from each separate room or
building in which applicant is storing, handling, or using chlorine, other than
hypochlorite.
5.15.e.1.C. There
shall be installation of a clear glass, gas-tight window in an exterior door or
interior wall of the chlorinator room to permit viewing of the chlorinator
without entering the room.
5.15.e.2. Heat. There shall be chlorinator
rooms with a means of heating and maintaining a temperature of at least 60
degrees Fahrenheit. The room shall also have protection from excess
heat.
5.15.e.3. Ventilation. There
shall be installation of forced, mechanical ventilation that provides one
complete air change per minute in all chlorine feed rooms and rooms where
storing chlorine cylinders. The entrance to the air exhaust duct from the room
shall be near the floor and the location of the point of discharge shall be so
as not to contaminate the air inlets to any building or inhabited areas. The
location of air inlets shall be so as to provide cross ventilation with air and
at such a temperature that shall not adversely affect the chlorination
equipment. The vent hose shall run without traps from the chlorinator and shall
discharge to the outside atmosphere above grade.
5.15.e.4. Electrical Controls. The controls
for the fans and lights shall be such that they shall automatically operate
when the door is opened and manually operated from the outside without opening
the door.
5.15.e.5. Respiratory
Protection. Respiratory air-pac protection equipment, meeting the requirements
of the National Institute for Occupational Safety and Health (NIOSH), shall be
available where the handling of chlorine gas takes place, and stored at a
convenient location, but not inside any room when using or storing chlorine.
There shall be instructions posted for using the equipment. The units shall use
compressed air, have at least a 30-minute capacity, and be compatible with the
units used by the fire department responsible for the plant. This rule requires
a minimum of two air-pacs.
5.15.f. Application of Chlorine.
5.15.f.1. Mixing with Flow. There shall be
provisions to ensure uniform mixing of the chlorine solution with the
wastewater flow near the point of application.
5.15.f.2. Contact Period. There shall be a
minimum contact period of 40 minutes at average daily flow or 15 minutes at
maximum daily flow. Additional contact time may be a requirement if the
discharge point is in proximity to a water supply intake, recreational area, or
some other similar area.
5.15.f.3.
Contact Tank. Design of chlorine contact tanks shall be to minimize
"short-circuiting" of flow. There shall be over and under, or end-around,
baffling provided. This rule requires air lift sludge returns from the contact
tank for all extended aeration sewage treatment plants unless preceded by a
filter or polishing pond. This rule requires multiple units for plants over
100,000 gallons in size.
5.15.g. De-chlorination. The removal of all
or part of the chlorine residual may be a requirement prior to final discharge,
to meet the adopted stream standards or other requirements for particular
streams.
5.15.g.1. Other Methods. The
Commissioner shall evaluate the use of other methods for disinfection on a
case-by-case basis. As a minimum, there shall be an investigation when
intending to use other disinfection methods.
5.15.g.2. Minimum effluent conditions, such
as clarity, soluble organics and pH are required for adequate
disinfection.
5.15.g.3. Methods for
dispersion and mixing with the waste stream are required.
5.15.g.4. Other factors, including but not
limited to, equipment reliability, safety and application rates are required
for varying waste flows.
5.15.g.5.
Refer to paragraph 5.1.c.3. of this rule.
5.15.h. Evaluation of Effectiveness.
5.15.h.1. Sampling. There shall be facilities
included for securing a sample prior to discharge to determine the
effectiveness of the disinfection method.
5.15.h.2. Residual Chlorine Testing and
Control. When using chlorine for disinfection, there shall be equipment for
measuring chlorine residual. When the discharge occurs in critical areas, the
installation of facilities for continuous automatic chlorine residual analysis,
recording and proportioning systems may be a requirement.
5.16. Supplementary Treatment.
5.16.a. General. Supplementary treatment
shall be a requirement when health considerations or waste load allocations and
effluent limitations require treatment more stringent than secondary.
5.16.b. Alternating Surface Sand Filters.
5.16.b.1. General. Normally, an applicant
shall use alternating surface sand filters for plants of 100,000 gallons per
day or less in size. The commissioner may permit alternating surface sand
filters for plants of over 100,000 gallons per day in size on a case-by-case
basis. No individual surface sand filter shall exceed 500 square
feet.
