W. Va. Code R. § 65-7-20 - Progress Reports/Extension of Certificate of Need
20.1. Any person holding a certificate of
need or who has been granted an exemption shall submit to the board, in
writing, a report on the progress being made toward completion of the approved
project according to the timetable contained in the application. The progress
report must contain a verification signed by the Chief Executive Officer and
shall be submitted at least forty-five (45) days prior to the expiration of the
certificate of need or exemption, or at any other time directed by the board.
The report shall include, at a minimum, the following:
20.1.a. The current status of the project in
relation to the timetable in the application;
20.1.b. The projected date of
completion;
20.1.c. The cause or
causes of any delays encountered;
20.1.d. Changes in the project, including any
proposed changes for which a request is made for the board to determine whether
the proposed change is reviewable as a substantial change or that an exemption
previously granted should be withdrawn and the applicant be required to obtain
a certificate of need for failure to meet the requirements of the
exemption;
20.1.e. The projected
total cost; and
20.1.f. Compliance
with any conditions of certification.
20.2. Any person holding a certificate of
need or exemption shall submit any additional information requested by the
board.
20.3. The creation of
shelled in space shall not be considered completion of the project unless
explicitly permitted in the board's decision granting the certificate of
need.
20.4. The board may not
impose new conditions which are unrelated to the representations made by the
applicant.
20.5. Any failure to
submit a complete and timely progress report is sufficient grounds for the
board to determine that any future certificate of need application is not
complete or for the board to refuse to approve any increase in rates.
20.6. The applicant shall incur an obligation
for a capital expenditure associated with an approved project or exemption
within twelve (12) months of issuance of the certificate of need or exemption,
unless the board has approved a timetable for the obligation of a series of
obligations for capital expenditures for discrete components to be incurred
over a period longer than twelve (12) months. If the board has approved a
timetable for the obligation of a series of obligations for capital
expenditures for discrete components to be incurred over a period longer than
twelve (12) months, the applicant shall incur the obligation for the first
component within twelve (12) months after the issuance of the certificate of
need or exemption.
20.7. Upon good
cause shown, the board may extend the duration of a certificate of need or
exemption for up to six (6) months. If the obligation required to be incurred
by subsection 20.6 of this rule is not incurred within eighteen (18) months of
the issuance of the certificate of need or exemption, the certificate or
exemption automatically expires.
20.8. If the obligation required to be
incurred by subsection 20.6 of this rule is incurred within the prescribed time
period, the applicant may request a renewal of the certificate of need in order
to complete the project.
20.9. If a
renewal review is underway, the board shall automatically extend the old
certificate of need until the completion of the renewal review.
20.10. The board may grant a renewal of the
certificate of need for time periods that are determined appropriate.
20.11. If a request for renewal of a
certificate of need is not made before its expiration, the certificate
automatically expires. For good cause shown, the board may waive the effect of
this subsection and permit the extension of the certificate of need during the
renewal review period.