Wis. Admin. Code Department of Transportation Trans 207.11 - Notification to department of natural resources
(1) In the early
stages of consideration of a proposed construction or reconstruction of a
highway structure in or over navigable waters, constructing authorities shall
notify the appropriate district office of the department of natural resources
of the intended construction. Such notice shall consist of a conceptual plan.
The constructing authority may request information concerning ordinary high
watermark elevation, and the navigational clearance considered appropriate for
the site and critical habitat that may be affected by the project, including
water and wetland habitat, and spawning and nesting areas. All or part of the
conceptual plan requirements may be waived by the department of natural
resources if early coordination reveals, in its opinion, that planned
activities have no adverse effect.
(2) The department of natural resources shall
have 30 days to comment and may, for good cause, request an extension of 10
days. If no response or request for extension is received within the 30-day
period, or if an extension is granted and no response is received during the 10
days, project development may proceed as planned. If environmental concerns are
noted, constructing authorities shall examine such concerns and act in such
manner as to prevent undue impairment of public rights in navigable
waters.