5.16.b.2. Filter Rate. The
design of an alternating sand filter shall be for a filter rate of not more
than 20 gallons per square foot per day.
5.16.b.3. Application. The effluent
application shall be with either a pump or siphon chamber designed to dose all
sections of the filter equally with three to four inches of liquid in 20
minutes or, where elevation differences permit, the Commissioner may permit
gravity application of effluent to the filter if the distribution of the
effluent is uniform.
5.16.b.4.
Location. The location of alternating surface sand filters shall not be within
100 feet of the nearest occupied residence or habitation. The commissioner may
waive this distance requirement in the event applicant obtains a release from
the neighboring property owner or owners.
5.16.b.5. Media. The sand used in alternating
surface sand filters shall be coarse, clean sand of uniform size. Effective
size of 0.5 to 1.5 mm in diameter with a uniformity coefficient of no greater
than 3.0 and less than 1% fines passing a 100 sieve. The Commissioner may waive
this requirement if finding the media is to perform in an adequate
manner.
5.16.b.6. Construction. The
side walls, dividing partitions and bottom of the sand filters shall be
impermeable. General construction shall be as shown in the Portfolio of
Drawings.
5.16.b.7. Disinfection.
This rule requires disinfection after the filters and before discharge to a
stream.
5.16.c. High-Rate
Effluent Filtration.
5.16.c.1. General.
High-rate filters may be either gravity or pressure.
5.16.c.1.A. Pressure. This rule limits the
use of pressure high-rate filters to plants of greater than 100,000 gallons per
day in size.
5.16.c.2.
Filtration Rates. Allowable rates for gravity filters shall not be greater than
one gallon per minute per square foot per day. Filtration rates for pressure
filters shall not be greater than five gallons per minute per square foot per
day. Rates are based upon the maximum flow rate applied.
5.16.c.3. Number of Units. There shall be
total filter area in two or more units, and calculation of the filtration rate
shall be on the total available filter area with one unit out of service, for
plants of 40,001 gallons per day or more in size.
5.16.c.4. Backwash. Backwash shall include
either or both air scouring and positive surface wash. There shall be a
provision for using filtered effluent for backwash and waste filter backwash
water. It shall return to the head of the plant.
5.16.c.4.A. Backwash Water Storage. Total
backwash water storage capacity required shall equal or exceed one complete
backwash cycle.
5.16.c.4.B.
Backwash Rate. The backwash rate shall not exceed 20 gallons per minute per
square foot with a minimum backwash period of 10 minutes.
5.16.c.4.C. Pumps. An applicant shall size
and interconnect pumps for backwashing filter units to provide the required
rate to any filter with the largest pump out of service.
5.16.c.5. Proprietary Equipment. Where
proposing proprietary filtration equipment not conforming to the preceding
requirements, an applicant shall provide data that supports the capability of
the equipment to meet effluent requirements under design conditions. The
Commissioner shall consider the equipment on a case-by-case basis.
5.16.c.6. Equipment Serving Plants with
Design Flows of 40,000 Gallons Per Day or Less. When proposing filtration
equipment serving plants with design flows of 40,000 gallons per day or less
not conforming to the preceding requirements, an applicant shall provide data
that supports the capability of the equipment to meet effluent requirements
under design conditions. The Commissioner shall consider the equipment on a
case-by-case basis.
5.16.d. TKN Removal.
5.16.d.1. General. Consideration shall be
given to TKN removal when the total Kjeldahl nitrogen limit as stated in the
discharge load allocation is less than 18 mg/l.
5.16.d.2. Methods. Methods used to achieve
TKN removal may include, but not be limited to: additional aeration in extended
aeration plants; separate stage nitrification; break-point chlorination;
nitrification column; and alternating surface sand filters.
5.16.e. Microscreening.
5.16.e.1. General. An applicant may use
microscreening units following a biological treatment process for the removal
of residual suspended solids.
5.16.e.2. Materials. Microscreen shall be
either a specially woven polyester or stainless steel with aperture size of 20
to 30 microns.
5.16.e.3. Design.
