Wis. Admin. Code Technical College System Board TCS 7.07 - Capital expenditure projects under s. 38.15, Stats
In determining whether capital expenditures for the acquisition of sites, purchase or construction of buildings or the lease/purchase of buildings exceeds $1,500,000, the following shall apply:
(1) All fixed equipment
purchased by a district for installation in or on a site or building acquired
by a district by purchase or lease/purchase, or within 2 years of the purchase
or lease/purchase, shall be considered part of the capital expenditure project
under s. 38.15, Stats.
(2) All moveable and minor equipment shall be
excluded in determining the amount of the capital expenditure project under s.
38.15, Stats.
(3) In determining whether the lease/purchase
of an existing building or the lease/purchase of a site is subject to the
limitations under s. 38.15(1),
Stats., the district shall compute the lease/purchase costs for the term of the
lease, discounted to the amount that would have been paid at the commencement
of the lease if the building or site was purchased outright.
(4) All district expenditures or proposed
expenditures for repair projects under s.
TCS 7.06(3)
(c) or remodeling and improvement projects
under s.
TCS 7.06(4)
(c) shall be considered part of a capital
expenditure project under s.
38.15, Stats.
(5) All capital expenditures on a single
campus site which are bid concurrently or which are approved by the board under
s. 38.04(10),
Stats., within 2 years shall be considered one capital expenditure
project.
(6) The board shall
designate what constitutes each single campus site.