023-3 Wyo. Code R. §§ 3-22 - Construction Reports
Each utility issued a certificate of public convenience and necessity for a specific project or extension shall:
(a) Report the date construction will
commence as soon as it is known, but no later than five business days prior to
commencement;
(b) Submit monthly
construction progress reports;
(c)
Report the date construction was completed within 20 business days of
completion; and
(d) Submit a report
no later than 180 days following completion of construction that includes:
(i) Name of project;
(ii) Date in service;
(iii) Labor costs;
(iv) Material costs by general
category;
(v) Administrative and
general expenses;
(vi) Engineering
costs;
(vii) Right-of-way
costs;
(viii) Costs and rates used
to calculate Allowance for Funds Used During Construction;
(ix) Other costs for which the utility will
seek recovery for in rates and how items (iii) through (vii) were accounted for
in its books and records;
(x)
Proposed depreciation rates;
(xi)
Journal entries transferring the completed project from Construction Work in
Progress to Utility Plant in Service by account number;
(xii) For facility modifications, journal
entries recording any plant retired and appropriate account numbers for utility
plant and reserve for depreciation;
(xiii) For facility modifications, journal
entries recording any plant salvage values and decommissioning costs or sale of
any plant retired;
(xiv) Contact
information for contractors that performed work;
(xv) Conditions (terrain, location, weather,
etc.) under which construction was performed;
(xvi) Any non-standard facility feature;
and
(xvii) Completed project maps
and engineering drawings, if changed from those previously submitted.