The hydraulic loading shall not be greater than 10 gallons per minute per
square foot of submerged drum surface. Maximum head loss shall be 12 to 18
inches. There shall be an overflow weir to bypass part of the flow when head
exceeds six to eight inches. It is recommended that drums be not less than 10
feet in diameter.
5.16.e.4.
Backwash. Application of continuous pressurized (60 psig) backwash shall be at
a minimum rate of eight gallons per minute per square foot of screen. There
shall be dual backwash pumps, with each pump being capable of supplying 100% of
the required flow. Backwash water shall return to the head of the plant at a
rate not to exceed 15% of the average daily design flow.
5.16.e.5. Reliability. There shall be dual
microscreen units with each unit being capable of providing 100% of the design
microscreen capacity. There shall be automatic drum speed controls with
provision for manual override for each screen. It is a requirement to enclose
all units in a heated and ventilated structure.
5.16.f. Polishing Ponds.
5.16.f.1. General. The design of polishing
ponds shall be in accordance with Section 5.14.b. of this rule. Polishing ponds
shall have a capacity of at least 65,000 gallons or capacity for a detention
time of 10 days plant design flow, whichever is greater.
5.16.f.2. Distance Requirements. The location
of polishing ponds shall be at least 100 feet from the nearest occupied
structure.
5.16.g. Post
Aeration. Meeting a discharge load allocation of 6.0 milligrams per liter
dissolved oxygen shall be by means of one of the following:
5.16.g.1. Post aeration tank with air added
by diffusion or mechanical means;
5.16.g.2. Cascade aeration; or
5.16.g.3. Polishing ponds shall provide the
dissolved oxygen requirements.
5.17. Sludge Handling and Disposal.
5.17.a. Anaerobic Sludge Digestion.
5.17.a.1. Multiple Units. This rule
recommends multiple tanks. When using a single digestion tank, there shall be
an alternate method of sludge processing or emergency storage to maintain
continuity of service.
5.17.a.2.
Depth. For those units proposed to serve as supernatant separation tanks, the
depth shall be sufficient to allow for the formation of a reasonable depth of
supernatant liquor. This rule recommends a minimum sidewater depth of 10
feet.
5.17.a.3. Maintenance
Provisions. To facilitate draining, cleaning, and maintenance, the following
features are desirable:
5.17.a.3.A. Slope. The
tank bottom should slope to drain toward the withdrawal pipe. For tanks
equipped with a suction mechanism for withdrawal of sludge, this rule
recommends a bottom slope not less than 1:12. When the sludge removal is to be
by gravity alone, this rule recommends 1:4 slope.
5.17.a.3.B. Access Manholes. In addition to
the gas dome, there shall be at least two 36-inch diameter access manholes in
the top of the tank. There shall be stairways to reach the access manholes.
There shall be a separate sidewall manhole. The opening should be large enough
to permit the use of mechanical equipment to remove grit and sand.
5.17.a.3.C. Safety. There shall be
non-sparking tools, safety lights, rubber-soled shoes, safety harness, gas
detectors for inflammable and toxic gases and at least two self-contained
breathing units for emergency use.
5.17.a.4. Sludge Inlets and Outlets.
5.17.a.4.A. Recirculation. There shall be
multiple recirculation withdrawal and return points, unless incorporating
mixing facilities within the digester. The return shall discharge above the
liquid level and the location shall be near the center of the tank.
5.17.a.4.B. Raw Sludge Discharge. Raw sludge
discharge to the digester shall be through the sludge heater and recirculation
return piping, or directly to the tank if there are internal mixing
facilities.
5.17.a.4.C. Withdrawal.
Sludge withdrawal to disposal shall be from the bottom of the tank. This pipe
shall interconnect with the recirculation piping.
5.17.a.5. Tank Capacity. The determination of
the total digestion tank capacity shall be by rational calculations based upon
such factors as volume of sludge added, its percent solids and character, the
temperature to maintain in the digesters, the degree or extent of mixing to
obtain and the degree of volatile solids reduction required. An applicant shall
submit calculations to the Commissioner, to justify the basis of design. When
the calculations are not based on the above factors, the minimum combined
digestion tank capacity design shall be based on: the assumption that a raw
sludge evolves from ordinary domestic wastewater, that a maintained digestion
temperature is to be in the range of 90 degrees Fahrenheit to 100 degrees
Fahrenheit or (32 degrees Celsius and 38 degrees Celsius), that the digested
sludge shall maintain 40% to 50% volatile matter, and that there shall be
frequent removal of the digested sludge from the system.
