Wis. Admin. Code Department of Transportation Trans 29.08 - Notification of work activities
(1) NOTIFYING
DEPARTMENT AND RAILROAD OPERATOR. The utility shall notify the department and
the railroad operator at least 72 hours prior to commencing any work upon,
over, under or within the department railroad property. If a utility ceases
work on a utility facility for more than 48 hours, except for holidays or
weekends, the utility shall again give the department and the railroad operator
72 hours notice prior to recommencing the work activity. At the conclusion of
all work, the utility shall notify the department and the railroad operator
within 10 calendar days, holidays and weekends excepted, that the work is
completed. When notified, the department may, within 30 days, inspect the
completed utility facility and inform the utility whether the work is
satisfactory.
(2) EMERGENCY UTILITY
WORK. If an emergency maintenance situation arises requiring immediate action
within the department railroad property to protect the general public safety,
the utility shall immediately notify the railroad operator, or the department
when no railroad operator is in place, that an emergency exists and that the
utility is proceeding to correct the emergency situation. Emergency operations
by a utility may be performed on department railroad property whenever
conditions or time considerations prevent application to the department for
prior written approval. However, as soon as practicable, the utility shall
apply to the department for the required permit under s.
Trans
29.04.