5.17.a.5.A. Completely-Mixed Systems.
Completely-mixed systems shall provide for effective mixing. Loading the system
may be at a rate up to 80 pounds of volatile solids per 1,000 cubic feet of
volume per day in the active digestion units. When there are no grit removal
facilities, reducing the digester volume due to grit accumulation shall be
considered.
5.17.a.5.B.
Moderately-Mixed Systems. For digestion systems where accomplishing mixing is
only by circulating sludge through an external heat exchanger, loading the
system may be at a rate up to 40 pounds of volatile solids per 1,000 cubic feet
of volume per day in the active digestion units. Modification to this loading
may be upward or downward depending upon the degree of mixing
provided.
5.17.a.6. Gas
Collection, Piping, and Appurtenances.
5.17.a.6.A. General. The design of all
portions of the gas system, including the space above the tank liquor, the
storage facilities, and the piping, shall be so that under all normal operating
conditions, including sludge withdrawal, the gas shall be maintained under
positive pressure. All enclosed areas where any gas leakage might occur shall
have adequate ventilation.
5.17.a.6.B. Safety. When producing gas all
safety facilities shall be used. There shall be pressure and vacuum relief
valves and flame traps, along with automatic safety shutoff valves. This rule
does not permit water seal equipment. Housing gas safety equipment and gas
compressors shall be in a separate room with an exterior entrance.
5.17.a.6.C. Gas Piping and Condensate. Gas
piping shall be of adequate diameter and shall slope to condensate traps at low
points. This rule does not permit the use of float-controlled condensate
traps.
5.17.a.6.D. Gas Utilization
Equipment. The location of gas-fired boilers for heating digesters shall be in
a separate room not connected to the digester gallery.
5.17.a.6.E. Electrical Fixtures. Electrical
fixtures and controls in places enclosing anaerobic digestion appurtenances,
when the tanks and piping normally contain hazardous gases, shall comply with
the National Electrical Code for Class 1, Group D, Division 2 locations. An
applicant shall isolate digester galleries from normal operating areas to avoid
an extension of the hazardous location.
5.17.a.6.F. Waste Gas. Waste gas burners
shall be readily accessible and located at least 25 feet away from any plant
structure if placed at ground level or located on the roof of the control
building if sufficiently removed from the tank. All waste gas burners shall
equip an automatic ignition, such as a pilot light or a device using a
photoelectrical cell sensor. The use of natural or propane gas to ensure
reliability of the pilot light shall be considered. Discharging the gas to the
atmosphere through a return-bend screened vent terminating at least 10 feet
above the ground surface, provided that the assembly incorporates a flame trap,
may be permissible in remote locations.
5.17.a.6.G. Ventilation. Any underground
enclosures connecting with digestion tanks, or containing sludge, gas piping or
equipment shall be equipped with forced ventilation. The piping gallery for
digesters shall not connect to other passages. If self-closing doors are used
at connecting passageways and tunnels to minimize the spread of gas, they shall
be tightly fitting.
5.17.a.6.H.
Meter. There shall be a gas meter with a bypass to meter total gas
production.
5.17.a.7.
Digester Heating.
5.17.a.7.A. Insulation.
Wherever possible, the construction of tanks shall be above ground water level
and suitably insulated to minimize heat loss.
5.17.a.7.B. Heating Facilities. Sludge may be
heated by circulating it through external heaters or using heating units
located inside the digestion tank.
5.17.a.7.B.1. The design of piping for
external heating shall be to provide for the preheating of feed sludge before
introduction to the digesters. There shall be provisions in the layout of the
piping and valving to facilitate cleaning of these lines. The sizing of heat
exchanger sludge piping should be for heat transfer requirements.
5.17.a.7.B.2. Other Heating Methods. The
Commissioner shall consider other types of heating facilities on their own
merits.
5.17.a.7.C.
Heating Capacity. There shall be heating capacity sufficient to consistently
maintain the design sludge temperature. When using a digester tank gas for
sludge heating, an auxiliary fuel supply is required.
5.17.a.7.D. Hot Water Internal Heating
Controls.
5.17.a.7.D.1. There shall be an
automatic mixing valve to temper the boiler water with return water so that the
inlet water to the heat jacket can be held below a temperature at which caking
shall be accentuated. In addition, there shall be manual control provided by
bypass valves.
5.17.a.7.D.2. The
boiler shall equip automatic controls to maintain the boiler temperature at
approximately 180 degrees Fahrenheit to shut off the main gas supply in the
event of pilot burner or electrical failure, low boiler water level, or
excessive temperature.
5.17.a.7.D.3. There shall be thermometers to
show temperatures of the sludge, hot water feed, hot water return, and boiler
water.
5.17.a.8. Supernatant Withdrawal.
5.17.a.8.A. Piping Size. Supernatant piping
shall not be less than six inches in diameter.
5.17.a.8.B. Withdrawal.
5.17.a.8.B.1. Arrangement of piping shall be
so that withdrawal can be made from three or more levels in the digester. There
shall be a positive unvalved vented overflow.
5.17.a.8.B.2. If providing a supernatant
selector, provisions shall be made for at least one other drawoff level located
in the supernatant zone of the tank in addition to the unvalved emergency
supernatant drawoff pipe. There shall be high pressure backwash
facilities.
5.17.a.8.C.
Sampling. There shall be provisions for sampling at each supernatant drawoff
level. Sampling pipes shall be at least 1.5 inches in diameter and shall
terminate at a suitably-sized sampling sink or basin.
5.17.a.8.D. Alternate Supernatant Disposal.
An applicant shall give consideration to supernatant conditioning, when
appropriate, in relation to its effect on plant performance and effluent
quality.
5.17.b. Aerobic Sludge Digestion.
5.17.b.1. General. Using aerobic digestion
may stabilize secondary sludge. There shall be digestion in single or multiple
tanks, designed to provide effective air mixing, reduction of the organic
matter, supernatant separation, and sludge concentration under controlled
conditions.
5.17.b.2. Digestion
Tanks. This rule recommends multiple tanks. An applicant may use a single
sludge digestion tank in the cases of small treatment plants, when making
provisions for sludge handling, or when a single unit shall not adversely
affect normal plant operations.
5.17.b.3. Mixing and Air Requirements. Design
of aerobic sludge digestion tanks shall be for effective mixing by aeration
equipment. There shall be sufficient air to keep the solids in suspension and
maintain dissolved oxygen between one and two milligrams per liter. There shall
be a minimum mixing and oxygen requirement of 30 cfm per 1,000 cubic feet of
tank volume with the largest blower out of service. If using diffusers, the
non-clog type is a requirement, and their design shall be to permit continuity
of service. If using mechanical aerators, there shall be a minimum of 1.0
horsepower per 1,000 cubic feet. This rule discourages the use of mechanical
equipment in areas where freezing temperatures are typical.
5.17.b.4. Tank Capacity. The determination of
tank capacities shall be based on rational calculations, including such factors
as quantity of sludge produced, sludge characteristics, time of aeration, and
sludge temperature.
5.17.b.4.A. Volatile
Solids Loading. The volatile suspended solids loading shall not exceed 100
pounds per 1,000 cubic feet of volume per day in the digestion units. Lower
loading rates may be necessary depending on temperature, type of sludge, and
other factors.
5.17.b.4.B. Solids
Retention Time. Required minimum solids retention time for stabilization of
biological sludges varies depending on type of sludge. Normally, there shall be
a minimum of 15 days retention for waste activated sludge and 20 days for
combination of primary and waste activated sludge, or primary sludge alone. In
areas where sludge temperature is lower than 50 degrees Fahrenheit, additional
detention time shall be considered.
5.17.b.5. Supernatant Separation. There shall
be facilities for separation and withdrawal of supernatant and for collection
and removal of scum and grease.
5.17.b.6. Sludge Thickening. Prior to
placement on sludge drying beds, all sludge produced by the activated sludge
process shall condition to a minimum solids content of 2% by weight.
5.17.c. Sludge Pumps and Piping.
5.17.c.1. Sludge Pumps.
5.17.c.1.A. Duplicate Units. There shall be
duplicate units.
5.17.c.1.B. Type.
There shall be plunger pumps, screw feed pumps, recessed impeller type
centrifugal pumps, progressive cavity pumps, or other types of pumps capable of
solids handling for handling raw sludge.
5.17.c.1.C. Minimum Head. There shall be a
minimum positive head of 24 inches at the suction side of centrifugal-type
pumps and that minimum is desirable for all types of sludge pumps. Maximum
suction lifts shall not exceed 10 feet for plunger pumps.
5.17.c.1.D. Sampling Facilities. Unless
sludge sampling valves are installed at the sludge pumps, the size of valve and
piping shall be at least 1.5 inches.
5.17.c.2. Sludge Piping.
5.17.c.2.A. Size and Head. Sludge withdrawal
piping shall have a minimum diameter of six 6 inches for gravity withdrawal and
three inches for pump suction and discharge lines. When withdrawal is by
gravity, the available head on the discharge pipe shall be adequate to provide
at least 3.0 feet per second velocity.
5.17.c.2.B. Slope. Gravity piping shall be
laid on uniform grade and alignment. The slope of gravity discharge piping
shall not be less than 3%. There shall be provisions for cleaning, draining and
flushing discharge lines.
5.17.c.2.C. Supports. The corrosion
resistance and continuing stability of supporting systems located inside the
digestion tank shall receive special consideration.
5.17.d. Sludge Dewatering.
5.17.d.1. Sludge Drying Beds. Estimating the
sizing of the drying bed shall be on the basis of four-square foot capita when
the drying bed is the primary method of dewatering, and one square foot capita
if using it as a back-up dewatering unit. Under no circumstances shall surface
water enter the bed areas.
5.17.d.2. Design.
5.17.d.2.A. Gravel. An applicant shall grade
the lower course of gravel around the underdrains, and it shall be 12 inches in
depth, extending at least six inches above the top of the underdrains. It is
desirable to place this in two or more layers. The top layer of at least three
inches shall consist of gravel one eighth 0.125 inch to 0.25 inch in
size.
5.17.d.2.B. Sand. The top
course shall consist of six to nine inches of clean washed coarse sand with an
effective size of 0.3 to 0.6 mm in diameter with a uniformity coefficient of no
greater than 4.0 and less than 1% fines passing number 100 sieve. The
Commissioner may waive this requirement if this media performs adequately. The
finished sand surface shall be level.
5.17.d.2.C. Underdrains. Underdrains shall be
at least four inches in diameter and the spacing of them shall be not more than
20 feet apart.
5.17.d.2.D.
Partially Paved Type. The design of the partially paved drying bed shall be
with consideration for space requirement to operate mechanical equipment for
removing the dried sludge.
5.17.d.2.E. Walls. Walls shall be watertight
and extend 15 to 18 inches above and at least six inches below the surface.
There shall be curbing of outer walls to prevent soil from washing onto the
beds.
5.17.d.2.F. Sludge Removal.
There shall be not less than two beds and their arrangement shall be to
facilitate sludge removal. There shall be concrete truck tracks for all
percolation-type sludge beds.
5.17.d.2.G. Sludge Influent. The sludge pipe
to the drying beds shall terminate at least 12 inches above the surface and be
arranged so that it shall drain. There shall be concrete splash plates for
percolation-type beds at sludge discharge points.
5.17.d.2.H. Protective Enclosure. A
protective enclosure shall be considered if winter operation is
required.
5.17.d.3.
Mechanical Dewatering Facilities. There shall be a provision to maintain
continuity of service so that an applicant may dewater sludge without
accumulation beyond storage capacity. The number of vacuum filters, vacuum
beds, centrifuges, filter presses, belt filters, and other mechanical
dewatering facilities shall be sufficient to dewater the sludge produced with
the largest unit out of service. Unless other standby facilities are available,
there shall be adequate storage facilities. The storage capacity shall be
sufficient to handle at least a three-month sludge production.
5.17.d.3.A. Auxiliary Facilities for Vacuum
Filters. There shall be back-up vacuum pumps and filtrate pumps. It is
permissible to have an uninstalled back-up vacuum pump or filtrate pump for
every three or less vacuum filters, provided that the removal or replacement of
the installed unit requires little effort.
5.17.d.3.B. Ventilation. There shall be
facilities for ventilation of dewatering area. The condition of the exhaust air
shall be to avoid odor nuisance.
5.17.d.3.C. Chemical Handling Enclosures.
There shall be lime-mixing facilities of lime dust.
5.17.d.4. Drainage and Filtrate Disposal.
Drainage from beds or filtrate from dewatering units shall return to the sewage
treatment process at appropriate points.
5.17.d.5. Other Dewatering Facilities. If
proposing to dewater or dispose of sludge by other methods, a detailed
description of the process and design data shall accompany the plans.
5.18. Sewage Sludge,
Disposal Methods. When considering sewage sludge disposal methods, such as
incineration and landfill, an applicant shall follow appropriate requirements
of the solid waste regulations.
5.19. Land Application of Sewage Effluent.
5.19.a. General. Land application shall not
be considered as a treatment process, but only a means of disposing of sewage
effluent that received secondary treatment. For public health reasons, this
rule shall not permit land disposal of effluent that received primary
treatment.
5.19.b. Preliminary
Considerations.
5.19.b.1. Land application
installations are normally used where the waste contains pollutants that can
successfully be removed through distribution to the soil mantle. Removal of
these pollutants may be through organic decomposition in the vegetation-soil
complex and by absorptive, physical, and chemical reactions with earth
materials. Preliminary considerations of a site for land application shall be
the compatibility of the waste with the organic and earth materials and the
percolation rates and exchange capacity of the soils. The land application of
wastewater shall eventually recharge the local groundwater. Therefore, the
quality, direction and rate of movement, and local use of the groundwater,
present and potential, are prime considerations in evaluating a proposed
site.
5.19.b.2. It is essential to
maintain an aerated zone of at least five feet and preferably more, to provide
good vegetation growth conditions and removal of nutrients. A groundwater mound
shall develop below a disposal site after it is in use. The major factors in
design of ground disposal fields are topography, soils, geology, hydrology,
weather, agriculture practice, adjacent land use and equipment selection and
installation.
5.19.c.
Site Plan and Report. The following shall be considerations and included in a
site plan and report:
5.19.c.1. Location Maps.
USGS topographic map of the area, a 7.5-minute series where published, showing
the location of the total property and proposed land application site; and West
Virginia Division of Highways County Maps showing location of the total
property.
5.19.c.2. Plan. A
topographic map of the entire property at a workable scale showing all
buildings, land application area, area of possible expansion, roads, direction
of groundwater flow, active and abandoned wells, public water supplies,
groundwater monitoring wells, streams, wooded areas, fences or other barriers,
visible geologic formations such as sinkholes and rock outcrops, ponds, and all
structures, wells, and ponds on adjacent property within 2,000 feet of the
boundaries of proposed disposal area.
5.19.c.3. Soil Map. A soil map shall be
furnished showing soil types within the land application site. An applicant may
incorporate this information on the plan.
5.19.c.4. Report.
5.19.c.4.A. Geology of Site. This includes
formations, rock types, degree of weathering of bedrock, local bedrock
structure, character and thickness of surficial deposits, solution openings and
sinkholes or limestone areas.
5.19.c.4.B. Hydrology of Site. This means the
depth to seasonal high-water table and test well data including chemical and
bacterial analysis for groundwater quality and depth of well.
5.19.c.4.C. Soils at Site. Cation exchange
capacity of the soils, soil types and characteristics, detailed chemical
analysis of the soils and thickness of the soils.
5.19.c.4.D. Climatological Data at Site. This
includes daily rainfall and daily temperature.
5.19.c.4.E. Agricultural Practices at Site.
This includes the present and intended soil-crop management practices, kinds of
crops to be grown, harvesting frequency and ultimate use of crop.
5.19.c.4.F. Effluent Characteristics. This is
the detailed chemical analysis of effluent to dispose.
5.19.c.4.G. Rate and Frequency of
Application. This includes all calculations relating to nitrogen, cadmium and
heavy metals and calculations for winter storage.
5.19.c.4.H. Management Practices. These
include types of equipment for transport and application; supervision of site;
contracts, land easements, land leases, land purchases, monitoring procedures,
and emergency procedures in the event of plant or equipment
breakdown.
5.19.d. Design.
5.19.d.1. Effluent Requirements. Secondary
treatment shall be a requirement (30 mg/1 of BOD5 and 30
mg/1 of suspended solids). Disinfection shall be a requirement with
disinfection occurring after secondary treatment.
5.19.d.2. Holding Pond. There shall be a
minimum 90-day storage to store all flow during periods when disposal cannot
occur. All storage shall be above a fixed water level to prevent complete
draining of the pond. A two-foot residual water depth is a requirement to
prevent growth of vegetation.
5.19.d.3. Application Rates. The maximum
application rates in terms of depth of effluent are: 0.25 inch per hour; 0.5
inch per day; 2 inches per week. The above are maximum rates and lower
application rates may be necessary in some areas due to soil
characteristics.
5.19.d.4. Slopes.
There shall be a limit on cultivated fields to 4% or less. The limit of slope
on sodded fields shall be to 8% or less. The limit on forested slopes shall be
8% for year-round operation but for seasonal operation 14% slopes may be
acceptable.
5.19.d.5. Runoff. The
design of the system shall be to prevent surface runoff from entering or
leaving the project site.
5.19.d.6.
Fencing. A fence at least six feet high or a locked entrance gate shall enclose
the irrigated area to keep out children and domestic animals.
5.19.d.7. Warning Signs. Appropriate signs
shall be posted along the fence around the project boundaries to designate the
nature of the facility and advise against trespassing.
5.19.e. Spray Irrigation.
5.19.e.1. Piping to Sprinklers. The
arrangement of the piping shall be to allow the irrigation pattern to be varied
easily. For a permanent system, facilities shall be designed to allow complete
drainage of the pipes to prevent pollution and freezing, and to provide an even
distribution over the entire field.
5.19.e.2. Pump Station. There shall be
duplicate pumps for delivery to the spray field, with the capacity of each pump
sized to handle maximum rate of flow, plus an allowance to deplete stored
volumes. The pump station shall have a metering device that shall show the
total flow and rates to the irrigation field. The top of the disinfection
facility and the wet well of the pumping station shall be at least as high as
the maximum holding pond surface elevation, to prevent flooding of the units
when the spray irrigation equipment is not in operation. A control valve
between the holding pond and the spray irrigation pump station is
required.
5.19.e.3. Buffer Zone.
Sprinklers shall be located to give a non-irrigated buffer zone around the
irrigated area, and the design of the buffer zone shall consider wind transport
of the wastewaters. A fence shall be placed at least 50 feet beyond the normal
projected spray area. A minimum of 350 feet from the fence of the enclosed
irrigated area to the property lines of adjacent areas or highways is required,
unless there are:
5.19.e.3.A. Low sprays to
reduce wind transport of the effluent; or
5.19.e.3.B. Physical buffers, such as trees,
along with low sprays.
5.19.f. Ridge and Furrow.
5.19.f.1. Slopes. The construction of furrows
may be down slope on sites up to 1%. The construction of furrows shall be at
right angles to the slope on sites up to 8%.
5.19.f.2. Construction. Furrows shall be no
more than 1,000 feet in length and spaced from 20 to 40 inches apart.
5.19.g. Overland Flow.
5.19.g.1. Slopes. Slopes shall range from 2%
to 8%. Lengths of slopes shall range from 150 to 300 feet.
5.19.g.2. Construction. Slopes may be
flooded, or application made by gated pipe or spray.
5.19.h. Monitoring and Reporting. A minimum
of one drilled groundwater monitoring well shall be in each dominant direction
of groundwater movement, and between the project site and public well(s) or
high-capacity private wells, there shall be a provision for sampling at the
surface of the water table and at five feet below the water table at each
monitoring site. The Commissioner shall approve the location and construction
of the monitoring well(s) before construction. These may include one or more of
the test wells where appropriate. If crops are used for animal or human
consumption, analysis of the crop shall be required at harvest. The
Commissioner shall determine frequency of reporting on a case-by-case basis,
based on site characteristics.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.